CITY OF SACRAMENTO
STANDARD
SPECIFICATIONS
FOR PUBLIC CONSTRUCTION
November 2020
STANDARD
SPECIFICATIONS
FOR PUBLIC CONSTRUCTION
City of Sacramento
California
Adopted by City Council
November 2020
TABLE OF CONTENTS
Section Title Pages
Section 1 Definitions and Terms 1-1 to 1-6
Section 2 Bid/Proposal Requirements and Conditions 2-1 to 2-6
Section 3 Award and Execution of Contract 3-1 to 3-3
Section 4 Scope of Work 4-1 to 4-8
Section 5 Control of Work and Materials 5-1 to 5-12
Section 6 Legal Relations and Responsibilities to the Public 6-1 to 6-17
Section 7 Prosecution and Progress 7-1 to 7-7
Section 8 Measurement and Payment 8-1 to 8-7
Section 9 Reserved 9-1
Section 10 Construction Materials 10-1 to 10-55
Section 11 Preconstruction Photographs 11-1 to 11-2
Section 12 Clearing and Grubbing, Tree Removal 12-1 to 12-2
Section 13 Existing Facilities 13-1 to 13-5
Section 14 Earthwork, Excavation, Embankment and Sub-grade 14-1 to 14-8
Section 15 Water Used in Construction 15-1 to 15-2
Section 16 Water Quality Control 16-1 to 16-6
Section 17 Laying Aggregate Base 17-1 to 17-3
Section 18 Headers 18-1 to 18-2
Section 19 Portland Cement Concrete Pavement, Joints and Curing 19-1 to 19-4
Section 20 Concrete in Structures 20-1 to 20-15
ii
TABLE OF CONTENTS
Section Title Pages
Section 21 Placing Steel Reinforcement 21-1 to 21-4
Section 22 Asphaltic Concrete 22-1 to 22-11
Section 23 Bituminous Seal 23-1 to 23-13
Section 24 Curbs, Gutters, and Sidewalks 24-1 to 24-5
Section 25 Sanitary Sewer and Drainage Manholes 25-1 to 25-7
Section 26 Laying Sewer and Drain Pipe 26-1 to 26-24
Section 27 Water Distribution Systems 27-1 to 27-37
Section 28 Driveway Culvert and Sidewalk French Drains 28-1 to 28-3
Section 29 Moving or Changing Utilities and Water Services 29-1
Section 30 Drain Inlets, Gutter Drains and Ditch Boxes 30-1
Section 31 Construction of Chain Link Fence 31-1 to 31-2
Section 32 Traffic Signs, Markings and Barricades 32-1 to 32-10
Section 33 Pneumatically Applied Mortar 33-1 to 33-4
Section 34 Electrical 34-1 to 34-15
Section 35 Landscape Planting 35-1 to 35-24
Section 36 Irrigation System 36-1 to 36-8
Section 37 Boring and Jacking 37-1 to 37-6
Section 38 Standard Drawings 38-1 to 38-10
Index i-1 to i-14
1-1
Section 1
DEFINITIONS AND TERMS
Unless expressly indicated otherwise, the following terms or abbreviations used
in these Specifications, or in any other Contract Documents, are defined as follows:
1-1 “A.A.S.H.T.O.” The American Association of State Highway and
Transportation Officials.
1-2 “Addendum” means a document issued prior to the execution of the
Agreement, that modifies or interprets any of the Contract Documents,
by additions, deletions, clarifications, or corrections.
1-3 “Agreement” means the written agreement executed by Contractor and
City, that constitutes one of the Contract Documents.
1-4 “A.S.T.M.” The American Society for Testing Materials.
1-5 “A.W.W.A.” The American Water Works Association.
1-6 “Bidmeans a response to a request or invitation for bids or proposals. A
“formal” Bid means a Bid submitted for a Contract required to be awarded
by the Sacramento City Council pursuant to the Sacramento City Code,
and “formal” bidding means the bidding process used for such Contracts.
1-7 “Bid Form” means the approved form upon which the City requires formal
Bids for the Work to be prepared and submitted.
1-8 “Bid Security” means the bid security furnished by the Bidder as a
guarantee of good faith that it will enter into a Contract and execute the
required Bonds covering the Work if awarded the Contract.
1-9 “Bidder” means any individual, partnership, corporation, or other entity
or combination thereof, submitting a Bid, whether acting directly or
through a duly authorized representative.
1-10 “Change Order” means an amendment to a Contract issued after the
effective date of the Contract.
1-11 “City” means the charter municipal corporation known as the City of
Sacramento, in the State of California.
1-2
1-12 “City Council” means the City Council of the City of Sacramento or any
other board, body, official or officials, to which or to whom the power
belonging to the City Council may pass.
1-13 “City Manager” means the City Manager of the City of Sacramento acting
either directly or through properly authorized representatives acting
within the scope of their authorized duties.
1-14 “Completion Date” means the date for completion of the entire Work as
defined in Section 9 of the Agreement.
1-15 “Contract” shall mean the written Contract Documents covering the
performance of the Work including the furnishing of labor, materials,
tools, and equipment.
1-16 “Contract Documents” means the various documents that make up the
Contract, which are identified in Section 1 of the Agreement.
1-17 “Contract Price” means the total dollar amount of the Contract.
1-18 "Contractor” means the individual, partnership, corporation, or other
entity or combination thereof, or its duly authorized representative, that
has entered into a Contract with the City.
1-19 “Controlling Operation” means an item of Work on the project’s critical
path whose duration time directly affects the date that the entire Work
can be completed.
1-20 “Critical Path Method Schedule” or “CPM Schedule” means a schedule
with a consecutive sequence for completion of the Work with the least
amount of float period(s).
1-21 “Day” means a working day, unless otherwise expressly defined in the
Special Provisions.
1-22 “Date of signing” means the date upon which the Contract, properly
executed by Contractor and delivered to the City, was executed by the
City.
1-23 “Director” means the Director of the City Department administering the
Contract.
1-24 “Division Manager” means the Division Manager of the City department
and division administering the Contract, or other City employee
1-3
designated by such Division Manager to perform any duties assigned to the
Division Manager in these Specifications.
1-25 “Engineer” means the Director, the Director’s subordinates, or other City
representative(s) who have been duly authorized to exercise control and
supervision of the Work. The Engineer typically is, but is not required to
be, either a professional engineer architect, or landscape architect,
depending on the nature of the Work.
1-26 “Federal Specifications” means the Standard Specifications of the United
States Government designated in the Contract Documents.
1-27 “Field Order” means a written instruction from the Engineer to
Contractor made in the field.
1-28 “Finance Director” means the Director of the Department of Finance of
the City of Sacramento and includes the “City Controller” as used in the
Sacramento City Charter.
1-29 “Fixed cost” means a cost that remains constant regardless of the
quantity of work done.
1-30 “Float period” means such period(s) of time as may be shown on
Contractor’s schedule(s) that are not allocated to the performance and
completion of the Controlling Operation(s) of the Work.
1-31 “Inspector” means an engineering or construction inspector acting within
the authorized scope of the particular duties and authority delegated to
such inspector by the City.
1-32 “Laws or Regulations” means any and all applicable laws, rules,
regulations, ordinances, codes, resolutions, requirements and/or orders
of any and all governmental bodies, agencies, authorities and courts,
including but not limited to provisions of the Sacramento City Charter and
City Code.
1-33 “LBE participation” means participation in performance of the Work by
Local Business Enterprises in accordance with the provisions of Article VIII
of Chapter 3.60 of the Sacramento City Code and the policies and
procedures adopted to implement those provisions.
1-34 “Liquidated damages” means the sum or sums prescribed in the Contract
Documents, pursuant to the authority of Government Code Section
53069.85, to be paid to the City or to be deducted from any payment due
or to become due to Contractor for delay beyond the time allowed in the
1-4
Contract Documents for completing the whole, or any specified portion,
of the Work.
1-35 “Landscape Architect” means a Landscape Architect of the City of
Sacramento assigned to the Work.
1-36 “Payment Bond” has the same meaning as in Section 3096 of the California
Civil Code, and refers to the approved form of security furnished by
Contractor and its Surety to guarantee the payment in full of all bills,
accounts and related costs for labor and materials used in construction of
the Work.
1-37 “Performance Bond” means the approved form of security furnished by
Contractor and its Surety to guarantee Contractor’s performance and
completion of the Work in accordance with the terms of the Contract.
1-38 “Plans” means the official Project Plans and Standard Drawings, profiles,
typical cross sections, general cross sections, working drawings and
supplemental drawings, or reproductions thereof, approved by the
Director, that show the location, character, dimensions and details of the
work to be performed. All such documents are part of the Plans whether
or not reproduced in the Special Provisions. In this definition, the terms
“Standard Drawings” and “Project Plans” mean:
(1) “Standard Drawings”: The Standard Drawings or Standard Drawing as
set forth in these Specifications. “Standard Drawing(s)” means
“Standard Detail(s)”.
(2) “Project Plans”: The Project Plans or Plans include specific details and
dimensions peculiar to the Work and that are supplemented by the
Standard Drawings as they may apply.
1-39 “Project Estimate” means the list of estimated quantities of Work to be
performed that is included in the Notice to Contractors
1-40 “Proposal” means the offer of the Bidder, including a Bid, for performance
and completion of the Work when properly completed, executed,
guaranteed and submitted on the Bid form.
1-41 “Special Provisions” means the specific clauses setting forth conditions or
requirements peculiar to the Work and supplementary to these
Specifications.
1-42 “Specifications” means the directions, provisions, and requirements
contained herein. In the Contract Documents, including the Special
1-5
Provisions, these Specifications may also be referred to as the “Standard
Specifications”.
1-43 “State Specifications” means the Standard Specifications of the State of
California, Department of Transportation, as currently approved and in
effect and as thereafter amended or renumbered.
1-44 “Subcontractor” means any person or firm of any tier directly or indirectly
utilized by Contractor to perform any portion of the Work.
1-45 “Substantially complete” means that the Engineer has determined that all
of the Work has been performed, but there are minor deficiencies, as
determined by the Engineer, that do not prevent the Work from being
fully functional nor pose any risk to the public health, safety or welfare
or public or private property, as determined by the Engineer. The Work
shall be considered substantially complete on the date that the Engineer
issues a punch list to Contractor as specified in Section 8-4 of these
Specifications.
1-46 “Supplier” means any person or firm directly or indirectly supplying any
materials or equipment for performance of, or incorporation in, the Work.
1-47 “Work” means all actions and activities that Contractor is contractually
required to undertake and perform as specified, indicated, shown, or
implied in the Contract, including all duly authorized Change Orders.
1-48 “Working day” means any day, except for the following:
(1) Saturdays, Sundays and legal holidays, unless otherwise indicated in
the Special Provisions.
(2) Days on which Contractor is prevented from proceeding with the
current Controlling Operation(s) of Work for at least (5) hours per day
due to inclement weather, or conditions resulting immediately
therefrom, as determined by the Engineer.
(3) Days on which Contractor is specifically required pursuant to the
Contract Documents or by operation of law to suspend the Controlling
Operation or Operations of Work, except in cases where such
requirement applies due to the failure on the part of Contractor or any
Subcontractor to carry out orders or to perform any provision of the
Contract.
2-1
Section 2
BID/PROPOSAL REQUIREMENTS AND CONDITIONS
2-1 NOTICE TO CONTRACTORS
“Notice to Contractors” is published by the City Clerk for formally bid
contracts in accordance with Article III of Chapter 3.60 of the Sacramento City
Code. Among other provisions, the Notice to Contractors makes reference to
Section 1770 et seq. of the Labor Code relating to determinations regarding
prevailing wages. Contractor shall pay prevailing wages according to the rates
established by these determinations. Copies of these determinations are on file
in the Office of the Director and shall be made available to any interested party
on request, and also may be retrieved from the internet at www.dir.ca.gov/dlsr.
A summary of the labor compliance requirements will be presented at
the pre-construction meeting. Each contractor and subcontractor (at all
levels/tiers) is required to submit certified payrolls and labor compliance
documentation electronically at the discretion of and in the manner specified
by, the City of Sacramento.
Electronic submittal will be through a web-based system, accessed on
the World Wide Web by a web browser.
Use of the system may entail additional data entry of weekly payroll
information including; employee identification, labor classification, total
hours worked and hours worked on this project, wage and benefit rates paid,
etc. The contractor’s payroll and accounting software may be capable of
generating a ‘comma delimited file’ that will interface with the software. If
the ‘comma delimited file’ option does not work, it is still the responsibility
of the contractor and subcontractors to manually enter their data into the
system specified by City of Sacramento, meeting the required deadlines for
those documents.
Every lower-tier subcontractor and vendor is required to provide labor
compliance documentation.
2-2 BID FORM
A Bid Form shall be made available to each prospective Bidder.
2-2
2-3 PROJECT ESTIMATE
The quantities included in the Project Estimate in the Notice to
Contractors, Bid Form and Contract are approximate only, and are given as a
basis for comparison of Bids. The City does not, expressly or by implication,
represent or agree that the actual amount of Work will equal the approximate
estimate. The City reserves the right to increase or decrease the amount of any
class or portion of the Work, or to omit portions of the Work, as may be deemed
necessary or advisable in the sole discretion of the Engineer, as provided in the
Contract Documents.
2-4 EXAMINATION OF CONTRACT DOCUMENTS AND SITE OF WORK
All Bidders shall carefully inspect the site of the contemplated Work, and
carefully review the Plans, Specifications, the Proposal and the other Contract
Documents. The submission of a Bid is conclusive evidence that the Bidder has
investigated and is satisfied as to the conditions to be encountered, the
character, quality, quantity and scope of Work to be performed, the quantities
of materials to be furnished, and the requirements of the Contract Documents,
and that the Bidder is aware of no material discrepancy between such conditions,
the character, quality, quantity and scope of Work to be performed, the
quantities of materials to be furnished, and the requirements of the Contract
Documents. If the Engineer has made investigations of conditions in areas where
the Work is to be performed or in other areas, some of which may constitute
possible local material sources, such investigations are made only for the purpose
of study and design. Subject to and upon the conditions set forth below, where
such investigations have been made, prospective Bidders or Contractor may,
upon written request, inspect the records of such investigations. Any inspection
of the records shall be made at such place or places that may be specified in the
Special Provisions or by the Engineer.
The records of such investigations are not part of the Contract and are
shown solely for the convenience of prospective Bidders or Contractor. The
Engineer and the City assume no responsibility whatsoever in respect to the
sufficiency or accuracy of such investigations, the records of the investigation,
or any interpretation in the investigation or made by the Engineer and that there
is no representation, warranty or guarantee, either express or implied, that the
conditions indicated by such investigations or records of the investigations are
representative of those existing throughout such areas, or any part thereof, or
that unanticipated developments may not occur, or that materials other than or
in proportion different from those indicated, may not be encountered.
The availability for use of information described in this Section is not a
waiver of the provisions of the first paragraph of this Section and all prospective
Bidders and Contractor are cautioned to make such independent investigations
2-3
and examinations as each of them may consider necessary to sufficiently inform
itself as to the conditions to be encountered in the performance of the Work,
and, with respect to possible local material sources, the quality and quantity of
material available from such sources and the type and extent of processing that
may be required in order to produce material conforming to the requirements of
the Contract. No information derived from such inspection of records of
investigations or interpretations made by the Engineer relieves any prospective
Bidder or Contractor from any risk or from properly fulfilling the terms of the
Contract.
2-5 PREPARATION OF PROPOSAL
Bid Forms and the plans and specifications are available on the City’s
website. Bids not presented on the Bid form shall be rejected.
Proposals must set forth in clearly legible figures, an item price and a
total for each item in the respective spaces provided, and must be signed by the
Bidder, who shall fill out all blanks in the Bid Form.
2-6 DETERMINATION OF AMOUNT BID MATHEMATICAL ERROR
In determining the amount bid by each Bidder, the City may disregard
computations that contain obvious mathematical errors in addition, subtraction,
multiplication, and division that appear on the face of the Proposal. When such
a computational error appears on the face of the Proposal, the City may, but is
not obligated to correct any such error and compute the total amount bid by said
Bidder on the basis of the corrected figure or figures to determine which Bidder
has submitted the lowest bid. However, the City has no responsibility or liability
to any bidder if the City determines which Bidder has submitted the lowest bid
without doing so.
When an item price is required to be set forth in the Proposal, and the
total price for the item is not consistent with the figure that is derived by
multiplying the item price by the Project Estimate of the quantity of work to be
performed for said item, the item price shall prevail over the total price for the
item. The total to be paid for each item shall be based upon the item price and
not the total price for the item. If the Proposal contains only a total price for
the item, and not the item price, the City shall determine the item price by
dividing the total price for the item by the stated Project Estimate of the
quantity of work to be performed for the item.
If the Proposal contains neither the item price nor the total price for the
item, then it shall be deemed non-responsive and will be rejected.
2-4
2-7 REJECTION OF PROPOSALS
Proposals may be rejected if they show any alteration of form, additions
not called for, mathematical errors, conditional Bids, changes that make the
Proposal illegible, or contain irregularities.
When Proposals are signed by an agent, other than an officer or officers
of the corporation authorized to sign contracts on its behalf or a member of a
partnership, a “power of attorney” must be filed with the City of Sacramento
prior to opening Bids or submitted with the Proposal; otherwise, the Proposal
shall be rejected as non-responsive. The City reserves the right to waive any
informalities or minor irregularities in the Bids.
2-8 BID SECURITY
All Bids shall be accompanied by one of the following forms of Bidder’s
security: Cashier’s check, a certified check, or a Bidder’s Bond executed by a
surety insurer admitted and duly authorized to transact business in the State of
California, made payable to the City.
No Bidder’s Bond shall be accepted unless it substantially conforms to the
Bond form included in the Special Provisions. Bidder’s Bond forms may be
obtained from the Engineer. The Engineer may waive the requirement to furnish
Bid Security for Contracts that may be awarded without City Council approval
pursuant to the Sacramento City Code.
2-9 SUBCONTRACTORS
Each contractor or subcontractor performing any work for the City of
Sacramento, must be currently registered with the California Department of
Industrial Relations (DIR), as specified in Labor Code Section 1725.5. Labor Code
Section 1771.1 (enacted by SB 854) provides that a Contractor or subcontractor
is not qualified to bid on, or be listed in a Proposal (subject to the requirements
of Section 4104 of the Public Contract Code), or engage in the performance of
any Work, unless currently registered and qualified pursuant to Labor Code
Section 1725.5.
In addition, each Bidder and each Contractor shall, to the extent required
by law, comply with to the Subletting and Subcontracting Fair Practices Act of
the State of California (Public Contract Code Sections 4100 et seq.) and shall, in
the Bid, on a form provided by the City, set forth:
1. The name and location of the place of business and the California
contractor license number for each proposed Subcontractor who shall
perform work or labor or render service to the prime Contractor in or
2-5
about the construction of the Work, or a Subcontractor licensed by the
State of California who, under a subcontract to the prime Contractor,
specially fabricates and installs a portion of the Work or improvement
according to detailed drawings contained in the Plans and Specifications,
in an amount in excess of one-half of one percent of the prime
Contractor’s total bid or, in the case of bids for the construction of streets
or highways, including bridges, in excess of one-half of one percent of the
prime Contractor’s total bid or $10,000, whichever is greater.
2. The portion and dollar amount of the work that will be done by
each such Subcontractor. The prime Contractor shall list only one
Subcontractor for each such portion as is defined by the prime
Contractor in the Bid.
3. Every Bidder shall list the Contractor’s current DIR registration
number and the current DIR registration number of all listed
subcontractors, on the Subcontractor and Local Business Enterprise
(LBE) Participation Verification Form included in the contractor’s
bid.
In addition to the above requirements, Contractor shall perform with its
own organization and with the assistance of workers under its immediate
superintendence, work of a value not less than twenty percent (20%) of the value
of all Work in the Contract. The dollar amount of subcontracted work that is
specifically indicated by the Bidder on the form provided by the City shall be
used to determine the value of work being subcontracted, as well as the value
of LBE Subcontractor participation for purposes of determining compliance with
LBE participation requirements, unless the Engineer determines such value to be
significantly misstated. The Bidder shall provide such bidding information as may
be requested by the Engineer to make this determination.
2-10 SUBMISSION OF PROPOSAL
The Proposal shall be submitted as directed in the Notice to Contractors
in a sealed envelope provided by the City. The Bidder shall plainly mark the
exterior of the envelope in which the Proposal is submitted to indicate that it
contains a proposal for the project for which the proposal is submitted, and the
date of the Bid opening therefor. Proposals submitted in envelopes that are not
properly marked may be rejected. The Proposal cannot be withdrawn or
modified after the time specified for opening of the Bids, except as may be
authorized under Section 2-12 below.
2-6
2-11 PUBLIC OPENING OF PROPOSALS
Proposals shall be opened and read publicly at the time and place
indicated in the Notice to Contractors. Bidders or their authorized agents may
be present.
2-12 RELIEF OF BIDDERS
A Bidder may request relief from its Bid, pursuant to the provisions of
Public Contract Code Section 5100 et seq.
2-13 DISQUALIFICATION OF BIDDERS
City shall not consider more than one Proposal from an individual,
partnership, corporation, or other entity or combination thereof, under the same
or different names. If City has reasonable grounds to believe that any individual,
partnership, corporation or combination thereof is interested in more than one
Proposal as a prime Bidder for the work contemplated, City may reject all
Proposals in which such individual, partnership, corporation or combination
thereof is interested. If City has reason to believe that collusion exists among
any Bidders, City may reject the Proposals. City may reject a Proposal in which
the bid(s) submitted for one or more items are obviously unbalanced, as
reasonably determined by City.
2-14 LICENSING OF BIDDERS
All Bidders and Contractors shall be licensed in accordance with the laws
of California and any Bidder or Contractor not so licensed is subject to the
penalties imposed by such laws. The Bidder’s or Contractor’s license must be of
a class that permits its holder to do the Work contemplated as of the date the
Proposal is submitted and such license must be maintained for the duration of
the work. The Bidder shall indicate its license number and class in the space
provided for that purpose on the Bid Form.
The City shall specify the classification of license that a Contractor must
possess at the time a Contract is awarded. This shall be included in the Plans
and Notice to Contractors (Public Contract Code Section 3300).
2-15 PREQUALIFICATION OF BIDDERS
The City may establish prequalification requirements for Bidders on one
or more Contracts consistent with applicable provisions of the City Code, and
other applicable laws or regulations. The City may establish prequalification
requirements for Bidders on one or more Contracts consistent with applicable
provisions of the City Code, and any other Laws or Regulations if applicable.
2-7
2-16 JOINT VENTURE BIDS
If two or more prospective Bidders desire to bid as a joint venture on a
project, the prospective Bidders must first file an affidavit of joint venture with
the City on a form approved by the Engineer. The affidavit of joint venture is
valid only for the specific project for which it is filed. If an affidavit of joint
venture is not filed and approved by the Engineer prior to Bid opening, the joint
bid shall be rejected. On projects for which pre-qualification is required, each
party to the joint venture must separately pre-qualify in order to file a joint
venture affidavit. Joint venture bidders must comply with the California
Business and Professions Code, sections 7029 and 7029.1. A joint venture is not
required to have a current DIR registration number until after contract award,
so long as the prospective partners in the joint venture each have current DIR
registration numbers at the time of Bid opening. And a joint venture shall not be
qualified as a Local Business Entity unless the prospective partners in the joint
venture would separately qualify as Local Business Entities at the time of bid
opening.
2-17 AGREEMENT TO ASSIGN
If a Bid is accepted, the Bidder will assign to City all rights, title, and
interest in and to all causes of action it may have under Section 4 of the Clayton
Act (15 U.S.C. Sec. 15) or under the Cartwright Act, Chapter 2 (commencing with
Section 16700) of Part 2 of Division 7 of the Business and Professions Code),
arising from purchases of goods, materials, or services by the Bidder pursuant to
the Contract. The assignment is effective at the time the City tenders final
payment to the Bidder without further acknowledgement by the parties (Cal.
Govt. Code §4552).
2-18 COMMUNITY WORKFORCE TRAINING AGREEMENT COMPLIANCE
If the Engineer’s estimate for a project or the actual Contract awarded
exceeds $1,000,000, the City’s Local Hire and Community Workforce Training
Program and the City’s Community Workforce Training Agreement (CWTA) apply.
By submitting a Proposal for such a project, the Contractor acknowledges
that it has read and understands all the requirements, terms, and conditions of
the CWTA and CWTA Summary attached to the request or invitation for bids or
proposals (or otherwise available from the City), and has included all costs
associated with compliance with the CWTA in its Bid.
If the CWTA applies, the Contractor must execute Addendum A to the
CWTA (“Agreement to be Bound”) and provide an executed original to the City
before the Contract can be awarded. Each subcontractor for Work covered by
the CWTA, including subcontractors not listed at the time of bid or otherwise
2-8
hired after contract award, must also execute Addendum A to the CWTA. No
Contractor or subcontractor may perform Work prior to executing Addendum A
and providing the executed original to the City. The failure to sign and submit
Addendum A by the Contractor, shall be grounds for awarding the Contract to
another bidder. The failure to sign and submit Addendum A by any subcontractor
shall be grounds for subcontractor substitution and/or for the City to withhold
payment for the Work performed in the absence of the necessary Addendum A.
Contractor must include the provisions of this section, as well as a copy
of the CWTA and the CWTA Summary, in every subcontract for Work covered by
the CWTA. By submitting a bid, Contractor represents that if the bid amount
exceeds $1,000,000, the Contractor and all its subcontractors performing Work
covered by the CWTA will execute the Agreement to be Bound if awarded the
contract.
The failure to submit an Addendum A or to otherwise comply with the
requirements of the CWTA on this project may also result in a future
determination that the Contractor and/or subcontractor is not responsible
(pursuant to City Code section 3.60.020) when bidding on future projects for the
City of Sacramento.
3-1
Section 3
AWARD AND EXECUTION OF CONTRACT
3-1 AWARD OF CONTRACT
Unless otherwise provided in the Special Provisions, or otherwise
authorized by the City Council in accordance with applicable provisions of the
Sacramento City Code, the award of a formally bid Contract, if it is awarded, will
be to the lowest responsible Bidder (as defined in section 3.60.020 of the
Sacramento City Code) whose Bid complies with the specific requirements of the
Contract Documents. The City Council reserves the right to reject any and all
Proposals.
3-2 TIME OF AWARD
The award of a formally bid Contract, if made, will be made within sixty
(60) calendar days after the opening of the Proposals.
If the lowest responsible Bidder refuses or fails to execute the Contract,
the City Council may award the Contract to the second lowest responsible Bidder.
Such award, if made, will be made within ninety (90) calendar days after the
opening of Proposals.
If the second lowest responsible Bidder refuses or fails to execute the
Contract, the City Council may award the Contract to the third lowest
responsible Bidder. Such award, if made, will be made within one hundred and
twenty (120) calendar days after the opening of the Proposals.
The periods of time specified above within which the award of the
Contract may be made, may be extended by written agreement between the
Engineer and the applicable Bidder.
3-3 COMPARISON OF BIDS
All Bids shall be compared on the basis of the Project Estimate of
quantities of Work to be done, with such corrections in mathematical errors
appearing on the face of the Proposal as the City may choose to make pursuant
to Section 2-6 of these Specifications.
3-4 PERFORMANCE AND PAYMENT BONDS
The successful Bidder shall provide Performance and Bonds to the City,
each for a sum equal to one hundred percent (100%) of the Contract Price. Each
3-2
Bond shall be executed by a surety insurer admitted and duly authorized to
transact business in the State of California. If the Contract Price is increased by
Change Order, Contractor shall increase the Performance and/or Payment Bond
amount(s) if and to the extent required by the Engineer.
Notwithstanding the foregoing, for any Contract awarded for a Contract
Price of $25,000.00 or less, no Performance Bond or Payment Bond is required
unless specifically required in the Special Provisions, except as otherwise
required by any laws or regulations.
3-5 RETURN OF BID SECURITY
After bids have been received and reviewed, Bid Security will be returned
to the respective Bidders except those submitted by the three lowest responsible
Bidders. The Bid Security of the three lowest responsible Bidders will be returned
after the Contract is executed, subject to the provisions of Section 3-7 below.
3-6 EXECUTION OF CONTRACT
The Contract shall be executed by the successful Bidder and returned to
the City together with the Performance and Payment Bonds, not later than
fifteen (15) calendar days after the date the Contract is awarded.
3-7 FAILURE TO EXECUTE CONTRACT
Failure of the lowest responsible Bidder, the second lowest responsible
Bidder, or the third lowest responsible Bidder to execute a formally bid Contract
and file acceptable Bonds and insurance as provided in the Contract Documents
shall be just cause for the City Council to void the Contract award to that Bidder
and utilize that Bidder’s Bid Security to recover the City’s cost as provided
below.
If the lowest responsible bidder refuses or fails to execute the Contract
as required herein, the City Council may award the Contract to the second lowest
responsible Bidder. If this occurs, the amount of the lowest responsible Bidder’s
Bid Security shall be applied by the City to the difference between the lowest
Bid and the Bid of the second lowest responsible Bidder and the surplus, if any,
shall be returned to the lowest responsible Bidder if a check is used, or shall be
credited to the surety on the Bidder’s Bond if a Bond is used.
On refusal or failure of the second lowest responsible Bidder to execute
the Contract, the City Council may award the Contract to the third lowest
responsible Bidder. If this occurs, in addition to application of the lowest
Bidder’s Bid Security as provided above, the amount of the second lowest
responsible Bidder’s Bid Security shall be applied by the City to the difference
3-3
between the second lowest Bid and the Bid of the third lowest responsible
Bidder, and the surplus, if any, shall be returned to the second lowest responsible
Bidder if a check is used, or credited to the surety on the second lowest Bidder’s
Bond if a Bond is used.
The successful Bidder may file with the Engineer a written notice, signed
by the Bidder or its authorized representative, specifying that the Bidder will
refuse to execute the Contract if presented. The filing of such notice shall
immediately have the same force and effect as the failure or refusal of the
Bidder to execute the Contract and furnish acceptable Bonds within the time
prescribed above.
3-8 FORM OF AGREEMENT AND SURETY BONDS
The form of the Agreement and the form of the Payment and Performance
Bonds required to be executed by the successful Bidder shall be approved by the
City Attorney.
4-1
Section 4
SCOPE OF WORK
4-1 INTENT OF PLANS AND SPECIFICATIONS
The intent of the Plans and Specifications is to prescribe the details for
the completion of the Work that Contractor undertakes to perform in accordance
with the terms of the Contract. Where the Plans and Specifications describe
portions of the Work in general terms, but not in complete detail, it is understood
that only the best general practice is to prevail and that only materials and
workmanship of the best quality shall be used. Unless otherwise specified,
Contractor shall furnish all labor, materials, tools, equipment, and incidentals,
and do all the Work involved in executing the Contract in a satisfactory and
workmanlike manner.
4-2 CLEANING UP
Contractor shall not allow the site of the Work to become littered with
trash, debris, garbage or waste material, and shall maintain the site in a neat,
orderly, safe and healthful condition until completion and acceptance of the
Work. Before final inspection of the Work, Contractor shall clean the work site
and all ground occupied by Contractor in connection with the Work of all rubbish,
excess materials, falsework, temporary structures and equipment. All parts of
the Work shall be left in a neat and presentable condition. Contractor shall
implement a program of proper cleaning and “housekeeping” practices,
employee training and other measures as needed to consistently maintain a clean
Work site and shall at all times take all measures necessary to protect work in
place and materials and equipment stored on site from contamination by dust,
dirt, debris or mold. Full compensation for cleaning up and protection of work,
materials and equipment is included in the prices paid for the various Contract
items of work, and no separate or additional payment shall be made for cleaning
up and protection of work, materials and equipment.
4-3 LINES AND GRADES
All Work done under this Contract shall be done to the lines and grades
shown on the drawings. Contractor shall keep the Engineer informed, at least 2
working days in advance, of the times and places at which Contractor wishes to
do work, in order that lines and grades may be furnished and necessary
measurements for record and payment made with the minimum of inconvenience
to the Engineer and delay to Contractor.
4-2
The datum to which all elevations mentioned herein or shown on the
drawings refer is the official datum of the City of Sacramento, unless specifically
shown or stated to be otherwise.
4-4 CHANGES IN THE WORK
The City reserves the right to make such alterations, deviations, additions
to or deletions from the Work or any of the Contract Documents, including the
right to increase or decrease the quantity of any item or portion of the Work or
to eliminate any item or portion of the Work, as may be deemed necessary or
advisable by the Engineer, and to require such extra work as may be determined
by the Engineer to be necessary for the proper completion or construction of the
whole Work.
Any such changes shall be set forth in a Change Order that shall specify,
in addition to the work to be done or omitted in connection with the change
made, the adjustment of Contract time, if any, and the increase or decrease in
Contractor’s compensation, if any, for that work. A Change Order issued by the
Engineer shall not be deemed approved and effective until signed by Contractor
(or otherwise deemed approved by Contractor as provided in this Section) and
approved by the City in accordance with applicable approval requirements of the
Sacramento City Code. The City’s payment in accordance with the provisions for
compensation set forth in an approved Change Order shall constitute full
compensation for all work included in or required by the Change Order, including
all direct, indirect and consequential costs incurred or claimed by the
Contractor.
Contractor may contest the terms or conditions of a Change Order issued
by the Engineer by submitting a written protest to the Engineer within 15
calendar days after Contractor’s receipt of such Change Order. The protest shall
state the points of disagreement, the applicable Contract Document references,
and the quantities and costs involved. If a written protest is not submitted within
the 15 calendar day period; (1) payment shall be made as set forth in the Change
Order, and Contractor shall not be entitled to any additional compensation for
all work included therein or required thereby; and (2) the Change Order shall be
deemed to have been approved and executed by Contractor.
Upon receipt of an approved Change Order, Contractor shall proceed with
the ordered work. In those instances where the Work would be delayed by
waiting for City to issue and/or approve a Change Order, the Engineer may direct
work to be done by issuing a written Field Order, and Contractor shall proceed
with the work so ordered prior to actual receipt of an approved Change Order.
In those cases, the Engineer shall, as soon as practicable, issue a Change Order
for the ordered work.
4-3
Increases or decreases in the quantity of a unit price bid item of Work
shall be determined by comparing the total quantity of that item of Work with
the bid quantity. If the total quantity of a unit price bid item of Work is
increased, the Engineer shall determine in the Engineer’s sole discretion whether
to pay for the additional quantity of the item (i) at the Contract unit price for
the item, (ii) at a different unit price or in a lump sum, if such price or sum is
agreed to by Contractor, or (iii) by cost and percentage, as provided in Section
8-10 below. If the total quantity of any item of Work required under the Contract
is decreased, the Engineer shall determine the reduction in compensation for the
item based on the Contract unit price for the item; provided that if the
compensation for any “major item” (defined below) is reduced by more than 20%
of the cost bid for that item, the Engineer may agree to pay Contractor for lost
overhead resulting from such reduction, if any, as determined by the Engineer
in the Engineer’s sole discretion; provided, further, that if the Engineer
eliminates in its entirety an item of the Work, the reduction in compensation
therefore shall be determined in accordance with Section 4-5 below.
As used in this Section and Section 4-5, “major item” means an item of
the Work with a cost, computed on the basis of the bid quantity for the item,
that exceeds the following percentages of the Contract price:
1. 10 % of the original Contract price, for Contracts originally awarded for a
price of less than one million dollars.
2. 8 % of the original Contract price, for Contracts originally awarded for a
price of at least one million dollars but less than five million dollars.
3. 6 % of the original Contract price, for Contracts originally awarded for a
price of at least five million dollars but less than ten million dollars.
4. 5 % of the original Contract price, for Contracts originally awarded for a
price of ten million dollars ($10,000,000.00) or more.
For extra work that does not constitute an increase of a unit price bid
item of the Work, the Engineer shall determine, in the Engineer’s sole discretion,
whether to pay for the extra work (i) at a unit price or lump sum agreed to by
Contractor, or (ii) by cost and percentage, as provided in Section 8-10.
4-5 ELIMINATED ITEMS
Notwithstanding any other provision of the Contract Documents, the
Engineer may at any time, in writing, entirely eliminate any item(s) of the Work
if the Engineer determines, in the Engineer’s sole discretion, that the item is
4-4
unnecessary to the project or will be performed by the City’s own personnel.
Any elimination of Work is not a waiver or invalidation of any of the conditions
or provisions of the Contract. If any item of Work is entirely eliminated,
Contractor shall not receive any compensation for the eliminated item, except
for actual costs incurred in connection with the eliminated Contract item if
reasonably incurred prior to the date of notification in writing by the Engineer
of the elimination. The payment by City for actual costs reasonably incurred by
Contractor, if any, prior to elimination of an item as provided in this Section
shall be computed in the same manner as if the work were to be paid by cost
and percentage as provided in Section 8-10 of these Specifications. In addition,
if any major item is entirely eliminated, the Engineer may agree, in the
Engineer’s sole discretion, to pay Contractor for lost overhead resulting from the
elimination.
If material acceptable to the City is ordered by Contractor for the
eliminated item prior to the date of notification of the elimination by the
Engineer, and if orders for that material cannot be canceled, the material shall
be paid for at the actual cost to Contractor. If so, the material paid for shall
become the property of the City. If the material is returnable to the vendor and
if the Engineer so directs, the material shall be returned and Contractor shall be
paid for the actual cost of charges made by the vendor for returning the material.
4-6 EXTRA WORK
Work is considered extra work only when the Engineer determines that
the work is not covered by any of the various items for which there is a bid price
or by combinations of those items. Contractor shall perform extra work and
furnish labor, material and equipment for extra work upon receipt of a Change
Order or other written order of the Engineer (including a Field Order) directing
Contractor to perform such extra work, in accordance with the provisions of
Section 4-4 above. Extra work must be authorized in writing by the Engineer
before the work is started. No payment shall be made for extra work performed
prior to Engineer’s prior written authorization.
4-7 GENERAL
The parties intend that differences between the City and Contractor,
arising under the Contract, be brought to the attention of the Engineer at the
earliest possible time in order that such matters may be settled, if possible, or
other appropriate action promptly taken. The City and Contractor agree to
initially strive to resolve all disputes amicably and in an informal manner. Any
dispute resolved informally shall be documented by the Engineer, and if the
dispute resolution involves a change in the Contract Work, increase or decrease
in the compensation due the Contractor, or adjustment in the time of completion
4-5
of the Work, then the informal dispute resolution shall be confirmed by a Change
Order pursuant to the Contract and Section 4-4 above. Informal discussions or
negotiations with the Engineer or other City representatives concerning informal
resolution of a dispute shall not suspend the claim filing and other deadlines
provided below, unless so provided by the Engineer in writing.
4-8 COMPLIANCE REQUIRED
Except as specifically otherwise provided in these Specifications,
Contractor shall not be entitled to payment of any additional compensation or
damages for any cause, including, but not limited to, any act or failure to act,
by the Engineer or the City, or any officer, employee, agent or contractor of the
City, the presence or discovery of any condition, or the happening of any event
or occurrence, unless Contractor gives the Engineer timely written notice of and
supporting data for any such potential claim and complies with the dispute
procedure as specified below. If the Contractor fails to timely file a written
Claim in accordance with Section 4-10 below, then the Contractor shall be
deemed to have waived any right or remedy to thereafter pursue the claim
against the City in any administrative, arbitration or litigation proceeding.
4-9 DEFINITION OF CLAIM
A “Claim” means a separate demand by the Contractor for: (a) a time
extension (including a demand for relief from damages or penalties for delay
assessed by the City under the Contract); (b) payment of money or damages
arising from work done by, or on behalf of, the Contractor pursuant to the
Contract and payment of which is not otherwise expressly provided for or the
Contractor is not otherwise entitled to; or (c) payment of an amount that is
disputed by the City.
The procedures and remedies set forth in sections 4.7-4.11 shall not apply
to: (i) any claim by the City against the Contractor or its surety or sureties (unless
the City, in its sole discretion, opts to proceed hereunder); (ii) any claim or
dispute relating to stop notices; or (iii) any claim relating to the approval, refusal
to approve or substitution of any subcontractor, regardless of tier, pursuant to
Public Contract Code section 4700, et seq.
4-10 REQUIREMENTS FOR FILING CONTRACT CLAIM; CONTENTS; FILING
DEADLINE
The Contractor may file a Claim with the Engineer. A Claim must: (a) be
in writing; (b) be labeled or clearly indicated as a Claim under the Contract; (c)
set forth in detail the reasons why the Contractor believes additional
compensation or a time extension is or may be due, the nature of the costs
involved, and, insofar as possible, the amount of the Claim; (d) include
documents that support and substantiate the Claim; and (e) include the following
4-6
certification, properly completed and executed by Contractor or any officer of
Contractor:
I, _______________________________BEING THE
______________________(must be an owner or officer)
OF____________________(CONTRACTOR), DECLARE UNDER PENALTY OF
PERJURY UNDER THE LAWS OF THE STATE OF CALIFORNIA, AND I DO PERSONALLY
CERTIFY AND ATTEST THAT: I HAVE THOROUGHLY REVIEWED THE ATTACHED
CLAIM FOR ADDITIONAL COMPENSATION AND/OR EXTENSION OF TIME, AND KNOW
ITS CONTENTS, AND THE CLAIM IS TRUTHFUL AND ACCURATE; THAT THE AMOUNT
AND/OR CONTRACT TIME EXTENSION REQUESTED ACCURATELY REFLECTS THE
CONTRACT ADJUSTMENT FOR WHICH THE OWNER IS LIABLE; AND FURTHER, THAT
I AM FAMILIAR WITH CALIFORNIA PENAL CODE SECTON 72 AND CALIFORNIA
GOVERNMENT CODE SECTION 12650, ET SEQ., PERTAINING TO FALSE CLAIMS, AND
FURTHER KNOW AND UNDERSTAND THAT SUBMISSION OR CERTIFICATION OF A
FALSE CLAIM MAY LEAD TO FINES, IMPRISONMENT, AND OTHER SEVERE LEGAL
CONSEQUENCES.
A Claim must be submitted to the Engineer within the following claim
filing deadlines: (a) if the Claim relates to extra, additional or unforeseen work
for which the Contractor intends to demand additional compensation, a time
extension, or both, notice shall be given to the Engineer prior to the time that
the Contractor commences performance of the work giving rise to the potential
claim for additional compensation or time extension, and Contractor shall not
proceed with that work until so directed by the Engineer in writing; and (b) for
all other Claims not included within (a) such as matters covered by the liquidated
damages provisions of the Contract or a Claim that is based directly and solely
on differences in measurements or errors in computation of Contract pay
quantities, the claim must be filed on or before 15 days after the date of the
occurrence, event or circumstance giving rise to the Claim. In no event shall a
Claim be filed later than the date of final payment.
Any additional data supporting the Claim must be given to the Engineer
not later than 30 days after the date of such written notice, unless the Engineer,
in writing, allows an additional period of time to ascertain more accurate data
supporting the claim. This data shall be accompanied by Contractor’s written
statement that the amount claimed covers all known amounts (direct, indirect,
and consequential) to which Contractor is entitled as a result of such condition,
act, failure to act, event, thing or occurrence.
4-11 ALL CLAIMS SUBJECT TO PUBLIC CONTRACT CODE SECTION 9204;
PROCEDURE
This procedure applies to the handling and resolution of all Claims sent to
the City, whether or not by registered mail or certified mail with return receipt
4-7
requested in accordance with Public Contract Code section 9204(c)(1). With
respect to all Claims submitted to the City in accordance with this procedure,
the provisions of Public Contract Code section 9204 shall apply. Pursuant to
Public Contract Code section 9204(f), the City has prescribed reasonable change
order, claim, and dispute resolution procedures and requirements in addition to
the provisions of section 9204 that do not conflict with or otherwise impair
section 9204’s timeframes and procedures.
1. Upon receipt of a properly submitted Claim, the Engineer shall conduct a
reasonable review of the Claim and, within a period of 45 calendar days,
provide the Contractor a written statement identifying what portion of
the claim is disputed and what portion is undisputed. Upon receipt of a
Claim, the Engineer and Contractor may, by mutual agreement, extend
the 45-calendar day time period.
2. The Contractor shall furnish reasonable documentation to support the
claim consistent with the requirements of Section 4.10.
3. If the Contractor disputes the Engineer’s written response, the Contractor
may request in writing an informal conference to meet and confer for
settlement of the issues in dispute. Such request by Contractor shall be
made within 15 calendar days from the date of the written statement
given by the Engineer. Upon receipt of a request in writing, the City shall
schedule a conference within 30 calendar days for settlement of the
dispute. The informal conference shall be conducted by the Division
Manager for the purpose of resolving the dispute.
4. Written notice of the date, time and location of the conference shall be
provided to Contractor not less than ten calendar days prior to the date
of the conference. On such date, or such other date to which the parties
may agree, Contractor shall be afforded a reasonable opportunity to
present Contractor’s position on and substantiation for the Claim. The
conference shall be conducted in an informal manner, and no record shall
be made of the proceedings, except that any written materials submitted
by the City or Contractor shall be preserved by the Division Manager until
the Work is finally accepted by the City.
5. Within ten days following the conclusion of the conference, if the Claim
or any portion of the Claim remains in dispute, the Division Manager shall
provide the Contractor a written decision identifying the portion of the
Claim that remains in dispute and the portion that is undisputed. Any
decision by the Division Manager to pay additional compensation to the
Contractor shall be contingent upon approval of a change order
authorizing such compensation by the Sacramento City Council, unless
City Council approval of the change order is not required under the
4-8
Sacramento City Code. Payment due on an undisputed portion of the claim
shall be processed and made within 60 calendar days after the Division
Manager issues the written decision.
6. If the Contractor disagrees with the Division Manager decision, the
Contractor shall, within 14 calendar days after the Contractor receives
the Division Manager’s decision, file a written request with the City to
submit the disputed portion of the claim to nonbinding mediation, with
the City and the Contractor sharing the associated costs equally.
Contractor hereby expressly waives all Claims not timely submitted to
mediation in accordance with this Section. The City and Contractor shall
mutually agree to a mediator or mediators within 10 days after the
disputed portion of the claim has been identified in writing. As part of the
process of evaluating a proposed mediator, each party may request that
the proposed mediator(s) disclose any prior or existing financial
relationship with either party. If the parties cannot agree upon a mediator
or mediators, each party shall select a mediator and those mediators shall
select a qualified neutral third party or parties to mediate with regard to
the disputed portion of the claim. Each party shall bear the fees and costs
charged by its respective mediator in connection with the selection of the
neutral mediator. If mediation is unsuccessful, the parts of the claim
remaining in dispute shall be subject to applicable procedures set out in
subsection 9 below.
7. The mediator, using advice and input from the parties, shall set the time
of each mediation session, as well as the mediation protocol (i.e.,
submission of briefs, statement of damages, etc.). The mediation will be
held at any convenient location agreeable to the mediator and the parties,
as the mediator determines. All reasonable efforts will be made by the
parties and the mediator to schedule the first session within 30 calendar
days after selection of the mediator.
8. The mediation may be terminated: (a) by the execution of a settlement
agreement by the parties; (b) by a written declaration of the mediator to
the effect that further efforts at mediation are no longer worthwhile; or
(c) by a writing on behalf of a party or parties to the effect that the
mediation proceedings are terminated.
9. If, at the termination of the mediation proceedings pursuant to Section
4.11.8, the Claim(s), or any portion thereof, remain(s) in dispute, the
City’s position shall constitute its final decision with regard to the
Claim(s). Any litigation arising out of the Claim(s) and the Contract
Documents shall be brought in the Sacramento County Superior Court, and
Contractor expressly waives the removal provisions of California Code of
Civil Procedure Section 394.
4-9
4-12 CONTRACT WORK PENDING CLAIM RESOLUTION
In the event of any dispute between the City and Contractor, or during
the pendency of any Claim(s) or associated proceedings under this Section or the
Contract Documents, Contractor shall not stop, or delay performance of, the
Work, but shall prosecute the Work diligently to completion in the manner
directed by the Engineer.
4-13 DISPUTES INVOLVING DESIGN PROFESSIONALS
If any Claim(s) asserted by the Contractor arise from or is/are related, in
any manner, to conduct or actions for which a design professional may be
responsible, the parties acknowledge and agree that the City may, in its sole
discretion, require the participation the design professional in any dispute
proceeding under this Section. This right shall remain solely within the discretion
of the City, and Contractor shall have no rights under the Contract Documents
to require or seek to compel the participation the design professional in any
dispute proceeding under this Section or elsewhere under the Contract
Documents.
4-14 ATTEMPT TO COMPROMISE AND SETTLE
All communications, statements, correspondence, information and other
evidence, whether documentary or oral, made or presented at, or in
anticipation of, the dispute resolution procedures set forth in sections 4.7-4.11
shall be deemed an attempt to compromise and settle the Contractor’s claim
under California Evidence Code section 1152, and as such will be inadmissible
for any reason in any litigation that may arise pertaining to the Claim or the
Contract.
5-1
Section 5
CONTROL OF WORK AND MATERIALS
5-1 AUTHORITY OF ENGINEER
As defined in Section 1 of these Specifications, “Engineer” may mean
either the Director or the representatives authorized by the Director to exercise
control and supervision of the Work. Much of the actual supervision and control
of the project may be by subordinate representatives designated as “Engineer.”
However, whenever in these Specifications, Plans or Special Provisions, the
Director is designated as the authority in any matter, it will mean only the
Director and not subordinates working under the Director’s supervision.
Whenever the word “Engineer” is used in these Specifications, Plans or Special
Provisions, then either the Director’s subordinates assigned to the supervision
and control of the Work or the Director will exercise such authority.
The Engineer will decide any and all questions as to the quality and
acceptability of materials furnished, work performed, and rate of progress of the
Work. The Engineer will decide all questions as to the interpretation of the
Specifications, Plans or Special Provisions, the fulfillment of the Contract on the
part of Contractor, and the rights of different contractors on the project. The
Engineer will determine the amount and quality of the Work performed and
materials furnished, for payment under the Contract.
Whenever, in these Specifications, or upon the Plans, the words
“directed,” “required,” “permitted,” “ordered,” “designated,” “prescribed,” or
words of like import are used, the direction, requirement, permission, order,
designation, or prescription of the Engineer is intended. Similarly, the words
“approved,” “acceptable,” “satisfactory,” or words of like import, mean
approved by, or acceptable to, or satisfactory to the Engineer, subject in each
case to the final determination of the Director or the City Council.
5-2 CONFORMITY WITH PLANS AND ALLOWABLE DEVIATIONS
Finished surfaces shall conform to the lines, grades, cross-sections, and
dimensions shown on the approved Plans and working drawings, unless a
deviation from the Plans is authorized in writing by the Engineer.
5-3 COORDINATION OF CONTRACT DOCUMENTS
These Specifications, the Plans, Special Provisions, and all supplementary
Plans, drawings, and other Contract Documents are essential parts of the
Contract, and a requirement occurring in one is just as binding as though
occurring in all. These documents are intended to be integrated to describe and
5-2
provide for a complete Work. Whenever a reference is made in these
Specifications to a Section or subsection of another agency’s Specifications, such
reference shall be deemed to include the General Provisions of such other
Specifications of which the Section or subsection is a part, to the extent
pertinent to the reference and not inconsistent with the other Contract
Documents. In the event of a conflict in the Contract Documents, unless
expressly indicated otherwise, the governing priorities are as follows:
1. A Change Order.
2. The Agreement.
3. Addenda. Subsequent addenda shall govern over prior addenda only to
the extent specified.
4. In case of conflict between the Specifications and the Special Provisions,
the Special Provisions shall govern.
5. In case of conflict between Plans and Specifications, the Plans shall govern
in matters of quantity and the Specifications shall govern in matters of
quality.
6. In case of conflict within the Plans involving quantities and quality,
Contractor shall furnish the greater quantity and quality material and
procedure.
7. In case of conflict within a plan sheet involving figured or numerical
dimensions the profile shall govern over the layout.
8. In case of conflict within the Specifications involving quality of material
or procedure, Contractor shall furnish the higher quality material and
procedure.
9. Specific notes shall govern over other notes and other portions of the Plans
except Schedules.
10. Larger scale drawings shall govern over smaller scale drawings.
11. Detail plans shall govern over standard plates bound within the
Specifications.
12. Figured or numerical dimensions shall govern over dimensions obtained by
scaling.
13. Where provisions of codes, safety orders, Contract Documents, referenced
manufacturers’ specifications or industry standards are in conflict, the
more restrictive and higher quality shall govern.
Contractor shall not take advantage of any error, discrepancy or omission
in any of the Contract Documents if such error, discrepancy or omission was or
should have been apparent to Contractor. As soon as Contractor discovers any
apparent error, discrepancy or omission, Contractor shall immediately notify the
Engineer, so that the Engineer may make a determination on the matter, which
determination shall be final, subject to Contractor’s right to submit a claim in
accordance with applicable provisions of the Contract Documents.
5-3
The Work shall be performed and completed according to the meaning
and intent of the Contract Documents.
In addition to the drawings made a part of this Contract at time of signing,
by incorporation or reference, the Engineer may furnish such additional drawings
from time to time during the progress of the Work, as are necessary to make
clear and to define in greater detail, as may be necessary, the intent of the
Specifications, Plans, Special Provisions and other Contract Documents and
Contractor shall make its Work conform to all such drawings.
Should it appear that the Work to be done or any of the matters related
to the Work are not sufficiently detailed or explained in the Contract Documents,
Contractor shall provide the Engineer with a request for information (RFI)
requesting such information or explanations as may be necessary to complete
the Work. The City shall respond to RFIs within 20 calendar days of receipt,
unless the Engineer reasonably determines that a longer time period is necessary
to provide the information requested by Contractor. The City response (but not
Contractor’s RFI) shall become part of the Contract, and Contractor shall be
responsible for conforming its activities and operations, including the activities
and operations of all subcontractors and suppliers, to all applicable
requirements, terms and conditions of the City’s response.
5-4 COOPERATION OF CONTRACTOR
After all necessary signatures by City, City will supply Contractor a copy
of the Plans, Special Provisions, and the fully executed Agreement. City will also
make available to Contractor at least five (5) copies of the Plans and Special
Provisions for Contractor’s use in prosecuting the Work. If Contractor requests
additional copies of the Plans or Special Provisions, the City or its designated
reprographics firm will supply such additional copies at Contractor’s expense.
Contractor shall give the Work the constant attention necessary to
facilitate the satisfactory progress of the Work. Contractor shall cooperate with
the Engineer, inspectors and with other contractors in every way possible.
Contractor shall at all times have a competent Superintendent at the site of the
Work. Contractor’s Superintendent shall be fully authorized as Contractor’s
agent on the Work. The Superintendent shall be capable of reading and
understanding all of the Contract Documents. Unless otherwise approved by the
Engineer, the Superintendent shall be an employee of Contractor responsible for
providing continuous on-site supervision of the Work and shall be fully authorized
to receive and follow any instruction given by the Engineer and to sign Change
Orders on behalf of Contractor. Unless specifically called for by the Special
Provisions, Contractor is not required to provide an office for use by the
Engineer.
5-4
If requested by the Engineer, Contractor shall provide daily reports signed
by Contractor’s Superintendent indicating the location and description of
operations and details of the equipment and labor used to perform the items of
Work. Such details shall include the description of the items of Work, names and
classifications of laborers, hours worked, description of equipment used,
equipment numbers, and hours equipment are in use, and hours equipment may
be idle.
5-5 CONSTRUCTION STAKES
The Engineer will furnish Contractor with all lines, grades and
measurements necessary for the proper prosecution and control of the Work
unless stated otherwise in the Special Provisions. Contractor shall provide the
Engineer with the City’s standard Survey Request Form at least three (3) working
days before construction stakes are required. The Engineer may reject any
unreasonable or incomplete Survey Request Form and require Contractor to
resubmit. Contractor shall have no claim for any costs, damages or extensions of
time arising from any delay caused by Contractor’s submittal of an unreasonable
or incomplete Survey Request Form.
Such stakes and markings as the Engineer may set for either the City’s or
Contractor’s guidance shall be preserved by Contractor. In the event that the
stakes or marks placed by the Engineer are destroyed through carelessness or
negligence on the part of Contractor or any Subcontractor and the destruction
of these stakes or marks causes a delay in the Work, Contractor shall have no
claim for damages or extensions of time. Additionally, the City reserves the right
to charge Contractor or deduct from the progress payments the costs to the City
for any re-staking or remarking required as a result of carelessness or negligence
on the part of Contractor or any Subcontractor.
5-6 PERMANENT SURVEY MONUMENTS
Contractor is responsible for verifying that the arrangements have been
made for preserving and perpetuating all permanent survey monuments that will
be affected by the Work. Contractor is responsible for preserving all permanent
survey monuments that are not proposed to be disturbed. Contractor shall
provide a minimum of ten (10) working day notice to Engineer prior to
disturbance or removal of any permanent survey monument, and shall coordinate
with the Engineer to reset monuments or provide permanent witness monuments
and file the required documentation with the County Surveyor pursuant to
Business and Professions Code Section 8771.
5-5
5-7 SUBMITTALS
Contractor shall supply all submittals required by the Special Provisions or
the Engineer. Unless otherwise specified herein, Contractor shall deliver five (5)
copies of the submittals to the Engineer when required by the Contract
Documents or the Engineer. Within twenty (20) calendar days after receipt of a
submittal, the Engineer will return two (2) marked copies of the submittal to
Contractor indicating one of the following four (4) actions taken by the Engineer,
in the Engineer’s sole discretion:
1. If the Engineer’s review indicates no exceptions, copies will be returned
marked "NO EXCEPTIONS TAKEN." Contractor may immediately
incorporate the material and equipment covered by the submittal into the
Work.
2. If the Engineer’s review indicates limited corrections are required, copies
will be returned marked "MAKE CORRECTIONS NOTED." Contractor may
immediately incorporate into the Work the material and equipment
covered by the corrected submittal, with the corrections noted by the
Engineer.
3. If the Engineer’s review indicates insufficient or incorrect data has been
submitted, copies will be returned marked "REVISE AND RESUBMIT." No
work may begin on incorporating the material and equipment covered by
this submittal into the Work until the submittal is revised, resubmitted,
and returned marked either "NO EXCEPTIONS TAKEN" or "MAKE
CORRECTIONS NOTED."
4. If the Engineer’s review indicates the material and equipment submittal
is unacceptable, copies will be returned marked "RESUBMIT." No work
may begin on incorporating the material and equipment covered by this
submittal into the Work until a new submittal is submitted and returned
marked either "NO EXCEPTIONS TAKEN" or "MAKE CORRECTIONS NOTED."
After approval by the Engineer, submittals (including any corrections
noted by the Engineer) shall become a part of the Contract, and the work shall
be done in conformity with such approved submittals. No work shall be started
or material or equipment purchased until the submittals have been approved.
Submittals furnished to the Engineer shall include finished drawings, if required,
that are neat, legible, to scale, and drawn to as large scale as reasonably
possible.
5-6
5-8 RECORD DRAWINGS
Contractor shall maintain a neatly and accurately marked set of record
drawings showing the final locations and layout of all facilities as-built. Drawings
shall be kept current weekly, with all work instructions and Change Orders,
accommodations, and construction adjustments. Drawings are subject to the
inspection by the Engineer at all times, and progress payments, or portions of
progress payments, may be withheld if drawings are not accurate and current.
Prior to City’s acceptance of the Work, Contractor shall deliver to the Engineer
one (1) set of neatly marked record drawings, accurately showing all the
information required above. If the Engineer does not approve the record
drawings, Contractor shall revise and resubmit the record drawings as necessary
to obtain the Engineer’s approval. If Contractor fails to comply with the
requirements of this section, the City may deduct and retain the cost of
preparing the record drawings from the Contract.
5-9 SUGGESTIONS TO CONTRACTOR ADOPTED AT CONTRACTOR’S OWN RISK
Contractor is solely responsible for determining whether to follow or
utilize any plan or method of work suggested by the Engineer to Contractor in
whole or in part, and Contractor shall assume all risks for this determination.
The Engineer and City will assume no responsibility or risk.
5-10 REQUEST FOR MODIFICATION OF WORK
Should conditions occur during the progress of the Work that make it
impossible for Contractor to comply strictly with the terms of the Contract with
respect to a portion of the Work, Contractor shall make written request to the
Engineer for a modification of such portion of the Work, provided that any
modification is not detrimental to the Work or create any additional cost to the
City. If the modification is acceptable to the Engineer, Contractor will be notified
in writing, consistent with any conditions specified by the Engineer. If a
modification is not acceptable to the Engineer, Contractor shall determine some
other method of performing such portion of the Work that is acceptable to
Engineer.
Such approved modifications do not affect or alter the application of any
provision of the Contract to any portion of the Work for which no modification is
approved by the Engineer.
5-11 RIGHT TO PERFORM EXTRA WORK
In case of neglect or refusal by Contractor to perform any extra work as
directed by the Engineer pursuant to Section 4-6 of these Specifications or to
make satisfactory progress in the execution of extra work, the City may employ
5-7
any person or persons to perform such work, and Contractor shall not in any way
interfere with the person or persons so employed.
5-12 PROVISIONS FOR EMERGENCIES
If, in the opinion of the Engineer, Contractor has not taken sufficient
precautions for the safety of the public or the protection of the Work or adjacent
structures or property and immediate action is necessary in order to protect the
public, any person or any property or property interest (“emergency work”), the
Engineer, with or without notice to Contractor, may, but is not obligated to,
take such action or obtain or provide for such work and material as the Engineer
may consider necessary and adequate to furnish such protection.
The City’s cost to perform, obtain or provide for such action, work and
material shall be paid by Contractor, and may be deducted by City from any
payment due or to become due to Contractor.
The performance of emergency work under the direction of the Engineer
shall in no way relieve Contractor from its responsibility or liability for any
damages that may occur while or after any actions are or have been taken by
the Engineer.
5-13 SUSPENSION OF WORK TO PROTECT HEALTH, SAFETY OR WELFARE OF
PERSONS OR PROPERTY
If the Engineer determines, in the Engineer’s sole discretion, that a
situation exists where continuation of the Work is illegal or endanger the health,
safety or welfare of persons or property on or affected by the Work, the Engineer
may order Contractor in writing to delay or suspend the Work in whole or in part
for a period of time equal to the period of time while such situation exists. Any
order given to Contractor to suspend or delay the Work shall identify the
situation that makes the suspension or delay necessary.
Such order of the Engineer does not modify or invalidate in any way any
of the provisions of this Contract, and Contractor is not entitled to any damages
or compensation from City on account of such delay or suspension.
5-14 RIGHT TO RETAIN IMPERFECT WORK
If any portion of the work done or material furnished under this Contract
is defective and not in accordance with the Contract Documents, and if the
defect is not of sufficient magnitude or importance to make the Work or any
portion of the Work dangerous or undesirable, the Engineer may, but is not
obligated to, retain the defective work instead of requiring the work to be
removed and reconstructed. The Engineer may make such deduction from the
5-8
payments due or to become due to Contractor as determined appropriate by the
Engineer to account for the defector pay the City’s costs of removal and
reconstruction.
5-15 STORAGE OF MATERIALS AND EQUIPMENT
Contractor is solely responsible for protecting work in place and materials
and equipment stored on-site or off-site from contamination by dust, dirt, debris
or mold. Materials and equipment shall be stored so as to ensure the
preservation of their quality and fitness for the Work. Stores of equipment and
materials shall be located to facilitate inspection by the City. Contractor is
responsible for all damages that occur in connection with the care and protection
of all materials and equipment to be incorporated in the Work until the
completion and final acceptance of the Work by the City.
Prior to storing any materials or equipment on private property not owned
by Contractor, Contractor shall obtain written permission from the property
owner and, if different than the property owner, the occupant of the property.
Contractor is solely responsible for obtaining such permission and complying with
any and all conditions and requirements of the property owner or occupant.
Contractor is solely responsible for maintaining adequate security and
warning signs and controlling dirt, debris and dust within the limits of
Contractor’s storage areas at all times. Contractor shall take all steps necessary
or required by the Engineer to prevent and eliminate blowing dust.
Prior to commencing the Work, Contractor shall submit a written “Storage
of Materials and Equipment Plan” for approval by the Engineer. The Plan shall
specify the location, entry date and exit date for all locations where Contractor
will store materials or equipment, and a site maintenance plan for all locations.
Additionally, this Plan shall describe the measures that Contractor will undertake
to minimize impacts to driveways, residents and the general public in the vicinity
of such storage locations during work and non-work hours. If this Plan is not
approved by the Engineer, Contractor shall revise and resubmit the Plan as
necessary to obtain the Engineer’s approval.
5-16 MANUFACTURER’S DIRECTION
Manufactured articles, material, and equipment shall be applied,
installed, connected, erected, adjusted, tested, used, cleaned, maintained, and
conditioned as recommended by the manufacturer. Copies of the manufacturer's
installation instructions and procedures shall be submitted, in accordance with
Section 5-7 of these Specifications.
5-9
5-17 QUALITY OF MATERIALS AND WORKMANSHIP
If the Contract provides that Contractor shall furnish materials or
manufactured articles or shall do work for which no detailed specifications are
set forth, the materials or manufactured articles shall be of the best grade in
quality and workmanship obtainable in the market from firms of established good
reputation, or, if not ordinarily carried in stock, shall conform to the usual
standards for first-class materials or articles of the kind required, with due
consideration of their intended use. The work performed shall fully conform
with the intent to secure the best standard of construction and equipment for
the Work as a whole or in part.
5-18 TRADE NAMES AND ALTERNATIVES
For convenience in designation, certain articles or materials to be
incorporated in the Work may be designated under a trade name or the name of
a manufacturer and its catalogue information. Unless the trade or manufacturer
name is expressly designated as the only brand that will be accepted, for one or
more of the purposes specified in Public Contract Code Section 3400(b), such
designation is deemed to include the words “or equal,” so that the use of an
alternative article or material of equal quality and possesses the required
features and characteristics for the purpose intended will be permitted, subject
to the following requirements:
The burden of proof as to the quality and suitability of alternatives is upon
Contractor, who shall furnish all relevant information as required by the
Engineer. The Engineer will be the sole judge as to the quality and suitability of
alternative articles or materials. The Engineer’s decision will be final.
If the Contract Documents permit the substitution of a similar or
equivalent material or article, no tests or action relating to the approval of the
substitute material will be made until the request for substitution is made in
writing by Contractor accompanied by complete data as to the equality of the
material or article proposed. Such requests shall be made in ample time to
permit approval without delaying the work, but need not be made within thirty
(30) days after award of the Contract.
5-19 DUTIES AND POWERS OF INSPECTORS
Inspectors are representatives of the City with respect to the duties and
powers entrusted to them, subject to any limitations on their authority specified
by contract or under any Laws or Regulations. Their duty is to inspect materials
and workmanship of those portions of the Work to which they are assigned, either
individually or collectively, under instructions of the Engineer, and to report any
deviations from the Contract Documents. If an inspector deems it necessary, the
5-10
inspectors may order Contractor to stop the Work until the Engineer determines
and orders that the Work may proceed.
5-20 INSPECTION
All work and materials furnished pursuant to this Contract are subject to
inspection and approval or rejection by the Engineer and such assistants as the
Engineer deems necessary. Contractor shall notify the Engineer of the time and
place of any factory tests required by the Contract, and the time and place of
preparation, manufacture or construction of any material for the Work, or any
part of the Work, that the Engineer notifies Contractor the Engineer wishes to
inspect.
Contractor shall give notice not less than three (3) working days in
advance of the beginning of the work on any such material or of the beginning
of any such test to allow the Engineer to make arrangements for inspecting and
testing or witnessing the inspection or testing, if such inspection and testing or
witnessing are deemed beneficial by the Engineer or are required by the
Contract.
If the Engineer considers it proper and practicable, the Engineer will, at
the written request of Contractor, cause materials intended for use in the Work
to be inspected at the point of production or manufacture. The Engineer may at
any time cause such an inspection, however, it will not be undertaken until the
Engineer is assured of the cooperation and assistance of both Contractor and the
material producer. The Engineer or the Engineer’s authorized representative(s)
will have free entry at all times to such parts of the plant as concerns the
manufacture or production of the materials. Adequate facilities shall be
furnished free of charge to make the necessary inspection. Notwithstanding the
foregoing, the City shall have no obligation to inspect materials at the source of
supply.
Unless authorized by the Engineer, any work done in the absence of an
inspector that is completed or in progress shall be subject to inspection. If
required by the Engineer, Contractor shall furnish all tools, labor, materials, and
other facilities necessary to make such inspection, even to the extent of
uncovering or taking down portions of the finished work. Contractor shall pay
the cost of such inspection and removing any defective work and performing any
necessary reconstruction.
5-21 REMOVAL OF REJECTED MATERIALS AND STRUCTURES
Contractor shall remove from the site of the Work, without delay, all
rejected materials or structures brought to or incorporated in the Work. If
Contractor fails to do so, or to make satisfactory progress in doing so within
5-11
forty-eight (48) hours after the service of a written notice from the Engineer,
the rejected material or work may be removed by City and the City may deduct
the cost of such removal from any payments that are due or may become due to
Contractor. No such rejected material shall again be offered for use by
Contractor under this Contract or any other contract with City. Contractor shall
not use any such rejected material in the performance of the Contract.
5-22 APPROVAL OF SOURCES OF SUPPLY OF MATERIALS
The Engineer may require Contractor to provide information on the source
of supply of materials for the Work and may require that the Engineer’s approval
be obtained prior to Contractor securing any or all materials. The Engineer may
require Contractor to submit representative samples of materials for inspection
and testing by City.
Even though a source of supply has been approved, the approval shall not
prevent subsequent disapproval or rejection of materials, if the quality of the
product or material is later determined to be below the standard or requirements
set by any of the Contract Documents.
5-23 PREPARATION FOR TESTING
Contractor shall maintain proper facilities and provide safe access for
inspection by City of all parts of the Work and of the shops or other locations
where any portion of the Work is prepared. Where the Specifications or Special
Provisions require work to be specially tested or approved, it shall not be tested
or covered up without at least a 24 hour written notice to the Engineer of its
readiness for inspection unless the written approval of the Engineer for such
testing or covering is first obtained.
5-24 METHODS OF SAMPLING AND TESTING
Contractor shall furnish samples of materials for testing as required by
the Engineer. Contractor shall furnish such samples without cost to City. Testing
shall be done to such standards as may be set forth in the Contract Documents.
References made in these documents to standard methods of testing materials
shall by such reference make such standards a part of the Contract.
5-25 REFERENCE TO STATE, FEDERAL OR NATIONAL SPECIFICATIONS
Whenever a reference is made in the Contract Documents to a
specification or test designation either of the A.S.T.M., the A.A.S.H.T.O., the
A.W.W.A., the Federal Specifications, or any other recognized national
organization or State of California agency, and the number or other
identification representing the year of adoption or latest revision is omitted, it
5-12
shall mean the specification or test designation in effect on the day the Notice
to Contractors for the Work was dated.
6-1
Section 6
LEGAL RELATIONS AND RESPONSIBILITIES TO THE PUBLIC
6-1 LAWS TO BE OBSERVED
Contractor shall be familiar with all Federal, State, and local Laws or
Regulations that affect those engaged or employed in the Work, or the material
or equipment used in or upon the site of the Work, or the conduct of the Work.
Any misunderstanding or ignorance on the part of Contractor of such Laws or
Regulations shall not in any way relieve Contractor of any responsibility under
the Laws or Regulations or the Contract or otherwise modify the Contract.
Contractor shall observe and comply with all Laws or Regulations affecting
the conduct of the Work, and Contractor and its Sureties shall defend, indemnify
and hold harmless City and all of its officers, agents, and employees against any
claim for liability arising from, based upon, or resulting from a condition created
as a result of, the violation of any such Law or Regulation, whether by Contractor
or any Subcontractor or Supplier or any of their respective officers, employees
or agents.
6-2 CERTAIN LAWS AFFECTING THE WORK
This list is not a comprehensive inventory of applicable Laws and
Regulations, but is a summary of a few selected State laws and City ordinances
applicable to the Work.
1. State Laws
a. Labor Discrimination
Contractor shall not discriminate in the employment of persons on
any ground listed in Labor Code Section 1735. The penalty for any such
discrimination will be as set forth in the Labor Code, Section 1735, and
Chapter 1 of Part 7 of Division 2 of the Labor Code.
b. Fair Labor Standards Act
Contractors shall comply with the Fair Labor Standards Act of 1938
(52 Stat. 1060) as amended as it may be applicable.
c. Contractor Licensing
Bidders and Contractors shall maintain license as required by
Chapter 9 of Division III of the Business and Professions Code.
6-2
d. Subcontractors
The rules concerning the use of Subcontractors have been discussed
in Section 2-9 of these Specifications. Particular reference was made
therein to Section 4101 to Section 4113, inclusive, of the Public Contract
Code.
e. Underground Service Alert
Prior to conducting any excavation, Contractor shall contact the
Underground Service Alert Northern California as required by
Government Code Section 4216.2, and shall take any and all other actions
necessary to comply with and shall be subject to the provisions of
Government Code Sections 4216.2 through 4216.9, inclusive.
2. Local Ordinances
a. Prevailing Wages
Pursuant to Section 3.60.180 of the Sacramento City Code,
Contractor shall pay not less than the prevailing rate of wages as
determined by the Director of the California Department of Industrial
Relations pursuant to Labor Code Section 1773. The wage rate
determinations may be viewed on the Internet at
http://www.dir.ca.gov/dlsr/. Withholdings and penalties shall be as set
forth in Section 3.60.180 of the Sacramento City Code and applicable
Labor Code provisions.
For Federally funded projects, Contractor shall pay the higher of
the Federal Davis Bacon Wage Rate, that is published with the Contract,
or the rate specified herein for each trade or work classification
employed. Contractor is responsible for submitting all required original
signed payroll documents to the City for itself and all Subcontractors. The
City shall not recognize any claim for additional compensation because of
the payment by Contractor of any wage rate in excess of the prevailing
wage rate required under the Contract.
The wage rates determined by the Director of the California
Department of Industrial Relations refer to expiration dates. Prevailing
wage determinations with a single asterisk (*) after the expiration date
apply to any contract advertised for bids prior to the expiration date and
are good for the life of the contract. Prevailing wage determinations with
double asterisks (**) after the expiration date indicate that the wage rate
to be paid for work performed after this date has been predetermined. If
6-3
Work under the Contract will extend past this date, Contractor and its
Subcontractors will be required to pay the new rate after such expiration
date.
Contractor should contact the Prevailing Wage Unit, Division of
Labor Statistics and Research (DLSR), (415-703-4780), to obtain
predetermined wage changes for rates designated by a double asterisk (**)
after the expiration date. The possibility of wage increases is one of the
elements to be considered by Contractor in determining its bid, and shall
not under any circumstances, be considered as the basis of a claim for
additional compensation or damages against the City under the Contract.
b. Hours of Labor
Contractor shall comply with the provisions of Section 3.60.180 of
the Sacramento City Code regarding the maximum hours of labor.
Withholdings and penalties shall be a set forth in Section 3.60.180 of the
Sacramento City Code and applicable Labor Code provisions.
c. Apprentices
Contractor shall comply with the provisions of Section 3.60.190 of
the Sacramento City Code, as well as any other applicable Laws or
Regulations.
d. Grading, Erosion, and Sediment Control
Contractor shall be responsible for the implementation and
maintenance of erosion, sediment and pollution control measures,
otherwise known as Best Management Practices (BMPs) within the limits
of the Work site and all areas impacted by the project at all times during
the course of construction, including evenings, nights, weekends and
holidays in addition to the normal working days in accordance with the
provisions of Chapter 15.88 of the Sacramento City Code.
e. Storm Water Management and Discharge Control
Contractor shall be responsible for the implementation and
maintenance of all BMP measures necessary to effectively prevent the
discharge of sediment, construction debris, trash, and all associated
construction pollutants from discharging to a river, creek, roadside ditch,
canal, basin and/or the storm water conveyance system in accordance
with Chapter 13.16, and Section 15.40.040 of the Sacramento City Code.
6-4
f. Work Affecting the Public Right-of-way
Contractor shall be responsible for obtaining City approval of and
complying with a traffic control plan, providing for the maintenance of
construction areas affected by the Work, protecting existing facilities in
the Work area, repairing any existing facilities damaged by Contractor’s
operations, and notifying the public prior to performing the Work in
accordance with the provisions of Chapter 12.20 of the Sacramento City
Code.
g. Noise Regulations
Contractor shall comply with the provisions of Chapter 8.68 of the
Sacramento City Code.
h. Dust Regulations
Contractor shall take reasonable cautions to prevent and control
the movement of dust created by Contractor’s Work activities in
accordance with Section 15.40.050 of the Sacramento City Code. Proposed
and implemented measures shall be in compliance with sections d and e.
The Engineer may stop Work activities during conditions of high winds that
may carry dust from the Work-site.
3. Amendments and Ordinance Changes
The statute and ordinance citations set forth above shall be deemed to
refer to future amended or renumbered versions of the statute or
ordinance cited.
6-3 PERMITS, LICENSES AND FEES
Unless otherwise indicated in the Special Provisions, Contractor shall at
Contractor’s sole expense obtain all necessary permits and licenses for the
construction of the Work, give all necessary notices, pay all fees required by law,
and comply with all Laws and Regulations relating to the Work and to the
preservation of the public health and safety.
6-4 PROTECTION OF CITY AGAINST PATENT CLAIMS
Contractor shall assume all cost arising from the use of patented,
copyrighted, trademarked or other similarly protected materials, equipment,
devices, or processes used on or incorporated in the Work and shall defend,
indemnify and hold harmless the City of Sacramento together with all of its
6-5
officers and employees, and their duly authorized representatives, from any and
all claims and actions, including claims and actions for violation of intellectual
property rights, arising on account of the use of any such materials, equipment,
devices, or processes by Contractor or any Subcontractor or Supplier. Before final
payment is made on the Contract, if requested by Engineer, Contractor shall
furnish acceptable proof of a proper release from all claims, costs, and liabilities
arising from the use of such materials, equipment, devices, or processes used on
or incorporated in the Work.
6-5 SANITARY REGULATIONS
Contractor shall comply with all Laws or Regulations governing sanitation
and public health, and shall defend, indemnify and hold harmless the City of
Sacramento together with all of its officers and employees, and their duly
authorized representatives, from any and all claims, actions or other liabilities
arising on account of any failure to do so by Contractor or any Subcontractor or
Supplier.
Contractor shall construct and maintain the necessary sanitary
conveniences for the use of the workers in such a manner and at such points as
shall be approved by the Engineer, and the use of these facilities shall be strictly
enforced.
Contractor shall obey and enforce such sanitary regulations and orders and
shall take such precautions against contagious or infectious diseases as required
by any Laws or Regulations or as the Engineer may deem necessary.
6-6 PUBLIC CONVENIENCE AND SAFETY
Contractor shall protect and preserve the safety of the public during the
progress of the Work. Contractor shall not unnecessarily cause inconvenience to
the public during the progress of the Work and shall minimize the inconvenience
caused by Contractor’s operations. Such operations include, but are not limited
to, work performed on or adjacent to the Work site, traffic lane and pedestrian
closures and deliveries of material and equipment.
Materials shall be stored on the work site so that no hazard to the public
and no damage to public property will result. Damage to property caused by
Contractor shall be repaired at Contractor’s expense to the satisfaction of the
Engineer. Spills resulting from hauling operations along or across any public
traveled way shall be removed immediately by Contractor at Contractor’s
expense. Water or dust palliative shall be applied as necessary or if ordered by
the Engineer for the alleviation or prevention of dust. Contractor shall insure
that all utility services to customers in the project area are maintained.
6-6
Applicable Public Utilities Commission regulations are in effect at railroad grade
crossings. Contractor shall not interfere with or impair railroad operations. If
the Work could affect railroad operations, Contractor shall contact the railroad
prior to construction and comply with all requirements pertaining to railroad
operations or facilities.
6-7 HOUSEKEEPING PRACTICES
Contractor shall implement good housekeeping practices during all
construction activities until completion and final acceptance of the Work. In
addition to practices specified elsewhere in the Contract Documents, Contractor
shall implement, at a minimum, the following housekeeping practices: solid
waste management, material storage and delivery area, concrete waste
management, trash management, and spill prevention and control.
Solid Waste Management: Contractor shall maintain a clean construction
site and provide designated areas for waste collection. The waste collection
areas shall contain leak-proof disposal containers with lids or covers. Site trash
shall be collected daily and placed in the disposal containers. Contractor shall
make arrangements for regular waste collection and regularly inspect the waste
disposal areas to determine if potential pollutant discharges exist.
Material Storage and Delivery Area: Contractor shall provide one central
material storage and delivery area (MSDA) for the duration of the Work. This
area shall be fenced or otherwise protected such that runoff will not leave the
MSDA site. Contractor shall regularly inspect the MSDA site to ensure that any
hazardous or non-hazardous materials have not spilled.
Concrete Waste Management: Contractor shall arrange for off-site
disposal of concrete wastes or disposed of in one designated area. Concrete
wastes, including left-over concrete and material from washing out the concrete
truck, shall not be disposed to the storm drain system via curb and gutter or
otherwise. If a designated area is provided, the area shall be bermed and
protected from the elements to allow the concrete to dry. The dried concrete
waste shall be removed and disposed of properly by Contractor at Contractor’s
expense. Proof of proper disposal may be required by the City inspector or
engineer.
Spill Prevention and Control: Contractor is responsible for instructing
employees and Subcontractors about preventing spills of hazardous materials and
controlling spills if they occur. Proper spill control and cleanup materials shall
be kept on-site near the MSDA and updated as materials change on site. If a
significant spill has entered the City’s drainage system, Contractor shall contact
the City’s drainage maintenance supervisor to ensure the discharge has not
impacted a body of water or drainage facility.
6-7
More information about required BMPs can be obtained by referring to the
City of Sacramento's Administrative and Technical Procedures Manual for
Grading, Erosion and Sediment Control available online at:
https://www.cityofsacramento.org/-/media/Corporate/Files/DOU/Specs-
Drawings/Sediment-control-manual.pdf?la=en
6-8 TRENCH SAFETY PLANS
Before beginning excavation for a trench five (5) feet or more in depth,
Contractor shall secure a permit from the Division of Industrial Safety. A copy
of this permit must be available at the construction site.
When required on the Plans or by the Engineer, Contractor shall submit to
the Engineer a detailed Plan showing the design of shoring, bracing, sloping or
other provisions to be made for worker protection from the hazard of caving
ground. Such Plan shall be approved by the Engineer at least five (5) days before
Contractor intends to begin work on the trench. If the Plan varies from the
shoring system standards established by the Construction Safety Orders of the
Division of Industrial Safety, the Plan shall be prepared by a registered civil or
structural engineer. Nothing in this provision allows the use of shoring, sloping
or protective systems less effective than that required by the Construction Safety
Orders of the Division of Industrial Safety.
Contractor’s bid for any item requiring excavation shall include all costs
to furnish, install, maintain and remove adequate sheeting, shoring and bracing,
and any other measures necessary to maintain adequate worker protection and
conform to all applicable safety orders.
6-9 COMPLIANCE WITH OSHA
Contractor is responsible for strict compliance with applicable
requirements of the California Occupational Safety and Health Act (Labor Code
Sections 6500 et seq.). This includes, but is not limited to, all applicable
Construction Safety Orders issued by the State of California, Division of Industrial
Safety, under Title 8 of the California Code of Regulations.
6-10 TRAFFIC CONTROL REQUIREMENTS
Contractor is solely responsible for furnishing, installing and maintaining
all warning signs and devices necessary to safeguard the public and the Work,
and to provide for the proper and safe routing of vehicular, bicycle, and
pedestrian traffic during the performance of the Work. This requirement is for
the duration of the project, and is not limited to working hours. The use of
6-8
flagmen, barricades, and construction signing shall comply with the current
edition of the California “Manual on Uniform Traffic Control Devices.”
Contractor shall submit a traffic control plan showing proposed traffic
control measures and detours for vehicles and pedestrians a minimum of ten (10)
working days prior to the start of any Work within or affecting the street right of
way. The traffic control plan shall include the following information pursuant to
City Code Chapter 12.20:
1. The name and business address of the applicant.
2. Diagram showing:
a. The location of the proposed work area;
b. The location of areas where the public right-of-way will be closed
or obstructed; and
c. The placement of traffic control devices necessary to perform the
work.
3. The proposed phases of traffic control in a narrative format including a
description and dates for the beginning and ending of each phase.
4. The time periods when the traffic control will be in effect.
5. A statement that the applicant will comply with the City’s noise ordinance
during the performance of all work.
6. A statement that the applicant understands that the plan may be modified
by the director at any time in order to eliminate or avoid traffic conditions
that are hazardous to the safety of the public.
Contractor shall not work until a City-approved traffic control plan is on
file with the Engineer. If the Engineer determines at any time that actual traffic
conditions render the approved plan inadequate to ensure public safety, the
Engineer may require the plan to be immediately modified. If a hazardous
condition cannot be eliminated by plan modification the Engineer may require
work under the plan to be stopped, and the plan suspended, until the safety
hazard is remedied. Contractor is not entitled to any costs, damages or
extension of Contract time arising from any stop work order issued by the
Engineer under this Section.
Contractor shall provide safe pedestrian, bicycle, and disabled access
through or around the construction area. It construction activities will block or
limit access to a Class IV bikeway, as designated in the City Bicycle Master Plan,
Contractor may be required to provide a minimum Class II bike lane as an
alternative in the traffic control plan to provide continuity in the protected
bicycle network. Sidewalk closure shall comply with the “Policy for Sidewalk
Closures” established by the City of Sacramento’s Department of Public Works
pursuant to federal and state disability access laws and regulations. Contractor
6-9
shall provide access to all existing driveways, adjacent parking areas, and
buildings at all times unless other arrangements are made with the property
owner and approved by the Engineer. Access for emergency vehicles shall be
clear at all times.
Contractor shall use skid resistant steel plates to cover all excavations
permitted to remain open in the roadway during non-working hours. Steel plates
shall be placed in a safe and proper manner that does not impede the passage of
pedestrians, bicycles, and the disabled community.
All Work within public streets and right-of-way shall be done in an
expeditious manner so as to cause as little inconvenience to the public as
possible. Unless otherwise approved, Contractor shall maintain at least one
travel lane in each direction at all times on two-way Primary Streets (defined
below), and at least two travel lanes at all times on one-way Primary Streets.
On working days, between 7:00 a.m. and 8:30 a.m. and 4:00 p.m. to 6:00
p.m., Contractor shall maintain the number of lanes normally available on all
Primary Streets unless otherwise approved in writing by the City Traffic Engineer.
In addition to the foregoing, on working days, Contractor shall maintain the
number of lanes normally available on J Street between Interstate 5 and 16
th
Street between the hours of 7:00 a.m. and 6:00 p.m. unless otherwise approved
in writing by the City Traffic Engineer.
“Primary Streets” are defined as any one of the following streets and its
adjacent public sidewalk:
3rd St. between I St. & Broadway G St. between 3rd St. & Alhambra Blvd.
5th St. between H St. & Broadway Garden Highway
6th St. between H St. & Q St. Greenhaven Dr.
7th St. between G St. & T St. H St.
8th St. between G St. & Broadway Heritage Lane
9th St. between G St. & Broadway Hornet Dr.
10th St. between G St. & Broadway Howe Ave.
11 th St. between G St. & Q St. I St. between 3rd St. & 29th St.
12th Ave. btwn Martin Luther King, Jr. Blvd. & Sutterville Rd J St.
12th St. between N 12th St. & W St. Jackson Road
13th St. between H St. & L St. Jibboom St.
14th St. between G St. & L St. K St. between 15th St. & Alhambra Blvd.
15th St. between F St. & Broadway L St. between 3rd St. & Alhambra Blvd.
16th St. between N 16th St. & Broadway La Mancha Way
19th St. between G St. & Broadway La Riviera Dr.
21st St. between 4th Ave. & G St Land Park Dr.
24th St btwn (Knight Way & Meadowview Rd, W St. & 2nd Ave) Mack Road
29th St. between D St. & W St. Main Ave. west of Kelton Way
30th St. between E St. & T St. Marconi Ave.
34th St. between Folsom Blvd. & Broadway Martin Luther King, Jr. Blvd.
43rd Ave. west of South Land Park Dr. Marysville Blvd. btwn Del Paso Blvd. & Bell Ave.
47th Ave., city portions between 24th St. & Stockton Blvd. Meadowview Road
6-10
55th St. Fruitridge Road
65th St. between Folsom Blvd. & Broadway Munroe St.
65th St. Expressway between Elvas Ave. & south city boundary N St. between 2nd St. & Alhambra Blvd.
North 12th St. Natomas Blvd.
Alta Arden Expressway N 16th St. Alhambra Blvd. btwn E. St & Broadway
Alta Valley Way North B St. between N Th St. & 16th St.
American River Dr. between Howe Ave. & Munroe St. Northgate Blvd.
Arcade Blvd. between Marysville Blvd. & Marconi Ave. Norwood Ave.
Arden Way P St. between 2nd St. & Stockton Blvd.
Arena Blvd Pocket Road
Azevedo Dr. Point West Way
Broadway Power Inn Road
Bruceville Road Q St. between 2nd St. & Alhambra Blvd.
Capitol Ave. between 15th St. & Folsom Blvd. Raley Blvd.
Carlson Dr. Response Road
Center Parkway Richards Blvd.
Challenge Way Rio Linda Blvd.
College Town Dr. Riverside Blvd.
Connie Dr. between Roseville Road & Marconi Ave. Roseville Road
Cosumnes River Blvd. Royal Oaks Dr.
Del Paso Blvd. south of Marysville Blvd. San Juan Road
Del Paso Rd. Seamas Ave. east of Riverside Blvd.
E St. between 7th St. & Alhambra Blvd. South Land Park Dr.
East Commerce Way South Watt Ave.
El Camino Ave. Sproule Ave.
Elder Creek Road Stockton Blvd.
Elsie Ave. Sunbeam Ave.
Elvas Ave. between 56th St. & 65th St. Sutterville Road
Ethan Way T St. between 34th St. & 39th St.
Evergreen St. Truxel Road
Exposition Blvd. University btwn Campus Commons & Fair Oaks.
Fair Oaks Blvd. Valley Hi Dr. between Franklin Blvd. & Mack Road
Florin Perkins Road W St. between 3rd St. & 29th St.
Florin Road West EI Camino Ave.
Folsom Blvd. Windbridge Dr.
Franklin Blvd. Winding Way
Freeport Blvd. X St. btwn 3 rd St. & Alhambra Blvd
The above definition of “Primary Streets” may be modified at any time
upon written notice to Contractor by City, as the City Traffic Engineer deems
necessary.
6-11 HOLIDAY SEASON CONSTRUCTION MORATORIUM
During the holiday season, construction will be suspended on Holiday
Season Moratorium Streets (defined below) unless otherwise approved in writing
by the City Traffic Engineer. “Holiday season” means the period of time
beginning on Thanksgiving Day and ending on the first regular working day
following New Year’s Day.
6-11
No new work that would interfere with traffic during the holiday season
shall begin on any Holiday Season Moratorium Streets after November 1. All
existing conditions within any Holiday Season Moratorium Streets shall be
restored to their original or better condition prior to the start of the holiday
season, and all unauthorized steel plates, barricades, and barriers shall be
removed from all traffic lanes.
Contractor may submit a written request to work within any Holiday
Season Moratorium Streets during the holiday season. The request shall specify
the time, date, and description of the work to be performed in the Holiday
Season Moratorium Streets and the full extent of Contractor’s proposed lane and
sidewalk closure. The City Traffic Engineer will decide whether to approve,
conditionally approve or deny such request, in whole or in part, in the City Traffic
Engineer’s sole discretion.
Emergency repairs to any Holiday Season Moratorium Streets are
permitted during the holiday season, provided that Contractor notifies the
Engineer at least one (1) hour in advance during working hours. If the emergency
arises during non-working hours, Contractor shall notify the Engineer before 9:00
a.m. the following workday. Any emergency repairs performed by Contractor
shall otherwise comply with the Contract Documents and all applicable Laws or
Regulations.
“Holiday Season Moratorium Streets” are defined as follows:
12
th
Avenue between Martin Luther King, Jr. Boulevard and Sutterville Road
21
st
Street between 4
th
Avenue and G Street
24
th
Street, between (Knight Way and Meadowview Rd) and (W Street and 2
nd
Avenue)
55
th
Street south of Fruitridge Road
Alta Arden Expressway
Arden Way
Broadway
Challenge Way
Del Paso Boulevard south of Marysville Blvd
El Camino Avenue
Ethan Way
Evergreen Street
Exposition Boulevard
Fair Oaks Boulevard
Florin Boulevard
Folsom Boulevard
Franklin Boulevard
Freeport Blvd, within one block of all its side streets between Broadway and Blair Ave
Fruitridge Road between Rickey Dr and 59th Street
Greenhaven Drive between Havenhurst Dr and Windbridge Dr
H Street
Heritage Lane
Howe Avenue
J Street
6-12
La Mancha Way
Mack Road
Marconi Avenue
Marysville Boulevard between Del Paso Boulevard and Bell Avenue
Meadowgate Dr between Munson Way and Franklin Boulevard
Meadowview Road
Munson Way
Natomas Boulevard
Northgate Boulevard
Point West Way
Power Inn Road
Response Road
Royal Oaks Drive
San Juan Road
Stockton Blvd, and w/in one block of all its side streets from Perry Ave to the south City limits
Truxel Road
Valley Hi Drive north of Wyndham Way
West El Camino Avenue
The definition of “Holiday Season Moratorium Streets” may be modified
at any time upon written notice to Contractor, as the City Traffic Engineer deems
necessary.
In addition to the above listed streets, no work shall be performed during
the holiday season on any street in the area bounded by the American River on
the north, the Sacramento River on the west, one block south of Broadway on
the south, and 34
th
Street on the east, without obtaining permission in writing
from the City Traffic Engineer.
6-12 CONTRACTOR NOT AN AGENT OF CITY
During the term of the Contract, Contractor shall be an independent
contractor and shall not under any circumstances be considered an employee,
agent, or other representative of the City. Contractor is not authorized to bind
City to any obligation. Nothing in this Contract creates any relationship of joint
venture, partnership or any other association of any nature whatsoever between
City and Contractor other than that of owner and independent contractor. City
has the right to control Contractor only insofar as provided in this Contract and
only insofar as the results of Contractor’s work pursuant to the Contract. The
City’s right of supervision does not reduce or abrogate Contractor’s liability for
any and all damage or injury to persons, public property or private property that
may arise directly or indirectly from Contractor’s performance of the Work.
6-13 APPROVAL OF CONTRACTOR’S PLANS NO RELEASE FROM LIABILITY
The approval by the Engineer of any drawing or any method of work
proposed by Contractor does not relieve Contractor of responsibility for any
errors and is not an assumption of risk or liability by City or any City officer or
6-13
employee. Contractor has no claim under the Contract on account of the failure
or partial failure or inefficiency of any plan or method so approved. Such
approval by the Engineer merely means that the Engineer has no objection to
Contractor’s using, at Contractor’s sole responsibility and risk, the plan or
method Contractor proposes.
6-14 CONTRACTOR SHALL NOT MORTGAGE EQUIPMENT
Contractor shall not mortgage or otherwise convey the title of the plant,
machinery, tools, appliances, supplies, or materials that may at any time be in
use, or further required or useful, in the performance of the Contract, without
prior written consent of the Engineer.
6-15 PROPERTY RIGHTS IN MATERIALS
Contractor is not vested with any right of property in the materials used
after they have been attached, or affixed to the Work, and on which partial
payments have been made by City. All such materials shall be the property of
Contractor and City jointly as their interests may appear, and may not be
removed from the Work by Contractor without the consent of City.
6-16 USE OF EXPLOSIVES
Explosives shall not be used on the Work unless permission to use them is
granted by the Engineer in writing, and only then under such conditions as may
be prescribed by the Engineer and in compliance with all applicable Laws or
Regulations.
6-17 CONTRACTOR’S LEGAL ADDRESS
At Contractor’s on site office, Contractor shall provide a representative
authorized to receive drawings, samples, notices, letters, instructions,
explanation or other communications or articles from City. Drawings, samples,
notices, letters, instructions, explanations, or other articles or communications
may be mailed or personally delivered either to Contractor’s address given in the
Proposal, or to Contractor’s representative at the site of the Work, or to
Contractor’s office at the site of the Work. The delivery at any of these places
of any such item from City to Contractor shall be deemed sufficient service upon
Contractor, and the date of such service shall be the date of mailing or personal
delivery. The address given in the Proposal may be changed by notice in writing
from Contractor to City. Nothing herein contained shall be deemed to preclude
or render inoperative the service of any drawing, sample, notice, letter,
instruction, explanation, article or communication to or upon any authorized
representative of Contractor personally.
6-14
6-18 ON STREET PARKING REMOVAL
In performing the Work, Contractor shall minimize the inconvenience to the
public and shall only place “No Parking” signs in areas where parking clearly needs
to be removed to safely perform the Work. “No Parking” signs shall be 11” by 17”
inches, with red letters on white construction paper or other material approved
by the Engineer, and shall comply with all applicable Laws or Regulations. “No
Parking” signs shall be neat and clean, and clearly indicate the specific times
and dates when parking is to be prohibited. “No Parking” signs shall be securely
fastened to barricades, and not placed on trees, utility poles, or other facilities
not approved by the Engineer.
Contractor shall maintain the “No Parking” signs and barricades prior to and
during the course of the Work. Contractor shall verify three days prior to
commencing the Work, and continuously during the course of the Work, that the
signs and barricades are adequately visible and properly placed.
The Engineer may arrange for vehicles that interfere with the Work to be
towed. No vehicles parked in a “No Parking” area will be towed without
acceptable documentation that the signs and barricades are properly placed, and
no towing is allowed unless the Engineer determines that a reasonable person
would have been able to determine that parking is not allowed. If Contractor
requests towing of a vehicle, Contractor shall include in such request written
documentation indicating that the “No Parking” barricades were placed at least
seventy-two (72) hours in advance of the start of Work, and Contractor shall
provide a photograph of the vehicle to be towed, showing the nearest “No
Parking” sign. Contractor shall reimburse City for any payment of a claim filed
against the City for the towing of any vehicle without the Engineer’s approval or
acceptable documentation as provided herein.
In Non-Metered Areas
Seventy-two (72) hours prior to the start of Work, Contractor shall place
“No Parking” signs on approved barricades at fifty (50) to sixty (60) foot
intervals.
In Metered Parking Areas
Contractor shall obtain permission to remove parking stalls from the City
Parking Division not less than three (3) working days before the start of construction
and shall be responsible for the payment of parking removal fees pursuant to
applicable provisions of the Sacramento City Code. It is recommended that
Contractor consult with the City’s Parking Division to obtain an estimate of the
fees.
If Contractor pays the applicable fees and the removal of parking stalls is
approved by City, seventy-two (72) hours prior to the start of Work, Contractor
6-15
shall place “No Parking” signs adjacent to every third parking stall to be
removed, when an entire block of parking is to be removed. Contractor shall
move these signs into every third parking stall at the beginning of the workday, in
conjunction with the covering of parking meters for all stalls to be removed. If
Contractor only needs to remove a portion of parking stalls on a block, every stall
removed shall be barricaded with a “No Parking” sign in conjunction with the
covering of parking meters for all stalls to be removed. Contractor shall comply
with any other conditions specified by the City for such parking stall removals.
In addition to the foregoing, Contractor shall comply with all applicable
requirements of the Sacramento City Code pertaining to on-street parking removal.
6-19 MAIN AND TRUNKLINE UTILITIES
The City is a member of the Underground Service Alert (U.S.A.) one-call
program. Contractor or any Subcontractor must notify the U.S.A. at least two (2)
working days, but not more than fourteen (14) calendar days, in advance of
performing excavation work as provided in Government Code Section 4216.2, and
Contractor shall comply with all other applicable requirements specified in
Article 2 of Division 5 of the Government Code, commencing with Section 4216.
Contractor is responsible for the timely removal, relocation or protection
of any existing main or trunkline utility facilities located on the Work site and
identified on any of the Contract Documents in their approximate location
(defined below). Subject to the provisions of this Section, City is responsible for
the timely removal, relocation or protection of any existing main or trunkline
utility facilities located on the Work site that are not identified in any Contract
Documents in their approximate location. This does not require City to indicate
the presence of existing service laterals or appurtenances whenever the
presence of existing service laterals on the site can be inferred from the
presence of other visible facilities, such as buildings, meter and junction boxes,
valves, service facilities, identification markings and other indicators, on, or
adjacent to, the Work site. Contractor is responsible for the timely removal,
relocation or protection of such service laterals.
If existing main or trunk line utility facilities on the Work site need to be
located or repaired, or removed and relocated, or protected, and the subsurface
main or trunk line utility facilities were not identified in any of the Contract
Documents at their approximate location, and any damage occurring to such
main or trunk line facilities was not due to the failure of Contractor or any
Subcontractor to use reasonable care, City shall pay for the cost of locating and
repairing, or removing and relocating, or protecting such main or trunk line
utility facilities. A subsurface main or facility is deemed to be in the
“approximate location” shown on the Contract Documents if the main or facility
or any portion of it is located within a strip of land extending twenty-four inches
6-16
(24”) on either side of the location for the exterior surface of the main or facility
shown on any of the Contract Documents. “Approximate location” does not refer
to the depth of the subsurface main or facility.
The City’s obligation to pay in instances of a discovery of main or trunk
line facilities on site in the circumstances described above is limited strictly to
the costs described above and for any equipment on the site of the Work
necessarily idled as a result of such circumstances.
In the event the completion of the project is delayed by (1) City’s failure
to provide for the repair, removal, relocation or protection of an existing main
or trunk line utility facility not identified in its approximate location on any of
the Contract Documents, or (2) failure by another owner of an existing main or
trunk line utility facility to provide for the repair, removal, relocation or
protection of such main or facility, except in cases where Contractor is
responsible under the Contract for causing such repair, removal, relocation or
protection to occur, then such delay shall be an Excusable Delay as that term is
defined in the Contract Documents.
Nothing in this section relieves a utility from a contractual or legal
obligation to pay the cost of removal or relocation of existing utility facilities.
For facilities owned by a public utility, the public utility has the sole discretion
to perform repairs or relocation work or permit Contractor to do such repairs or
relocation work at a reasonable price. Nothing in this section precludes City
from pursuing any appropriate remedy against the utility for delays that are the
responsibility of the utility.
If, after commencing the Work, Contractor discovers existing main or
trunk line utility facilities located on the site of the Work that were not identified
on any of the Contract Documents in their approximate location, Contractor shall
immediately notify the Engineer and the owner of the utility facility in writing
by the most expeditious means available.
6-20 ITEMS CONTAINING TRADE SECRETS OR PROPRIETARY RIGHTS PROHIBITED
Neither Contractor nor any Subcontractor shall furnish any item or
combination of items to which, or in which, Contractor or any Subcontractor or
Supplier claims any trade secret or proprietary right. City shall own without
restriction all items furnished under this Contract. Such items shall include but
not be limited to, any item assembly, combination of items, process, electrical
or mechanical or electro-mechanical or microprocessor process or program, or
any combination or sequence of these items. Neither Contractor nor any
Subcontractor shall furnish any item or combination of items pursuant to this
Contract containing any program or programmable item without first obtaining
the written consent of the Engineer, that may be withheld or conditioned in any
6-17
manner determined to be in the best interest of the City by the Engineer in the
Engineer’s sole discretion. In the event of any conflict between the provisions of
this Section and Section 5-18 (“Trade Names and Alternatives”), the provisions
of this Section shall prevail.
7-1
Section 7
PROSECUTION AND PROGRESS
7-1 ASSIGNMENT
The Contract may be assigned only upon written consent of the City, and
also with the consent of Contractor’s Sureties.
7-2 WORK SCHEDULE AND ADEQUATE RESOURCES
Contractor shall perform the Work under this Contract with all materials,
tools, machinery, apparatus, and labor necessary to the complete and timely
execution of everything described, shown or reasonably implied under this
Contract on or before the Contract Completion Date.
Contractor shall give full information to the Engineer as to Contractor’s
plans for carrying on any part of the Work before commencing that Work.
Contractor shall submit to the Engineer prior to the pre-construction meeting or
as otherwise required in the Special Provisions a detailed achievable schedule
for the various items of Work and for completion of the Work as a whole, using
the critical path method (CPM) or other format acceptable to the Engineer. If
such schedule is not accepted in writing by the Engineer, Contractor shall revise
and resubmit the schedule as necessary to obtain the Engineer’s written
acceptance. If at any time during performance of the Work the Engineer notifies
Contractor that its latest accepted schedule is not reasonable or does not
accurately reflect the current progress or sequence of Work, Contractor shall
revise and resubmit an updated schedule within five (5) working days of the
Engineer’s notification. If such updated schedule is not accepted in writing by
the Engineer, Contractor shall revise and resubmit the schedule as necessary to
obtain the Engineer’s written acceptance. Notwithstanding any contrary
provision of the Contract Documents, Contractor is not entitled to claim any
damages or compensation for any delay caused by the City unless Contractor’s
claim of City-caused delay is substantiated by an accurate CPM schedule
accepted by the Engineer indicating the Controlling Operation(s) and sequence
of Work, that Contractor submitted to the City prior to the occurrence of the
delay.
The schedule(s) required by this section shall show the order in which
Contractor proposes to carry out the Work, the total float period, the logical
relationships between Work activities, the critical path, the dates on which
Contractor will commence the different tasks comprising the Work (including
procurement of materials, plant, and equipment), and the contemplated dates
for completing such tasks.
7-2
The schedule(s) submitted shall be consistent in all respects with the
completion time requirements and any order of work requirements indicated in
the Contract.
Subsequent to the time that submittal of a schedule is required in
accordance with these Specifications, no progress payments will be made for any
Work until such schedule has been submitted to the Engineer.
If at any time before the beginning or during the progress of the Work,
any part of Contractor’s plant, or equipment, or any of Contractor’s methods of
execution of the Work, appear to the Engineer to be unsafe, inefficient, or
inadequate to insure the required quality or rate of progress of the Work, the
Engineer may order Contractor to increase or improve its facilities or methods,
and Contractor shall promptly comply with such orders at no cost to the City;
but neither compliance with such orders nor failure of the Engineer to issue such
orders shall relieve Contractor from its obligation to secure the degree of safety,
the quality of the Work, and the rate of progress required of Contractor under
the Contract Documents. Contractor alone is responsible for the safety,
adequacy, and efficiency of its plant, equipment, and methods.
7-3 WORK UNDER UNFAVORABLE WEATHER AND OTHER ADVERSE CONDITIONS
During unfavorable weather and other adverse conditions, Contractor
shall pursue only such portions of the Work as will not be damaged by the
weather or other adverse conditions. If the quality or efficiency of any portions
of the Work will be affected by any unfavorable conditions, such portions shall
not be performed while those conditions exist, unless Contractor can overcome
these conditions by special means or precautions approved by the Engineer.
7-4 SATURDAY, SUNDAY, HOLIDAY, AND NIGHT WORK
No work shall be done between the hours of 6 p.m. and 7 a.m., nor on
Saturdays, Sundays or legal holidays, except such work necessary for the proper
care and protection of work already performed or except in case of emergency
or special situation, and in any case only with the permission of the Engineer or
as specified in the Special Provisions.
Notwithstanding the foregoing, if Contractor first requests and obtains
the written permission of the Engineer, Contractor may establish different hours
of work as a regular procedure, as specifically approved by the Engineer.
However, the Engineer may revoke such permission at any time for any reason.
If such off-period work is approved, Contractor shall comply with any and all
conditions established for such work by the Engineer at Contractor’s own cost
and expense, and Contractor shall pay any and all costs incurred by the City in
7-3
connection with such off-period work, including but not limited to the Citys
costs to inspect such work.
7-5 SEPARATE CONTRACTS
City reserves the right to let other contracts in connection with the
project. Contractor shall afford other contractors reasonable opportunity for
the introduction and storage of their materials and the execution of their work
and shall properly connect and coordinate Contractor’s work with theirs.
If any part of Contractor’s Work depends for proper execution or results
upon the work of any other contractor, Contractor shall inspect and promptly
report to the Engineer any defects in such work that render it unsuitable for such
proper execution or results. Contractor’s failure to inspect and report any
defects in the work shall constitute an acceptance of the other contractor’s work
as fit and proper for the reception of Contractor’s Work, except as to defects
not arising from the Contractor’s Work that may develop in the other
contractor’s work after the execution of Contractor’s Work.
7-6 REMOVAL OF UNSATISFACTORY EMPLOYEES
Contractor and Contractor’s Subcontractors shall, on the site of the Work,
employ only competent persons skilled in their respective lines of work.
Whenever the Engineer notifies Contractor that any person employed by or
representing Contractor or any Subcontractor on the Work is, in the Engineer’s
opinion, incompetent, unfaithful or disorderly, or refuses to carry out the
provisions of this Contract, or uses threatening or abusive language to or
otherwise threatens or abuses any City employee or representative or any
member of the public, or is otherwise unsatisfactory, Contractor shall remove or
require its Subcontractor to remove the person from the Work and shall not
return that person to the Work unless approved by the Engineer.
7-7 PROTECTION OF WORK, PERSONS AND PROPERTY AGAINST DAMAGE
Contractor shall protect the Work, all materials incorporated or to be
incorporated in the Work and all equipment used in connection with the Work,
whether located on or off the Work-site, and all public and private improvements
and facilities within the site of the Work, from damage due to the nature of the
Work, the action of the elements, trespassers, vandalism, fire or any other cause
whatsoever, until the completion and City acceptance of the Work. The City does
not have or assume any responsibility for collecting indemnity from any person
or persons causing damage to the work or property of Contractor. Any and all
costs incurred by Contractor to protect the Work, materials, equipment,
improvements and facilities as provided above shall be included in Contractor’s
7-4
Proposal and Contractor shall not be entitled to any additional compensation or
damages from City.
Contractor shall furnish such guards, fences, warning signs, walks, and
lights as is necessary, or as may be ordered by the Engineer, and shall take all
other necessary precautions to prevent damage or injury to persons or property.
Existing public and private improvements including utilities and adjacent
properties shall be protected from potential damage resulting from the
operations of Contractor or any Subcontractor. Typical improvements to be
protected include, but are not limited to: trees, shrubbery, fences, walls,
existing pavement, sidewalks, street improvements and underground utilities
that are either to be, or not to be, removed under the Contract.
All existing street signage, markings and striping damaged as a result of
construction shall be replaced in kind by Contractor, to the satisfaction of the
Engineer. In the case of partial damage, the whole stripe or marking in its
entirety shall be replaced. Temporary marking and striping shall be installed
within 3 working days of any damage.
All painted or other markings, such as Underground Service Alert (USA)
markings, on the pavement, sidewalk or gutters used for constructing the project
shall be removed by Contractor before final acceptance of the Work.
If public or private improvements are damaged by the operations of
Contractor or any Subcontractor, the damaged improvements shall be replaced
or restored at Contractor’s expense to pre-damage condition.
Any underground facility not shown on the Plans does not relieve
Contractor of the responsibility to appropriately notify USA in order to determine
the location of underground facilities, or to exercise sound judgment when
working in the vicinity of known, visible or reasonably ascertainable underground
facilities. It is Contractor’s responsibility to ascertain the location of those
underground facilities that may be subject to damage by reason of Contractor’s
operations.
7-8 TIME OF COMPLETION
Contractor shall complete all Work within the time set forth in the
Agreement.
Contractor shall not be charged for a working day on which the Engineer
determines, that as a result of inclement weather or conditions resulting from
the weather, Contractor is or was prevented from engaging in the current
Controlling Operation or Operations of the Work with its normal labor and effort
for at least five (5) hours of the day.
7-5
The current Controlling Operation or Operations mean any feature of the
Work (e.g., an operation or activity, or a settlement or curing period) that, if
delayed or prolonged, will necessarily delay the time of completion of the entire
Work, as determined by the Engineer based on Contractor’s most recent schedule
that has been accepted by the Engineer.
The Engineer will furnish Contractor a weekly statement showing the
number of working days charged to the Contract for the preceding week, the
number of working days of time extensions being considered or approved, the
number of working days originally specified for the completion of the Contract
and the extended date for completion, if any, except when working days are not
being charged in accordance with the provisions in Section 7-9 “Temporary
Suspension of Work.” Contractor is allowed 15 calendar days from the date of
the Engineer’s issuance of the weekly statement of working days in which to file
a written protest of the Engineer’s determination of working days; otherwise the
weekly statement is deemed accepted by Contractor as correct.
7-9 TEMPORARY SUSPENSION OF WORK
The Engineer has the authority to suspend the performance of the Work
wholly or in part, for such period as the Engineer deems necessary, due to
unsuitable weather, or for such other conditions as are considered unfavorable
for the suitable prosecution of the Work, or for such time as the Engineer may
deem necessary due to the failure on the part of Contractor or any Subcontractor
to carry out orders, or to satisfactorily perform any provision of the Contract.
Contractor shall immediately comply with the written order of the Engineer to
suspend the Work wholly or in part. The suspended Work shall be resumed when
conditions are favorable or methods are corrected, as ordered or approved in
writing by the Engineer.
If a suspension of Work or any portion of the Work is ordered by reason of
the failure of Contractor or any Subcontractor to carry out orders or to
satisfactorily perform any portion of the Contract, or by reason of weather
conditions being unsuitable for performing any item or items of Work, which
items, in the opinion of the Engineer, could have been performed prior to the
occurrence of such unsuitable weather conditions had Contractor diligently
prosecuted the Work in accordance with the Contract when weather conditions
were suitable, Contractor shall perform at its own expense all the work necessary
to (i) preserve and protect the Work and related facilities and improvements
from weather and other environmental conditions during the period of
suspension, (ii) repair any damage to the Work and/or related facilities and
improvements occurring before, during or after the period of suspension, and
(iii) provide a safe, smooth, and unobstructed passageway through construction
for use by public traffic and any other public use during the period of suspension.
7-6
In the event Contractor fails to timely perform such Work, the City may perform
such work and the cost of the Work will be paid by Contractor or will be deducted
from moneys due or to become due Contractor under the Contract.
Except as may be provided otherwise in the Contract Documents, if the
Engineer orders a suspension of all or a portion of the Work, or a portion of the
Work that is the current Controlling Operation or Operations, by reason of
unsuitable weather conditions, and in the opinion of the Engineer the suspension
is not due to the failure of the Contractor or any Subcontractor to carry out
orders or to satisfactorily perform any portion of the Contract nor due to the
Contractor’s failure to diligently prosecute the Work in accordance with the
Contract prior to such suspension, Contractor shall perform all work necessary
to (i) preserve and protect the Work and related facilities and improvements
from weather and other environmental conditions during the period of
suspension, and (ii) provide a safe, smooth, and unobstructed passageway
through construction for use by public traffic and any other public use during the
period of suspension, provided that the cost of such work shall, upon approval
by the Engineer, be paid for as extra work as provided in Section 4-4 above, or,
at the option of the Engineer, all or a portion of such work shall be performed
by the City at no cost to Contractor.
If the Engineer orders a suspension of all of the Work, or a portion of the
Work that is the current Controlling Operation or Operations, due to unsuitable
weather or due to such other conditions that the Engineer considers unfavorable
to the suitable prosecution of the Work, and in the opinion of the Engineer the
suspension is not due to the failure of the Contractor or any Subcontractor to
carry out orders or to satisfactorily perform any portion of the Contract nor due
to the Contractor’s failure to diligently prosecute the Work in accordance with
the Contract prior to the suspension, the days on which the suspension is in effect
shall not be considered working days. If a portion of Work at the time of such
suspension is not a current Controlling Operation or Operations, but subsequently
becomes the current Controlling Operation or Operations, the determination of
working days will be made on the basis of the current Controlling Operation or
Operations.
If a suspension of all or a portion of the Work is ordered by the Engineer,
due to the failure on the part of Contractor or any Subcontractor to carry out
orders given or to satisfactorily perform any provision of the Contract, or by
reason of weather conditions being unsuitable for performing any item or items
of Work, which items, in the opinion of the Engineer, could have been performed
prior to the occurrence of such unsuitable weather conditions had Contractor
diligently prosecuted the Work in accordance with the Contract when weather
conditions were suitable, the days on which the suspension order is in effect shall
be considered working days unless such days are not working days pursuant to
Section 1-48(1) of these Specifications.
7-7
A suspension of Work under any of the conditions set forth in this Section
shall not relieve Contractor of its responsibilities under the Contract Documents.
This Section 7-9 does not apply to any suspension of work to protect the health,
safety, welfare or condition of persons or property pursuant to Section 5-13 of
these Specifications.
7-10 DETOURS
Contractor shall construct and remove detours and detour bridges for the
use of public traffic as provided in the Special Provisions, or as shown on the
Plans, or as directed by the Engineer. Payment for such work shall be made as
set forth in the Special Provisions, or, if not addressed there, at the Contract
prices for the items of work involved if such prices are specified in the Contract.
If not addressed in the Special Provisions and no such prices are specified in the
Contract, all detours shall be constructed and removed at no additional charge
by Contractor.
Contractor shall pay all costs of repairing damage to detours caused by
public traffic.
When public traffic is routed through the Work, Contractor’s obligation to
provide for a safe passageway through construction operations shall not be
considered to constitute construction or maintenance of a detour and Contractor
shall not be entitled to any additional payment therefor, unless otherwise
specified in the Special Provisions.
Detours constructed by Contractor exclusively for Contractor’s or any
Subcontractor’s own use and convenience for hauling materials and equipment
shall be constructed and maintained by Contractor at its own expense.
The failure or refusal of Contractor to construct and maintain adequate
detours at the proper time and in satisfactory condition for use by public traffic
shall be sufficient cause for closing down the Work until the Engineer determines
that such detours have been constructed and are in satisfactory condition for use
by public traffic. Contractor is solely responsible for all costs incurred to repair
any damage to any detour caused by Contractor’s or any Subcontractor’s hauling
or other activity.
8-1
Section 8
MEASUREMENT AND PAYMENT
8-1 MEASUREMENT OF QUANTITIES
The Engineer shall determine quantities of Work acceptably completed
under the terms of the Contract, or as directed by the Engineer in writing, based
on measurements taken by the Engineer or the Engineer’s assistants. In
computing quantities, the length, area, solid content, number, weight or time
in standard units, as the case may be, shall be computed as specified in the
Contract. All earth excavation shall be computed to the neat lines and grades
as set and directed by the Engineer and shall be computed in relation to the
original undisturbed condition.
8-2 SCOPE OF PAYMENT
The compensation provided by the Contract constitutes full payment for
all materials, supplies, equipment, tools, labor, and all incidentals necessary to
complete the Work; for performing all work and services contemplated and
implied by the Contract; for loss or damage arising from the nature of the Work,
or from action of the elements; from unforeseen difficulties that may be
encountered during the performance of the Work; for all risks of every
description connected with the performance of the Work, and for any
infringement of patent, trademark, or copyright; and for completing the Work
according to the Contract Documents.
For unit price items, payment for those items at the unit price bid by
Contractor constitutes full payment for all work and services related to such
items, except as otherwise specified in the Contract Documents. For any work
or services required to perform the Work that are not specifically described in
the Contract Documents, Contractor will include payment for such work and
services under the bid of any item(s) that Contractor deems appropriate and
City shall not pay additional compensation for any such work or services. No
payment shall be made for materials stored on- or off-site until such materials
are properly installed and incorporated in the Work.
8-3 PAYMENT ON ENGINEER’S CERTIFICATE
City shall make no payment pursuant to the Contract until the Engineer
certifies that such payment is due on account of Work done and material
furnished in accordance with the Contract.
8-2
8-4 COMPLETION OF WORK AND FINAL PAYMENT
1. Issuance of Punchlist
A punch list may be issued when the Engineer determines as provided
below, that the work is “substantially complete” as that term is defined in
Section 1 of these Specifications. The Engineer may issue a punch list on the
Engineer’s own initiative or in response to Contractor’s request. If Contracto4r
believes the Work is substantially complete and requests issuance of a punch
list, the following provisions shall apply:
a. Contractor shall submit to the Engineer a written request for
issuance of a punch list. Contractor also shall provide any
information relating to the Work that may be requested by the
Engineer after receiving Contractor’s request. The Engineer shall
request such information, if any, not later than five (5) working
days after receiving Contractor’s request for issuance of a punch
list.
b. After reviewing the request and information and performing such
other investigations, inspections or reviews necessary to ascertain
the condition or status of the Work, the Engineer, in the Engineer’s
sole discretion, shall either (1) issue a punch list, or (2) notify
Contractor in writing that the Work is not yet substantially
complete, and include a list of items of the Work that are not yet
complete and have more than minor deficiencies. Unless
otherwise agreed by the parties, the Engineer shall take one of the
above actions within ten (10) working days after receiving
Contractor’s request for issuance of a punch list, or, if the
Engineer requests information, within ten (10) working days after
the Engineer receives such information. Any subsequent requests
by Contractor for issuance of a punch list shall be made in
accordance with the provisions of this Section.
The City may issue one or more punch lists, as determined necessary or
appropriate by the Engineer. The issuance of a punch list is solely for purposes
of identifying items of the Work that have minor deficiencies, and shall not
modify or otherwise affect the meaning, application or operation of any
provision of the Contract Documents, including but not limited to any warranty,
liquidated damages or termination provisions.
2. Final Acceptance of the Work
Final acceptance occurs when the Engineer determines that the entire
Work is complete. The Engineer may make this determination on the Engineer’s
8-3
own initiative or in response to Contractor’s request. If Contractor believes the
entire Work, including all punch list work, is complete and requests final
acceptance, the following provisions shall apply:
a. Contractor shall submit to the Engineer a written request for final
acceptance. Contractor shall provide any information relating to
the condition or status of the Work as requested by the Engineer.
The Engineer shall request such information, if any, not later than
five (5) working days after receiving Contractor’s request for final
acceptance.
b. After reviewing such request and information and performing such
other investigations, inspections or reviews as may be necessary
to ascertain the condition or status of the Work, the Engineer, in
the Engineer’s sole discretion, shall either (1) issue final
acceptance establishing the date of completion of the entire
Work, or (2) notify Contractor in writing that the entire Work is
not yet complete, and include a list of items of the Work that are
deficient. Unless otherwise agreed by the parties, the Engineer
shall take one of the above actions within ten (10) working days
after receiving Contractor’s request for final acceptance, or, if the
Engineer requests information, within ten (10) working days after
the Engineer receives such information. Any subsequent requests
by Contractor for final acceptance shall be made in accordance
with the provisions of this Section. The date of completion of the
entire Work determined by the Engineer shall be specified in any
Notice of Completion filed pursuant to Civil Code Section 3093.
Completion of the Work shall not be deemed to occur under the Contract
for any purpose until the Engineer determines the date of completion as
provided above.
3. Final Payment
After determining the date of completion, the Engineer shall make a final
estimate of the amount and value of Work performed under the Contract If
necessary, the Engineer shall prepare a balancing Change Order. The Engineer
shall send the final estimate to Contractor with a balancing Change Order, if
required, for Contractor’s review and signature.
Not later than fifteen (15) calendar days after receiving the final
estimate and balancing Change Order, if any, Contractor shall either (1) sign
the final estimate and balancing Change Order, if any, and return them to the
Engineer, or (2) notify the Engineer in writing of any disagreement with the final
estimate. If Contractor fails within this time period to either return the signed
8-4
final estimate and balancing Change Order, if any, or notify the Engineer in
writing of any disagreement with the final estimate, this is deemed acceptance
by Contractor of the Engineer’s final estimate and balancing Change Order (if
any).
After Contractor’s signature or acceptance of the final estimate and
balancing Change Order, if any, the City may approve the final payment amount
and execute the balancing Change Order, if any, in accordance with applicable
approval requirements of the Sacramento City Code. If Contractor timely
notifies the Engineer in writing of a disagreement with the final estimate, if
such disagreement is not resolved fifteen (15) calendar days after the Engineer
receives such notification, the City may unilaterally approve a final payment
amount and execute a balancing Change Order, if required, in accordance with
applicable approval requirements of the Sacramento City Code. The unilateral
approval by the City does not affect Contractor’s right to seek additional
compensation, if any, but only to the extent authorized under other provision(s)
of the Contract Documents.
The City’s final payment consists of the entire sum found to be due by
the Engineer after deducting all previous payments and all amounts charged
against or withheld from Contractor under any provision of the Contract
Documents or any Laws or Regulations, and all amounts retained under the
provisions of the Contract. All prior partial estimates and payments are subject
to correction in the final estimate and payment. The City’s release of any
amounts charged, withheld or retained at the time of final payment are not
considered a “final payment” as the term is used herein.
No payment made under the Contract constitutes acceptance by City of
any defective work or improper materials.
8-5 ASSIGNMENT OF CLAIMS
Contractor shall not assign any right to any portion of the moneys that
may become due or may be claimed to become due to Contractor under the
Contract without the written approval of the City. No person other than the
party signing the Contract shall have any claim arising from the Contract, except
as specifically provided in these Specifications.
8-6 PAYMENTS BY CONTRACTOR
1. Contractor shall provide all labor, services, materials, and equipment
necessary to perform and complete the Work under the Contract. Except
as otherwise approved by City, Contractor shall: (1) pay in full for
transportation and utility services on or before the 20
th
day of the month
following the calendar month in which such services are rendered; and,
8-5
(2) pay for at least 90% of the cost off all materials, tools, and other
expendable equipment, on or before the 10
th
day after payment by City
of any progress payment relating to those costs.
2. In the absence of other provisions in the Contract applicable to any
Subcontractor, Contractor shall pay each Subcontractor, within ten (10)
days after each payment City makes Contractor, the sum allowed in such
payment for and on account of the Work performed by the Subcontractor,
to the extent of the Subcontractor’s interest therein, as required by
Section 7108.5 of the California Business and Professions Code.
3. In addition to other responsibilities specified in the Contract Documents,
Contractor is responsible for payment of:
a. Restaking costs resulting from loss of stakes and survey markers
due to Contractor’s or any Subcontractor’s negligence;
b. Repeat testing of soils and materials when the previous testing
results failed to meet the requirement(s) specified in the Contract
Documents; and
c. Overtime inspection costs when the Engineer determines the
overtime inspection was performed primarily to benefit
Contractor.
8-7 RELEASE AT TIME OF FINAL PAYMENT
If requested by City, as a condition precedent to final payment,
Contractor and each assignee under any assignment approved in accordance
with the Contract Documents and in effect at the time of final payment, shall
execute and deliver a release in form and substance satisfactory to City that
discharges City, its officers, agents and employees of and from all liability,
obligations and claims arising under the Contract, provided that disputed
Contract claims in stated amounts may be specifically excluded by Contractor
from the operation of the release pursuant to Public Contract Code Section
7100, but only to the extent that Contractor has complied with all procedures
and requirements applicable to the presentation and processing of such claim(s)
under the Contract Documents.
8-8 EXTRA WORK A PART OF THE CONTRACT
If extra work is ordered or authorized by the City in accordance with the
Contract, such work is a part of the Contract and subject to each and all of its
terms and conditions.
8-6
8-9 INSPECTION AND PAYMENTS NO WAIVER OF CONTRACT PROVISIONS
No inspection, order, measurement, approval, modification, certificate,
payment, acceptance of work or material (including, but not limited to,
acceptance of the entire Work), extension of time or possession of any part of
or the entire Work shall operate as a waiver of any of the terms and conditions
of the Contract, the powers reserved in the Contract to the City, or any right of
City to damages or to reject work in whole or part. No waiver of any breach of
the Contract constitutes a waiver of any other or subsequent breach. All
remedies provided in the Contract are cumulative and in addition to all other
rights and remedies that may exist at law or in equity.
8-10 PAYMENT BY COST AND PERCENTAGE
Payment by cost and percentage shall be made as follows:
1. For all materials purchased by Contractor and used in the specific portion
of the Work, Contractor shall receive the actual cost of such materials
including freight charges, as shown by original receipted bills for material
and freight, to which shall be added an amount equal to fifteen percent
(15%) of the sum.
2. For all labor of any class including foremen engaged in the specific
portion of the Work, Contractor shall receive the prevailing wage and
fringe benefits (not including payroll taxes) paid for each hour such labor
is engaged in the specific work, in accordance with the following method
of calculation:
1.33 [(hourly wage + fringes) + 0.24 (hourly wage + fringes)]
3. For any Contractor-owned machine, power machinery and equipment
deemed necessary and desirable to use on the specific portion of the
Work, Contractor is allowed a rental price equivalent to the current
Caltrans rental rate (less any state mark-ups) +15%. For machines and
equipment rented by Contractor, a rental price, fully maintained, must
be agreed upon by City and Contractor in writing before the specific work
is begun, for each hour such machines and equipment are used, to which
shall be added no percentage. If a rental price is not agreed to in writing
as specified herein the current Caltrans rental rate shall be used.
4. Where extra work under cost and percentage is being performed by a
Subcontractor, Contractor is allowed a five percent (5%) surcharge on the
combined total of (1), (2), and (3) above for work performed by the
Subcontractor. This surcharge is only allowed to Contractor and not to
any Subcontractors.
8-7
Contractor shall keep and present to the City in such form as the Engineer
may direct, complete and correct documentation of the net cost of all labor and
materials subject to the provisions of this Section.
No claim for payment for extra work, whether done by cost and
percentage or otherwise, can be honored unless the Engineer has given prior
written authority and permission for such work.
9-1
Section 9
(RESERVED)
10-1
Section 10
CONSTRUCTION MATERIALS
This Section describes various classes and types of materials used in public
construction within the City of Sacramento. Materials to be used for the work
and not included in this section shall be described and specified in the Special
Provisions.
10-1 PORTLAND CEMENT
Unless otherwise specified in the Special Provisions, all cement used in
concrete shall conform to ASTM C 150 and these Specifications, and shall be Type
II, unless otherwise specified herein.
ASTM C 150, Type III, Portland cement shall be used for concrete requiring
high early strength where specifically required by the Special Provisions.
Type II and Type III Portland cements shall be “low alkali” containing not
more than 0.60 percent by weight of alkalies, calculated as the percentage of
Na
2
O plus 0.658 times the percentage of K
2
0.
When directed by the Engineer, Contractor shall furnish certificates of
compliance stating that the cement delivered to the work complies with these
Specifications.
10-2 CONCRETE AGGREGATES
Unless otherwise specified in the Special Provisions all concrete
aggregates shall conform to ASTM C 33, except that grading requirements shall
be as specified in Section 10-5 of these Specifications.
10-3 WATER FOR CONCRETE
Water used for mixing concrete and water used for curing concrete shall
be clean, free from oil, acid, alkalies, vegetable matter, or other deleterious
matter. No water containing excessive amounts of salts, sulphates, or chlorides
shall be used.
10-4 PREFORMED EXPANSION JOINT FILLER
Unless otherwise specified in the Special Provisions, preformed expansion
10-2
joint filler material shall conform to ASTM D 1751.
10-5 PORTLAND CEMENT CONCRETE
1. Composition:
Portland cement concrete (referred to herein as concrete) shall be
composed of Portland Cement, fine aggregate, coarse aggregate, admixtures if
used, and water.
Concrete shall be designated as one of the following classes:
Class “A” Concrete shall contain six (6) sacks (564 pounds) of Portland
cement per cubic yard and shall have a maximum size of coarse aggregate of one
and one-half inches (1½").
Class “B” Concrete shall contain six (6) sacks (564 pounds) of Portland
cement per cubic yard and shall have a maximum size of coarse aggregate of one
inch (1")
Class “C” Concrete shall contain five (5) sacks (470 pounds) of Portland
cement per cubic yard and shall have a maximum size of coarse aggregate of one
inch (1”).
Class “D” Concrete shall contain five (5) sacks (470 pounds) of Portland
cement per cubic yard and shall have a maximum size of coarse aggregate of
three-quarters inch (¾").
When approved by the Engineer, fly ash conforming to ASTM C 618 may be
used to replace up to 20 percent of the Portland cement requirement for Class
A and B concrete except that fly ash shall not replace Portland cement for
concrete used to pave alleys.
Should the quantity of ingredients designed to produce a cubic yard of
finished concrete result in a yield greater than one cubic yard, the relative
proportions of fine and coarse aggregates shall be adjusted as necessary to
maintain a constant quantity of Portland cement in each cubic yard of concrete.
Contractor shall determine the mix proportions for all concrete to be used
in the work. A mix design for each class of concrete used in the work shall be
submitted to the Engineer for approval at least five (5) working days prior to the
proposed concrete being incorporated into the work.
10-3
10-5 PORTLAND CEMENT CONCRETE (cont.)
2. Proportioning:
The coarse and fine aggregates shall be combined in such proportions
that the percentage composition by weight of the individual and primary sizes of
aggregates and of the combined aggregates, as determined by laboratory screens
and sieves, will be as follows:
GRADING AND COMPOSITION REQUIREMENTS
Sieve
Size
Designation and Nominal Size
Percentage Passing Sieves
Primary Aggregate Sizes
Combined Aggregate Sizes
1½x
1" x
Fine
1½"
1"
¾"
¾"
No. 4
Max.
Max.
Max.
2"
1½"
1"
¾"
⅜"
No. 4
No. 8
No. 16
No. 30
No. 50
No. 100
No. 200
100
88-100
1-59
0-17
0-7
--
--
--
--
--
--
0-2
--
100
88-100
37-100
0-53
0-16
0-6
--
--
--
--
0-2
--
--
--
--
100
95-100
65-95
45-85
25-55
10-35
2-10
0-5
100
90-100
50-86
45-75
38-55
30-45
23-38
17-33
10-22
4-9
1-3
0-2
--
100
90-100
55-100
45-75
35-60
27-45
20-35
12-25
5-15
1-5
0-2
--
--
100
90-100
60-80
40-60
30-45
20-35
13-23
5-15
1-5
0-2
In addition to the above required grading analysis in the primary aggregate
size, the distribution of the fine aggregate sizes shall be such that the difference
between the total percentage passing the No. 16 sieve and the total percentage
passing the No. 30 sieve shall be between 10 and 40; and the difference between
the percentage passing the No. 30 and No. 50 sieves shall be between 10 and 40.
Exact proportions of primary aggregate sizes used in the concrete mix
shall be as designated and/or approved by the Engineer. The Engineer may
adjust the mix to accommodate changes in aggregates and moisture contents, to
improve mixing and placing characteristics and to secure maximum quality of
the finished concrete.
10-4
10-5 PORTLAND CEMENT CONCRETE (cont.)
3. Mixing:
All concrete mixing shall be done in machine batch mixers of an approved
type, having a capacity of not less than a full one-sack batch, unless the quantity
to be mixed is, in the opinion of the Engineer, too small to justify the use of a
batch mixer. Sacks of cement shall be completely emptied by dumping directly
upon other materials previously measured into the mixer, and no splitting of
sacks of cement will be allowed, except where Contractor provides suitable
equipment approved by the Engineer, the cement may be weighed into the batch
from bulk storage.
Mixing shall continue for not less than one (1) minute and in mixers larger
than one cubic yard capacity this minimum shall be increased so that minimum
mixing time shall not be less than one (1) minute for each cubic yard or part
thereof of mixer capacity.
Where transit mixers are used, the mixing period shall conform to the
requirements of ASTM C 94.
The total volume of material mixed per batch shall not exceed the rated
capacity of the mixer as determined by the standard requirements of the
Associated General Contractors of America. All mixing equipment shall be
operated at the speeds recommended by the manufacturer, provided, however,
that the revolving drum type, except on transit mixers, shall not make less than
fourteen (14) or more than eighteen (18) revolutions per minute, and that the
rotation rate of transit mixing drums be such as to produce a peripheral speed
of approximately two hundred feet (200’) per minute. Each paving mixer or
stationary mixer shall be equipped with an acceptable timing device.
Should Contractor elect to utilize transit mixing equipment, he shall make
adequate advance arrangements for preventing delays in delivery and placing of
the concrete. An interval of more than forty-five (45) minutes between any two
consecutive batches or loads, or a delivery and placing rate of less than eight (8)
cubic yards of concrete per hour, shall constitute cause for shutting down the
work for the remainder of the day, and if so ordered by the Engineer, Contractor
shall make at his own expense, a construction joint at
the location and of the type directed by the Engineer, in the concrete already
placed.
Transit-mixed concrete shall be delivered to the site of the work and
discharge shall be completed within ninety (90) minutes after the addition of the
cement to the aggregates or before the drum has been revolved 250
10-5
10-5 PORTLAND CEMENT CONCRETE (cont.)
revolutions, whichever comes first. In hot weather or under conditions
contributing to quick stiffening of the concrete or when the temperature of the
concrete is 85 F. or above, the time between the introduction of the cement to
the aggregates and discharge shall not exceed forty-five (45) minutes.
A ticket showing volume of concrete and the mix number shall accompany
each batch of transit-mixed concrete delivered to the job site. The ticket shall
also show the time of day at which the materials were batched.
4. Placing:
The placing of the concrete from a stationary or transit mixer must be
done in such a manner as to avoid separation of constituent materials of the
concrete. The Engineer shall have the right to stop concrete pouring if the
placing of the concrete is improper in this respect.
5. Water Control:
Within the limits hereinafter specified, the amount of water required for
the proper consistency of concrete shall be determined by the slump test in
accordance with ASTM C 143, except that the ratio of weight of water (water
cement ratio) shall not exceed 0.55 unless otherwise approved by the Engineer.
The allowance for slump, unless otherwise directed by the Engineer, shall
be as follows:
a. concrete paving and reinforced structures (heavy sections), not
more than three inches (3");
b. reinforced structures (thin sections) and columns, not more than
four inches (4");
concrete placed under water, not less than six inches (6") nor more
than eight inches (8").
No additional mixing water shall be incorporated into the concrete during
hauling or after arrival at the delivery point, unless authorized by the Engineer.
If the Engineer authorizes additional water to be incorporated into the concrete,
the drum shall be revolved not less than 30 revolutions at mixing speed after the
water is added and before discharge is commenced.
10-6
10-5 PORTLAND CEMENT CONCRETE (cont.)
If mixing in transit is allowed, the control equipment as above specified
shall be at the proportioning plant and there shall be no water added after the
mixture leaves the plant, unless directed by the Engineer.
Contractor shall furnish, without charge, such materials as may be
required for making tests of concrete during the progress of the work. Such tests
will be made at the expense of the City of Sacramento, except that, if tested
concrete does not meet required standards, the cost of additional testing shall
be borne by Contractor.
No concrete shall be used which has partially set, and no concrete shall
be re-tempered or remixed.
10-6 CURING COMPOUNDS FOR CONCRETE
Concrete curing compounds shall be used where specified in these
Specifications and the Special Provisions. The compounds shall conform to the
requirements of Section 90, “Concrete,” of the State Specifications.
10-7 AGGREGATE BASES
Aggregate bases shall conform to the requirements of Section 26 of the
State Specifications, except as modified herein.
The combined aggregate shall conform to the grading specified for the
three-quarter inch (¾") maximum aggregate for Class 2 aggregate base, unless
otherwise specified in the Special Provisions. Aggregate may include material
processed from reclaimed asphalt concrete, Portland cement concrete, lean
concrete base, cement treated base or a combination of any of these materials.
The amount of reclaimed material may constitute up to 100% of the total volume
of the aggregate used.
Aggregate base will be paid for at the contract price bid per ton or per
cubic yard delivered to the job and placed according to the Plans and
Specifications. The method used on any work will be shown by the list of
quantities on the Proposal and by the type of unit price requested in the
Proposal.
The weight of material to be paid for will be determined by deducting
from the weight of material delivered to the work, the weight of water in the
material, at the time of weighing, as determined by California Test 226, in excess
of one (1) percentage point more than the optimum moisture content as
determined by ASTM D 1557. The weight of water deducted as provided in this
Section will not be paid for.
10-7
Quantities of aggregate base to be paid for by the ton or cubic yard will
be calculated on the basis of the dimensions shown on the plans adjusted by the
amount of any change ordered by the Engineer. No allowance will be made for
aggregate base placed outside said dimensions unless otherwise ordered by the
Engineer.
The above prices and payment shall be full compensation for furnishing
all labor, material, tools, equipment, water, and incidentals, and for all work
involved in constructing aggregate base complete in place as shown on the Plans,
and as specified in these Specifications and the Special Provisions or as directed
by the Engineer.
10-8 AGGREGATE SUBBASE (GRADED)
Aggregate subbase shall conform to the requirements of Section 25 of the
State specifications. Aggregate subbase shall be Class 1, unless otherwise
approved by the Engineer.
Payment for aggregate subbase shall be per ton of material delivered to
the job and placed in accordance with the Plans and Special Provisions. The
weight of material to be paid for will be determined by deducting from the
weight of material delivered to the work, the weight of water in the material,
at the time of weighing, as determined by California Test 226, in excess of one
(1) percentage point more than the optimum moisture content as determined by
ASTM D 1557. The weight of water deducted as provided in this Section will not
be paid for.
The compacting of the material shall be done in accordance with the
requirements for placing aggregate bases, as provided in these Specifications.
Payment for the material at a price per ton or cubic yard shall constitute
full compensation for furnishing, hauling, placing, compacting, and finishing the
material including the furnishing of all labor, material, tools, equipment, water
and incidentals.
10-9 CEMENT TREATED BASES
Road-mixed and plant-mixed cement treated bases shall conform to the
requirements of Section 27 of the State Specifications.
Measurement and payment for cement treated bases shall be in
accordance with the State Specifications or may be paid for at a price per ton or
cubic yard of cement treated base complete in place as so indicated in the
Special Provisions.
10-8
10-10 LIME STABILIZATION
Lime stabilization shall conform to the requirements of Section 24 of the
State Specifications, except as modified herein.
Unless otherwise specified in the Special Provisions or approved by the
Engineer the amount of lime to be added shall constitute a minimum of four and
one-half percent (4.5%) by unit weight of the material to be stabilized.
10-11 TREATED PERMEABLE BASES
Treated permeable bases shall conform to the requirements of Section 29
of the State Specifications.
10-12 GEOGRID
Geogrid may be used in areas requiring soil stabilization, such as
unsuitable subgrade, or as specified in the Special Provisions, or as approved by
the Engineer. Geogrid material shall conform to the following requirements
unless otherwise specified in the Special Provisions.
The reinforcement material shall be biaxially oriented geogrid with high
tensile modulus in relation to the material being reinforced, with large
apertures, thick ribs and junctions to permit significant mechanical interlock
with the material being reinforced, and with high continuity of tensile strength
through all ribs of the structure.
The geogrid shall maintain its reinforcement and interlock under normal
construction practices, and be resistant to both ultraviolet degradation and all
forms of biological degradation normally encountered in the material being
reinforced. Geotextiles shall not be accepted as reinforcing material. The
geogrid shall be installed per the manufacturers recommendations and as
specified in the Special Provisions. Grid ties shall be installed a maximum of
twenty feet apart and overlaps shall be a minimum of two feet, unless otherwise
approved by the Engineer.
The geogrid shall be a single-layer grid that meets the dimensions and
properties outlined below. Multi-layered grids fastened together shall not be
acceptable. The biaxial geogrids shall conform to the property requirements
listed below:
10-9
Property
Test Method
Units
Value
Mass
ASTM D
5261-92
oz/sy
8.75 (nom)
Tensile
Peak Tensile MD (a)
GRI GG1
lb/ft
1,200 (min)
Tensile at 5% MD
GRI GG1
lb/ft
810 (min)
Peak Tensile CMD (b)
GRI GG1
lb/ft
1,970 (min)
Tensile at 5% CMD
GRI GG1
lb/ft
1,340 (min)
Stiffness
Torsional Stiffness
Corps of
Engineers
cm-kg/de
g
6.5 (min)
Flexural Stiffness True
Initial
ASTM D 1388
mg-cm
750,000 (min)
Modulus in Use MD (c)
GRI GG1 (b)
lb/ft
20,500 (min)
True Initial Modulus in
Use CMD (c)
GRI GG1
lb/ft
30,000 (min)
Interlock
MD dimension
I. D. Calipered
in
0.75-1.50
CMD dimension
I. D. Calipered
in
0.75-1.50
Open area (d)
COE Method
Modified
%
70 (min)
Junctions
Efficiency
GRI GG2
%
90 (min)
Strength MD
GRI GG2
lb/ft
1,080 (min)
Strength CMD
GRI GG2
lb/ft
1,778 (min)
(a) MD - Machine Direction which is along roll length
CMD - Cross Machine Direction which is across the roll width.
(b) Resistance to in-plane rotational movement measured by
applying a 20 cm-kg moment to the central junction of a 9" x 9"
specimen restrained at its perimeter. (U.S. Army Corps of
Engineers Methodology).
(c) True resistance to elongation when initially subjected to a load
measured via GRI-GG1 without deforming test materials under load
before measuring such resistance or employing “secant” or “offset
tangent methods of measurement so as to overstate tensile
properties.
(d) Percent open area measured without magnification by Corps of
Engineers method as specified in CW 02215 Civil Works Construction
Guide, November 1977.
10-10
Stress transfer capability through junctions (i.e. material overlaps). The
value of the Peak Tensile Strength CMD multiplied by Junction Efficiency shall
be greater than 1,080 lb/ft.
10-13 BEDDING SAND
Bedding Sand shall have a minimum sand equivalent of 50. Ninety to one
hundred percent (90-100%) shall pass the #4 sieve and a maximum of fifteen
percent (15%) shall pass the #200 sieve. Sand material shall be of a good quality
with a minimum resistivity of 5,000 ohm-cm., a minimum pH of 6.0, a maximum
chloride concentration of 300 ppm and a maximum sulfate concentration of 1,000
ppm.
Chemical
Analysis
ASTM Method
Conductivity
D 1125
Sulfate
D 516A (SM 4500)
PH
D 2976/D 4972/G 51
Chlorides
D 512C
10-14 CRUSHED SCREENINGS
In these Specifications, in the Special Provisions, or on the Plans, the use
of crushed screenings may be specified for certain purposes. When so specified
this shall mean a uniformly graded material that is the product of crushing rock
or gravel; free of organic matter, oil, alkali, or other deleterious substances and
is hard, sound and durable.
Unless otherwise indicated in the Special Provisions, the crushed
screenings shall conform to the requirements for Class 1 Permeable Material
Type A as set forth in Section 68 of the State Specifications.
10-15 SLURRY CEMENT BACKFILL
Slurry Cement Backfill specified herein for use as trench backfill shall
conform to the requirements of Section 19 of the State Specifications and must
be a fluid workable mixture of aggregate, cement, and water.
Slurry cement backfill may be used as structure backfill only for pipe
culverts.
10-11
10-16 CONTROL DENSITY FILL (CDF)
Control Density Fill (CDF), also known as Controlled Low Strength Material
(CLSM) or Ready Mixed Flowable Fill (RFF) as processed and distributed by the
National Ready Mixed Concrete Association and referred to herein as CDF type
materials), may be used as an alternate initial backfill and/or trench backfill
material, if approved by the Engineer, or if specified in the Special Provisions.
CDF type materials may only be used as an alternate trench backfill material
above the initial backfill material if approved in writing by the engineer and the
material supplier submits strength tests performed in accordance with either
ASTM C31 & C39 or ASTM D4832 that show the mix consistently has a 28-day
compressive strength not exceeding 150 psi. Separate approval by the Engineer
of CDF type materials as specified herein is not required for filling abandoned
pipelines.
Hand Excavatable: Material shall be a hand excavatable mixture of
cement, aggregate, entrained-air admixture, and water mixed in accordance
with ASTM C 94. The 28-day compressive strength shall not exceed 150 psi unless
otherwise directed or approved in writing by the Engineer when used for trench
backfill above the initial backfill zone.
Flowable: Material shall be flowable with a high slump, non-segregating
consistency that readily flows and fills voids, congested areas, difficult to reach
places, and that may additionally be used for pipe abandonment, structure
backfill, and structure cavity fill as directed.
Rapid Set: Material shall obtain early strength gain, to allow traffic load
or other live loads on the fill in less than one (1) day after placing the material.
Cement: Shall be type I or II in accordance with ASTM C 150. Mix designs
consisting of up to equal parts cement and Type F pozzolan conforming to ASTM
C618 may be submitted for consideration.
Pozzolan: Shall be added to improve flowability and shall be type F in
accordance with the requirements of ASTM C 618.
Aggregate: Coarse aggregate, if used, shall consist of well graded mixture
of crushed rock with a maximum size aggregate of inch. 100% shall pass the
½-inch sieve. Not more than 30% shall be retained by the ⅜ inch sieve and not
more than 12% shall pass the number 200 sieve. Mix designs consisting of sand
only with no coarse aggregate may be submitted for consideration. All aggregate
shall be free from organic matter and not contain more alkali, sulfates, or salts
than the native materials at the site of work.
Admixtures: Air entrainment admixture shall be added (minimum of 8%,
maximum of 20%) to improve workability in accordance with ASTM C 260.
10-12
Water: Shall be potable, clean, and free from silty organic matter, alkali,
salts, or other impurities.
Compressive Strength: The minimum 28 day compressive strength shall be
20 psi and the maximum shall be 150 psi.
Mixing, transporting and placing CDF type materials shall be in accordance
with ACI 304 and ACI 304.6R. Prior to placement, the trench shall be free of
loose soil and the trench bottom shall be stable and non-yielding with no excess
moisture. The pipe haunch areas shall be clear so that the CDF type material
will readily flow around the pipe. Place CDF type material simultaneously on
both sides of the pipe to minimize potential lateral displacement of the pipe.
Also, pipe sections may need to be secured against floating during CDF type
material placement, or place the material in lifts to reduce the potential for
flotation. Commence placement of granular trench backfill above CDF type
initial backfill only when overlying material placement and compaction will not
cause deformation of the initial backfill.
10-17 CLEAN CRUSHED ROCK
In these Specifications, on the Plans, or in the Special Provisions, the use
of clean crushed rock may be specified for certain purposes. When so indicated
on the Plans or in the Special Provisions, a clean crushed rock of the type
indicated shall be provided which is the product of crushing rock or gravel.
Clean crushed rock shall have a minimum Cleanliness Value of sixty (60)
as determined by California Test 227, and the portion of the material which is
retained on the -inch sieve shall contain at least fifty percent (50%) of particles
having three (3) or more fractured faces. The percentage composition by weight
of clean crushed rock shall conform to the following gradations for the Type
specified.
10-13
% Passing Sieves
Sieve
Size
Type A
Type B
Type C
Type D
2"
--
--
--
100
1½"
--
--
100
--
1"
--
100
90-100
--
¾"
100
70-100
30-60
0-17
½"
90-100
30-60
0-20
--
⅜"
20-60
0-20
0-6
0-7
No. 4
0-15
0-5
0-5
--
No. 200
0-2
0-2
--
0-2
10-18 ASPHALT BINDERS AND ASPHALTIC EMULSIONS
Asphalt binders and asphaltic emulsions as required by these
Specifications or by the Special Provisions shall mean respectively the asphalt
binders as specified in Section 92 of the State Specifications and asphaltic
emulsions as specified in Section 94 of the State Specifications.
10-19 SEWER AND DRAINAGE PIPE
1. Joints
Unless otherwise specified herein, sewer and drain pipes shall have
elastomeric gasket joints providing a water tight seal. An exception to this
requirement is fusion welded solid wall HDPE. Any leakage in solid wall, fusion
jointed HDPE means that a joint is faulty and must be repaired at the
contractor’s expense.
2. Manhole Connections
Unless otherwise specified, connecting a 24 inch or smaller inside
diameter pipe, not cast into the base of a manhole, shall be accomplished by
using a coring machine. The annular space between the outside of the pipe and
the manhole wall shall be sealed by using a flexible annular space filler such as
"Kor-N-Seal Cavity O-Ring" by NPC Inc. or approved equal. Such connection shall
be made in conformance with manufacturer’s recommendations.
Unless otherwise specified, connecting a pipe with an inside diameter
greater than 24 inch to a manhole shall be accomplished by cutting a hole into
10-14
the manhole and grouting in the pipe. The hole shall be no more than the pipe
outside diameter plus the thickness of the manhole wall. The annular space
between the outside surface of the pipe and the hole in the wall shall be filled
with non-shrink grout and the pipe shall be properly installed with an approved
water stop.
In the connection of the pipe to a drop inlet, the use of a coring machine
and flexible annular space filler are not required.
3. Deflection
For all flexible pipe and fittings, the minimum pipe stiffness at 5%
deflection shall be 46 PSI according to ASTM D 2412. All flexible conduits shall
be tested with a mandrel 5% smaller than the average inside diameter of the
pipe no sooner than 96 hours after placement of the backfill. Mandrel tests may
be performed by the City after a 6 month period of time at which time a
maximum deflection of 7-1/2% from the base I.D. will be allowed. The mandrel
used shall be the PHOS PVC Sewer Pipe Deflection Gauge or other deflection
gauge approved by the Engineer.
4. Drainage and Sewer Pipe Requirements
The requirements for the various types of pipe are summarized in the
following paragraphs:
a. Acrylonitrile-Butadiene-Styrene (ABS)
ABS gravity sewer pipe and fittings in sizes 4" & 6" shall conform to
ASTM D 2661. Eight inch (8") and larger in diameter shall conform to either
ASTM D 2751, SDR 23.5 or ASTM D 2680 (ABS composite pipe).
Joints shall be solvent cemented (SC). All Service connections shall
be installed with “Tee” fittings. Saddles are not approved. When the
sewer main is of a material other than ABS, the connection joint to the
sewer main shall be made with a flexible adapter manufactured by
FERNCO, or approved equal.
b. Closed Profile Poly Vinyl Chloride (CPPVC)
CPPVC pipe with integral bell and spigot joints shall conform to
ASTM F 1803. Joints shall be of the bell and spigot type with elastomeric
seals conforming to the requirements of ASTM D 3212. Gaskets shall be
factory installed and chemically bonded to the bell end of the pipe.
Gasket material shall conform to ASTM F 477 and shall be capable of the
same water tightness requirements as smooth or solid wall PVC pipe.
10-15
c. High Density Polyethylene (HDPE) Solid Wall Fusion Jointed
HDPE pipe shall be as manufactured by Phillips Drisco pipe, a
division of Phillips Petroleum company, or equal. The material shall be
listed by PPI (Plastic Pipe Institute, a division of the Society of the Plastics
Industry) in PPI TR-4 with a 73.4°F hydrostatic design basis of 800 psi. The
PPI listing shall be in the name of the pipe manufacturer and shall be
based on ASTM D 2837 and PPI TR-3 testing and validation of samples of
the pipe manufacturer’s production pipe.
Material Requirements - Pipe shall be high molecular weight, high
density polyethylene pipe and shall have a standard dimension ratio of
32.5 (SDR 32.5). The material shall have a standard PE code designation
of PE 3408 and have a cell classification of 345434C as described in ASTM
D 3350. The pipe shall contain no recycled compound except that
generated in the manufacturer’s own plant from resin of the same
specification from the same raw material pipe
The pipe shall be homogeneous throughout and free of visible
cracks, bubbles, holes, foreign inclusions or other injurious defects. It
shall be uniform in color, opacity, density, and other physical properties
and produced to the dimensions and tolerances specified in ASTM F 714.
The inside and outside surfaces shall be semi-matte or glossy in
appearance. Any pipe not meeting these criteria shall be rejected.
The polyethylene pipe manufacturer shall provide certification that
stress regression testing has been performed on the specific product. The
said certification shall include a stress life curve per ASTM D 2837. The
stress regression testing shall have been done in accordance with ASTM D
2837, and the manufacturer shall provide a product supplying a minimum
Hydrostatic Design basis (HDR) of 1,600 psi, as determined in accordance
with ASTM D 2837.
The manufacturer’s certification shall state that the pipe was
manufactured from one specific resin in compliance with these
specifications. The certification shall state the specific resin used, its
source, and list its compliance to these specifications.
Joints - All joints for the buried polyethylene pipe shall be of the
thermal butt fusion type or bolted flanges reinforced with stainless steel.
Fittings - Polyethylene fittings shall be of the same material as the
pipe and manufactured by the pipe manufacturer.
10-16
d. Polyvinyl Chloride (PVC)
PVC drain pipe and fittings, with at least eighteen inches (18”) of
cover to sub-grade, shall conform to ASTM D 3034 and ASTM F 679 and
shall be SDR 35 pipe with elastomeric gasket joints providing a watertight
seal.
PVC drain pipe and fittings, with less than eighteen inches (18”) of
cover to sub-grade, shall be class 100 SDR 25 or 26 pipe conforming to
AWWA C 900.
All joints shall be integral wall bell and spigot configuration,
factory formed. Pipes at joints are not to be inserted beyond “stop-mark”
on spigot end. All service connections shall be installed with “Tee”
fittings, gasketed “Tee” saddles with stainless steel bands, or other
approved tapping devices. Solvent welded “Wye” saddles are not
approved. All rubber rings shall conform to ASTM F 477.
e. Reinforced Concrete Pipe (RCP)
Reinforced concrete pipe shall conform to ASTM C 76 Class III, IV,
or V. The class of pipe will be shown on the Plans or indicated in the
Special Provisions. Sections of circular pipe with elliptical reinforcing shall
have the location of the minor axis of the reinforcing indicated by three
inch (3”) wide, waterproof, painted stripes on the inside and outside of
the pipe at the top and bottom, at least twelve inches (12”) long at each
end of the pipe section.
Joint materials for concrete pipe shall be rubber gasket joints
conforming to the requirements of ASTM C 443 and shall be flexible and
able to withstand expansion, contraction, and settlement. All rubber
gaskets shall be stored in as cool a place as practicable, preferably at 70º
F. or less, and in no case shall the rubber gaskets be exposed to the direct
rays of the sun.
Rubber gaskets, of the type requiring lubrication, shall be
lubricated with the lubricant recommended and supplied by the
manufacturer of the pipe.
f. Vitrified Clay Pipe (VCP)
Vitrified clay pipe shall conform to the specifications for extra
strength clay pipe as set forth in ASTM C 700.
Stoppers shall be used with branch pipes that are to be left
unconnected. Stoppers for branch pipes having flexible compression
joints may be either clay discs with flexible compression joints, factory
10-17
applied, that will mate with the branch joint; or a resilient material of
controlled design and dimensions for mating with the branch pipe to which
it is to be applied; or, of other material approved by the Engineer.
Wooden stoppers will not be accepted.
Joint materials for vitrified clay pipe shall be an approved type of
factory-made mechanical compression joint conforming to the
requirements of ASTM C 425. Banded rubber couplings and sleeves
conforming to ASTM C 425 are acceptable.
g. Corrugated Metal Pipe
Corrugated metal pipe may only be used for driveway culverts and
shall conform to ASTM A 760, Type 1 or 1R. Minimum depth of cover shall
be 6 inches.
h. Corrugated HDPE Pipe
Corrugated High Density Polyethylene (HDPE) pipe may only be
used for driveway culverts. HDPE pipe shall have smooth interior and shall
be Type S conforming to AASHTO M 252 for four inch (4”) through ten inch
(10”) diameter pipe and to AASHTO M 294 for twelve inch (12”) and larger
pipe. Provide Grade 2A2 gasketed joints in conformance with ASTM D
1056. Installation shall be in accordance with manufacturer’s standards
and ASTM D 2321. Minimum depth of cover shall be 12 inches.
i. Glass-Fiber-Reinforced Thermosetting-Resin Pipe
Unless indicated otherwise in the Special Provisions, Glass-Fiber-
Reinforced Thermosetting-Resin Pipe shall conform to the requirements
of ASTM D 3262 with a pipe stiffness designation C (36 psi).
10-20 SUBSURFACE DRAINS
Subsurface drains shall comply with Section 68 of the State Specifications.
10-21 RESERVED
10-22 FIELD ASSEMBLED PLATE CULVERT
Field assembled plate culverts shall conform to Section 67 of the State
Specifications.
10-18
10-23 REINFORCING STEEL
Reinforcing steel shall conform to Section 52, “Reinforcement”, in the
State Specifications. Unless otherwise provided by the Special Provisions, bar
reinforcement shall be deformed Grade 60 conforming to ASTM A 615, “Deformed
Billet-Steel Bars for Concrete Reinforcement”.
Welded steel wire fabric for concrete reinforcement shall conform to
ASTM A 185. The gauge of the wire and the dimensions of the mesh will be as
shown on the Plans or indicated in the Special Provisions.
10-24 CURB DOWEL AND TIE BARS
Dowel and tie bars for curbs shall conform to ASTM A 615. Grade 60 or
Grade 40 may be used at Contractor’s option.
10-25 CASTINGS FOR MANHOLES, COVERS, ETC.
Casting for manhole heads, covers, and other purposes shall be tough gray
iron, free from cracks, holes, swells and cold sheets, be of workmanlike finish,
and conform to ASTM A 48/A 48M, Class 30. The quality shall be such that a blow
from a hammer will produce an indentation on a rectangular edge of the casting,
without flaking or cracking the metal.
All castings are to be manufactured true to pattern and with satisfactory
fit of component parts. Round frames and covers shall have machined bearing
surfaces. All manhole covers which do not fit neatly and bear firmly in the ring
shall be rejected.
Alternate Castings for manhole covers
Where specified, casting shall be constructed of ductile iron in
conformance with ASTM A536A, Class 60-45-12. Castings shall match the
dimensions shown in Section 38. Cover shall be hinged and may or may not be
gasketed. Gasket shall be mechanically fitted to frame such that removal and
attachment can be accomplished without the use of tools and glue, per
manufacturer's instructions. Lid shall have a rated capacity in excess of H20
loading per AASHTO.
10-26 WATER PIPE Distribution (12 inch diameter & smaller)
Water Distribution System pipe shall be of the material type as indicated
on the Plans or specified in the Special Provisions and shall comply with AWWA
standards and NSF/ANSI Standard 61. All pipe shall be the regular product of a
firm which has successfully manufactured comparable pipe for at least three (3)
years.
10-19
Unless otherwise directed or approved:
12-inch diameter buried pipe shall be ductile iron only, and
12-inch diameter and smaller pipes placed on bridges shall be
liquid-epoxy lined and coated welded steel per AWWA C200 and
AWWA 210.
1. Ductile Iron Pipe
All ductile iron pipe shall conform to the following AWWA Standards as
listed below:
a. AWWA C 104 (ANSI A21.4), “Cement-Mortar Lining for Ductile-Iron
Pipe and Fittings for Water,” if cement-mortar lined.
b. AWWA C 111 (ANSI A21.11), “Rubber-Gasket Joints for Ductile-Iron
Pressure Pipe and Fittings.”
c. AWWA C 150 (ANSI A21.50), “Thickness Design of Ductile-Iron
Pipe.”
d. AWWA C 151 (ANSI A21.51), “Ductile-Iron Pipe, Centrifugally Cast,
for Water.”
Pipe shall comply with the following requirements:
a. Size 4, 6, 8, 12 inch diameter only
b. Laying Condition Type 5
c. Minimum Depth of Cover Three (3) feet for improved; four and
one-half (4 -1/2) feet
for unimproved
d. Working Pressure-150psi
e. Laying Length Minimum eighteen (18) foot nominal lengths with
allowable trim pipe lengths in accordance with AWWA C 151 and
special shorter lengths provided as required by the drawings.
f. Joints Push on or mechanical
g. Restrained Joints Bolted flanged connections, push-on locking
gasket such as “Field-Lok” gaskets as manufactured by U.S. Pipe,
push-on joint restraint such as “TR-Flex” as manufactured by U.S.
Pipe, wedge action joint mechanism such as “Megalug” as
manufactured by EBAA Iron, Inc. or approved equal.
h. Gasket Lubricant Minimum required plus 10% additional
10-20
i. Pressure Class-350
j. LiningsStandard thickness of cement w/ asphalt seal coat.
CoatingsMinimum one (1) mil thick petroleum asphaltic material.
k. Certification by Manufacturer Required
2. Polyvinyl Chloride Pipe
All polyvinyl chloride pipe in sizes ranging from four through eight inch
(4”-8”) shall conform to AWWA C 900 “Polyvinyl Chloride (PVC) Pressure Pipe,”
or AWWA C 909 “Molecularly Oriented Polyvinyl Chloride (PVCO) Pressure Pipe”.
Pipe shall be manufactured with cast iron outside diameters (CIOD) for all sizes.
Pipe shall comply with the following requirements:
a. Size 4, 6, 8, 12 inch diameter only
b. Class 150
c. Dimension Ratio 18
d. Laying Length 20 feet
e. Joints Integral bell and spigot joints conforming to the
requirements ASTM D 3139 with factory supplied elastomeric
gaskets meeting the requirements of ASTM F 477.
f. Restrained Joints Bolted flanged connections, Wedge action joint
mechanism such as “Megalug” as manufactured by EBAA Iron, Inc.
or approved equal.
g. Gasket LubricantMinimum required plus 10% additional
h. Each pipe length shall be marked showing the nominal pipe size and
O.D. base, the AWWA pressure class, the AWWA specification
designation, and the seal of the testing agency that verified the
suitability of the material.
10-27 WATER PIPE FITTINGSDistribution (12 inch diameter & smaller)
Water pipe fittings shall be of the material type as indicated on the Plans
or specified in the Special Provisions and comply with AWWA standards and AWSI
61. All fittings shall be the regular product of a firm which has successfully
manufactured comparable fittings for at least three (3) years.
10-21
All water pipe fittings shall be Ductile Iron and shall conform to the
following AWWA Standards:
1. AWWA C 104 (ANSI A21.4), “Cement-Mortar Lining for Ductile-Iron Pipe
and Fittings for Water,” if cement-mortar lined.
2. AWWA C 110 (ANSI A21.10), “Ductile-Iron and Gray-Iron Fittings for
Water.”
3. AWWA C 111 (ANSI A21.11), “Rubber-Gasket Joints for Ductile-Iron
Pressure Pipe and Fittings.”
4. AWWA C 153 (ANSI A21.53) “Ductile-Iron Compact Fittings for Water
Service.”
5. AWWA C 116 (ANSI A21.16) “Protective Fusion-Bonded Epoxy Coatings for
the Interior and Exterior surfaces of the Ductile-Iron and Gray-Iron Fittings
for Water Supply Service,” if fusion-bonded epoxy lined or coated.
Fittings shall comply with the following requirements:
1. Pressure Rating 250 psi minimum.
2. Coatings Exterior: Minimum one (1) mil thick petroleum asphaltic
material coated. Interior: Lined with standard thickness cement and
asphaltic seal coated. Or, exterior and interior: Minimum eight (8) mil
thick fusion bonded epoxy coated.
3. Joints Push-On, mechanical, or flange
4. Certification by manufacturer
5. Dimensions AWWA C 153 Compact Fittings are approved.
6. Bolts shall be carbon steel ASTM A 307, Grade B. Nuts shall be heavy hex
nuts conforming to ASTM A 563, Grade C3.
7. Rubber gaskets for flanged joints shall be full faced with a thickness of
eight of an inch (⅛”). The material used for the rubber gaskets shall be
hardness (Shore A) 70 to 85 suitable for a minimum of one hundred and
fifty pounds per square inch (150 psi), cold water service.
10-22
10-28 WATER PIPE Transmission (greater than 12 inch diameter)
Water Transmission System pipe shall be of the material type as indicated on the
Plans or specified in the Special Provisions and comply with AWWA standards and ANSI
61. All pipe shall be the regular product of a firm which has successfully manufactured
comparable pipe for at least three (3) years. Pipe shall conform to the following
requirements:
1. Welded Steel Pipe (WSP)
All welded steel pipe shall conform to the following AWWA Standards:
a. AWWA C 200, “Steel Water Pipe 6 in. and larger.”
b. AWWA M 11, “Steel Pipe A Guide for Design and Installation”
except as modified herein.
c. AWWA C 205, “Cement-Mortar Protective Lining and Coating for
Steel Water Pipe 4 in. and Larger Shop Applied.”
Pipe shall comply with the following requirements:
a. Pipe shall be designed for one hundred and fifty pounds per square
inch (150 psi) working pressure with an additional seventy-five
pounds per square inch (75 psi) allowance for surge. Pipe design
shall be in accordance with AWWA M 11 to withstand the
simultaneous application of external earth loads , HS-20 live load
and internal pressures. The minimum steel cylinder thickness shall
be ten (10) gauge. Drawings shall be submitted to the Engineer for
approval and shall include the following:
i. Pipeline layout showing stations and elevations;
ii. Details of standard pipe, joints, specials and fittings;
iii. Calculations for pipe design field welded joint restraint and
fittings reinforcement;
iv. Details of joint bonding and field welded joint restraint
calculations.
b. The nominal diameter or inside diameter of the pipe and other
fabricated steel sections as shown on the plans is the clear
diameter of the lined pipe after the application of the interior
mortar lining.
10-23
10-28 WATER PIPE Transmission (greater than 12 inch diameter) (cont.)
c. Each piece of pipe shall be hydrostatically tested and the stress in
the pipe during testing shall not be less than seventy-five percent
(75%) of the steel minimum yield strength.
d. Minimum Depth of Cover shall be three feet (3’) in improved and
four and a half feet (4½’) in unimproved areas.
e. Laying Length thirty-two to fifty feet (32’-50’), depending on the
shop practice of the manufacturer or fabricator, unless otherwise
required by the Contract Documents. Sufficient short pieces shall
be provided to allow for two foot (2’) adjustments within each one-
half mile of straight pipe.
f. Pipe End FinishThe end finish of individual lengths of pipe to be
provided under these Special Provisions shall be one of the
following types, unless otherwise indicated on the Plans:
i. Bell and spigot pipe ends for joints with rubber gaskets.
a. Bell and spigot pipe ends for field welded joints.
b. Plain-ends fitted for butt straps for field welded joints.
iv. Plain-ends fitted with flanges.
v. Plain-ends for mechanically coupled field joints.
The types of joints proposed to be used shall have been thoroughly tested
for water leaks at the design pressures. The Engineer may require Contractor to
furnish a record of experience in installing the types of joints for comparable
sizes of pipe called for on the Plans. Details of the type of pipe joints proposed
to be used shall be included with the shop drawings and lay sheets submitted for
the pipe.
Cement mortar lining and coating for WSP shall conform to AWWA C 205.
Field joints shall be lined and coated to match pipe in accordance with AWWA C
205.
Bell and Spigot Joints with Rubber Gaskets for WSP shall employ joint rings
(Carnegie rings) and shall be designed and fabricated to accommodate a rubber
0-ring gasket seal in accordance with AWWA C 303.
The field welding of WSP with bell and spigot joint rings (Carnegie rings)
or lap joints shall conform to Standard Drawing W-903. Lap joints shall conform
to AWWA C 200.
10-24
10-28 WATER PIPE Transmission (greater than 12 inch diameter) (cont.)
Field welded butt-strap joints shall typically only be used for closure
pieces and shall conform to Standard Drawing W-904. The ends of pipes to be
fitted with butt straps for field welded joints shall conform to AWWA C 200.
When field conditions warrant and with the approval of the Engineer,
straight butt strap welded joints may be used for directional changes in pipe
alignment of up to five (5°) degrees.
WSP pipe flanges shall conform and be fitted to plain-end pipe in
accordance with AWWA C 207, Class D, and AWWA C 200.
Rubber gaskets for flanged joints shall be full faced with a thickness of
eight of an inch (⅛”). The material used for the rubber gaskets shall be hardness
(Shore A) 70 to 85 suitable for a minimum of one hundred and fifty pounds
per square inch (150 psi), cold water service.
Bolts shall be carbon steel ASTM A 307, Grade B. Nuts shall be heavy hex
nuts conforming to ASTM A 563, Grade C3.
WSP ends for mechanically coupled field joints shall be plain and conform to
AWWA C 200 and these Standards Specifications. Mechanically coupled joints
shall conform to the material, dimensions, and tests of AWWA C 219.
All plain-end pipe joined by flexible couplings shall be fitted with stiffener
rings welded to the exterior pipe surface in a plane perpendicular to the axis of
the pipe.
Stiffener rings shall have minimum dimensions of three eights inch (⅜”)
thick by three inches (3”) in width. Stiffener rings that are to be integral with a
joint harness shall be suitably increased in thickness and reinforced with plate
gussets to adequately withstand the thrust from adjacent fittings. Stiffener rings
and harness rings or lugs shall be installed at the pipe manufacturing or
fabrication shop. Material for stiffener rings and plate gussets shall be carbon
steel meeting the requirements of ASTM A 36 or ASTM A 283, Grade D.
All mechanically coupled field joints shall be encased with eight (8) mil
minimum thickness polyethylene material.
Restrained Joints for WSP transmission lines shall conform to the
requirements set forth in AWWA M 11, “Steel Pipe - A Guide for Design and
Installation.” Joints shall be one of the following types:
10-25
10-28 WATER PIPE Transmission (greater than 12 inch diameter) (cont.)
a. Lap welded slip joint The joint shall conform to and be welded in
accordance with Standard Drawing W-903 in section 38 of these
Standard Specifications.
b. Double welded butt strap joint Butt straps shall conform to and
be welded in accordance with Standard Drawing W-904 in section
38 of these Standard Specifications.
c. Flanged and bolted Flanges shall be in accordance with AWWA C
207 Class D for operating pressures to one hundred and fifty pounds
per square inch (150 psi) and surge pressures to two hundred and
twenty five pounds per square inch (225 psi).
d. Mechanical coupling Mechanical couplings shall be as specified in
section 10-29 of these Standard Specifications and shall be
harnessed for the maximum pressure in accordance with AWWA M
11.
e. Carnegie end rings restrained by means of welding the bell and
spigot ring in accordance with Standard Drawing W-903 in section
38 of these Standard Specifications
Dimensions for standard and special fittings including tees, wyes, crosses,
bends and elbows, reducers, flanged side and bottom outlets, access manholes,
etc. shall conform to AWWA C 208. Materials and fabrication of standard and
special fittings shall conform to AWWA C 200. All fittings shall be designed to
have a strength at least equal to that of the adjacent straight pipe. Flanged
outlets shall be designed in accordance with the AWWA Design Manual M 11.
The required transverse steel area in all welded steel pipe fittings shall
be provided by the steel cylinder. The length of reducers shall not be less than
the diameter of the largest end.
Cement mortar lining and coating of fittings shall conform to the
applicable sections of AWWA C 205 and these Standard Specifications.
2. Concrete Cylinder Pipe (CCP)
All concrete cylinder pipe shall conform to the following:
a. AWWA C 303, “Concrete Pressure Pipe, Bar-Wrapped, Steel-
Cylinder Type.”
10-26
10-28 WATER PIPE Transmission (greater than 12 inch diameter) (cont.)
b. AWWA Manual M 9 “Concrete Pressure Pipe” except as modified
herein.
Pipe shall comply with the following requirements:
a. Pipe shall be designed for one hundred and fifty pounds per square
inch (150 psi) working pressure with an additional seventy-five
pounds per square inch (75 psi) allowance for surge. Pipe shall be
designed in accordance with ANSI/AWWA C 303, and AWWA Manual
M9 to withstand the simultaneous application of external earth
loads, HS-20 live load and internal pressures. Drawings shall be
submitted to the Engineer for approval and shall include the
following:
i. Pipeline layout showing stations and elevations;
ii. Details of standard pipe, joints, specials and fittings;
iii. Calculations for pipe design field welded joint restraint and
fittings reinforcement;
iii. Details of joint bonding and calculations.
b. The cylinders shall be true right cylinders formed from one piece
of sheet or coil steel. Field circumferential butt welds are not
acceptable.
c. Minimum steel cylinders shall be ten (10) gage.
d. The nominal diameter or inside diameter of the pipe and other
fabricated steel sections as shown on the plans is the clear
diameter of the lined pipe after the application of the interior
mortar lining
e. Laying Length thirty two to forty feet (32- 40’) for concrete
cylinder pipe depending on the shop practice of the manufacturer
or fabricator, unless otherwise required by the Contract
Documents. Sufficient short pieces shall be provided to allow for
two foot (2’) adjustments within each one-half mile of straight
pipe.
10-27
10-28 WATER PIPE Transmission (greater than 12 inch diameter) (cont.)
f. Pipe End Finish - The end finish of individual lengths of CCP to be
provided under these Standard Specifications shall be one of the
following types, unless otherwise indicated on the Plans:
i. Bell and spigot pipe ends for joints with rubber gaskets.
ii. Bell and spigot pipe ends for field welded joints.
iii. Plain-ends fitted for butt straps for field welded joints.
iv. Plain-ends fitted with flanges.
v. Plain-ends for mechanically coupled field joints.
The types of joints proposed to be used shall have been thoroughly tested
for water leaks at the design pressures. The Engineer may require Contractor to
furnish a record of experience in installing the types of joints for comparable
sizes of pipe called for on the Plans. Details of the type of pipe joints proposed
to be used shall be included with the shop drawings and lay sheets submitted for
the pipe.
The exposed inside and outside surfaces of the joints, flanges,
reinforcement lugs, and all other exposed steel shall be protected from the
formation of rust with an AWWA approved coating applied at the time of
manufacture or fabrication of the pipe.
The CCP ends shall employ joint rings (Carnegie rings) and shall be
designed and fabricated to accommodate a rubber 0-ring gasket seal in
accordance with AWWA C 303.
The field welding of CCP with bell and spigot joint rings (Carnegie rings)
or lap joints shall conform to the Drawing W-903, Section 38 of these Standard
Specifications. Lap joints shall conform to AWWA C 200.
Field welded butt-strap joints for CCP shall be typically used for closure
pieces and shall conform to Standard Drawing W-904. The ends of pipes to be
fitted with butt straps for field welded joints shall conform to AWWA C 200.
When field conditions warrant and with the approval of the Engineer,
straight butt-strap welded joints may be used for directional changes in pipe
alignment of up to five degrees (5°).
10-28
10-28 WATER PIPE Transmission (greater than 12 inch diameter) (cont.)
Steel pipe flanges for CCP shall conform and be fitted to plain-end pipe in
accordance with AWWA C 207, Class D, and AWWA C 200.
Rubber gaskets for flanged joints shall be full faced with a thickness of
eighth of an inch (⅛”). The material used for the rubber gaskets shall be hardness
(Shore A) 70 to 85 suitable for a minimum of one hundred and fifty pounds per
square inch (150 psi), cold water service.
Bolts shall be carbon steel ASTM A 307, Grade B. Nuts shall be heavy hex
nuts conforming to ASTM A 563, Grade C3.
CCP ends for mechanically coupled field joints shall be plain and conform
to AWWA C 200 and these Standard Specifications. Mechanically coupled joints
shall conform to the material, dimensions, and tests of AWWA C 219.
All plain-end pipe joined by flexible couplings shall be fitted with stiffener
rings welded to the exterior pipe surface in a plane perpendicular to the axis of
the pipe. Stiffener rings shall have minimum dimensions of three eighths inch
(⅜”) thick by three inches (3”) in width.
Stiffener rings that are to be integral with a joint harness shall be suitably
increased in thickness and reinforced with plate gussets to adequately withstand
the thrust from adjacent fittings. Stiffener rings and harness rings or lugs shall
be installed at the pipe manufacturing or fabrication shop. Material for stiffener
rings and plate gussets shall be carbon steel meeting the requirements of ASTM
A 36 or ASTM A 283, Grade D.
All mechanically coupled field joints shall be encased with eight (8) mil
minimum thickness polyethylene material.
Restrained Joints for CCP transmission lines shall conform to the
requirements set forth in AWWA M 9, "Concrete Pressure Pipe." Joints shall be
one of the following types:
a. Lap welded slip joint The joint shall conform to and be welded in
accordance with Standard Drawing W-903 in section 38 of these
Standard Specifications.
b. Double welded butt strap joint - Butt straps shall conform to and
be welded in accordance with Standard Drawing W-904 in section
38 of these Standard Specifications.
10-29
10-28 WATER PIPE Transmission (greater than 12 inch diameter) (cont.)
c. Flanged and bolted Flanges shall be in accordance with AWWA C
207 Class D for operating pressures to one hundred and fifty pounds
per square inch (150 psi) and surge pressures to two hundred and
twenty five pounds per square inch (225 psi).
d. Mechanical coupling Mechanical couplings shall be as specified in
section 10-29 of these Standard Specifications and shall be
harnessed for the maximum pressure in accordance with AWWA M
9.
e. Carnegie end rings restrained by means of welding the bell and
spigot ring in accordance with Standard Drawing W-903 in section
38 of these Standard Specifications.
Standard and special fittings for CCP shall include adapters, reducers,
bends, tees, wyes, connections to mainline valves, closures, beveled pipe,
restrained-joint pipe, short pipe, and pipe with outlets required for branches,
access manholes, air valves, and blow-offs. The fabrication and manufacture of
standard and special fittings shall conform to the requirements of Section 4 of
AWWA C 303.
3. Ductile Iron Pipe (DIP)
All ductile iron pipe shall conform to the following:
a. AWWA C 104 (ANSI A21.4), “Cement-Mortar Lining for Ductile-Iron
Pipe and Fittings for Water.”
b. AWWA C 110 (ANSI A21.10), " Ductile Iron and Gray Iron Fittings for
Water."
c. AWWA C 111 (ANSI A21.11), “Rubber-Gasket Joints for Ductile-Iron
Pressure Pipe and Fittings.”
d. AWWA C 150 (ANSI A21.50), “Thickness Design of Ductile-Iron
Pipe.”
e. AWWA C 151 (ANSI A21.51), “Ductile Iron Pipe, Centrifugally Cast,
for Water.”
f. AWWA C 153 (ANSI A21.53), "Ductile-Iron Compact Fittings for
Water Service."
10-30
10-28 WATER PIPE Transmission (greater than 12 inch diameter) (cont.)
g. AWWA M41, "Ductile-Iron Pipe and Fittings."
DIP shall also comply with the following requirements:
a. The minimum wall thickness design shall be determined using
AWWA C 150/A21.50.
b. The design working pressure shall be one hundred and fifty pounds
per square inch (150 psi) minimum.
c. When determining the wall thickness of the pipe, the following
shall be considered:
i. internal pressure, including static and transient pressure;
ii. external pressure, including trench loading and earth fill;
and
iii. practical considerations for handling, shipping, lining and
coating, or similar operations.
d. Nominal inside diameter shall not be less than the design diameter
or size specified.
e. Hydrostatic testing shall be made before the application of cement-
mortar lining.
f. Ductile iron pipe laying lengths shall be furnished in standard
lengths suited to the manufacturer's shop practice and in
accordance with AWWA C 151/A21.51. Sufficient field pieces shall
be provided to allow for a two foot (2’) adjustment - within each
one-half mile of straight pipe.
All DIP and fittings shall be cement-mortar lined in accordance with AWWA
C 104/A21.4.
Pipe shall be lined by a centrifugal process. Fittings shall be lined by a
projection method or by hand application.
The entire ductile iron pipeline including fittings, valves and
appurtenances shall be encased in polyethylene material with a minimum
thickness of eight (8) mil. The polyethylene shall conform to and be installed in
accordance with AWWA C 105/A21.5.
10-31
10-28 WATER PIPE Transmission (greater than 12 inch diameter) (cont.)
The end finish of individual lengths of DIP to be provided under these
Standard Specifications shall be one of the following types, unless otherwise
indicated on the Plans:
a. Bell and spigot pipe ends for joints with rubber gaskets.
b. Mechanically coupled field joints.
c. Plain-ends fitted with threaded flanges.
The types of joints proposed to be used shall have been thoroughly tested
for water leaks at the design pressures. The Engineer may require Contractor to
furnish a record of experience in installing the types of joints for comparable
sizes of pipe called for on the Plans. Details of the type of pipe joints proposed
to be used shall be included with the shop drawings and lay sheets submitted for
the pipe.
The exposed inside and outside surfaces of the pipe joints shall be
protected from the formation of rust with an AWWA approved coating applied at
the time of manufacture of the pipe.
Bell and spigot joints with rubber gaskets for DIP shall conform to the
requirements of AWWA C 111/A21.11 regarding push-on joints.
Mechanically coupled field joints, bolts and nuts for DIP shall conform to
the requirements of AWWA C 111/A21.11. All mechanically coupled field joints
shall be encased with a minimum eight (8) mil thick polyethylene.
Bolts shall be carbon steel ASTM A 307, Grade B. Nuts shall be heavy hex
nuts conforming to ASTM A 563, Grade C3.
Ends fitted with threaded flanges for DIP shall conform to the
requirements of AWWA C 115/A21.15.
Pipe ends fitted with restraining rings for DIP shall receive approval by the
Engineer prior to the installation of the pipe. It is suggested that test documents
from the manufacturer's testing documentation be submitted with the required
pipe lay sheet submittals.
Restrained Joints for Ductile Iron transmission mains shall be one of the
following types:
a. Flanged and bolted Flanges shall be in accordance with AWWA C
10-32
10-28 WATER PIPE Transmission (greater than 12 inch diameter) (cont.)
110 or AWWA C 153 for operating pressures to one hundred and fifty
pounds per square inch (150 psi) and surge pressures to two
hundred and twenty five pounds per square inch (225 psi).
b. Push-on locking gasket such as "Field-Lok" gaskets as manufactured
by U.S. Pipe.
c. Push-on joint restraint such as "TR-Flex" as manufactured by U.S.
Pipe.
d. Wedge action joint mechanism such as "Megalug" as manufactured
by EBAA Iron, Inc. or approved equal.
e. Mechanical coupling Mechanical couplings shall be as specified in
section 10-29 of these Standard Specifications.
Fittings and openings for DIP shall conform to the requirements of AWWA
C 110/A21.10. Where outlets are required, tees shall be used, with the outlet
branch being flanged.
Bolts shall be carbon steel ASTM A 307, Grade B. Nuts shall be heavy hex
nuts conforming to ASTM A 563, Grade C3.
10-29 BUTTERFLY VALVES & FLEXIBLE COUPLINGS (Transmission)
1. General
Butterfly valves shall be short bodied, tight closing, and rubber-seated
with flanged ends. Butterfly valves shall comply with the requirements of AWWA
C 504, Class 150B and these Standard Specifications. Valves shall be bubble-tight
at rated pressures in either direction, and shall be satisfactory for
throttling service and/or operation and for valve operation after long periods of
inactivity. All butterfly valves shall be Triton XR or Groundhog valves as
manufactured by the Henry Pratt Company, Lineseal III valves as manufactured
by Mueller Company, or approved equals.
Valve discs shall rotate ninety degrees (90˚) from the full open position
to the tight shut position. The valves shall allow for an angular mis-position of
the disc up to one degree (1˚) off center without leakage. The manufacturer
shall have successfully manufactured tight-closing, rubber seated AWWA
butterfly valves for a period of at least five (5) years with local installation list.
10-33
Butterfly valves shall be provided with manual actuators. The actuators
shall provide sufficient output torque to operate the valves at a shutoff pressure
of one hundred and fifty pounds per square inch (150 psi) and at a maximum flow
velocity of sixteen feet per second (16 fps) when opening or closing. In no case
shall the torque rating be less than required for Class 150B valves per AWWA C
504. The Engineer may request Contractor to provide torque and actuator
calculations to verify compliance.
2. Butterfly Valve Materials and Construction
Materials for all parts and components shall be suitable for the intended
use of the valve considering strength, ductility and corrosion protection. All
materials shall conform to the requirements of AWWA C 504. Valves shall comply
with NSF/ANSI 61.
Valve Disc: Valve discs shall be constructed from ductile iron ASTM A 536
for valve sizes thirty inches (30”) and larger, from cast iron ASTM A 126, Class B
for valve sizes less than twenty inches (20”), or from cast iron ASTM A 48/A 48M
Class 40 for twenty-four inch (24”) valves. Valve discs shall be furnished with
316 stainless steel seating edge, ground smooth and polished to mate with the
rubber seat on the body. The disc shall not have any hollow chambers that can
entrap water or ribs transverse to the flow stream. All surfaces shall be visually
inspected and measured to assure all structural members are at full design
parameters.
Valve Seat: All seats shall be Buna-N rubber in the body design. Valves
twenty inches (20”) and smaller shall have bonded seats that meet the test
procedures of ASTM D 429 Method B. Seats for valve sizes twenty-four inches
(24”) and larger shall be retained in the valve body by mechanical means without
retaining rings, segments, screws or hardware of any kind in the flow stream.
Seats shall be a full three hundred and sixty degrees (360°) without interruption
and have a plurality of grooves mating with a spherical disc edge
seating surface. Valve seats shall be field adjustable around the full three
hundred and sixty degrees (360°) circumference and replaceable without
dismantling operator, disc or shaft and without removing the valve from the line.
Seats attached to the valve disc are not allowed.
Valve Shaft: All shafts shall be turned, ground and polished and
constructed of 18-8 Type 304 stainless steel conforming to ASTM A 276. Valve
shaft seals shall consist of self-adjusting "V" type packing capable of replacement
without removal of the valve shaft.
10-34
10-29 BUTTERFLY VALVES & FLEXIBLE COUPLINGS (Transmission) (cont.)
Valve Bearings: All valves shall be fitted with non-metallic sleeve-type
bearings. Bearings shall be corrosion resistant and self-lubricating. Bearing load
shall not exceed one-fifth of the compressible strength of the bearing or shaft
material. Non-adjustable thrust bearings designed to center the valve disc shall
be furnished with the valve assembly and be preset at the factory.
Manual Valve Actuator: Manual valve actuators shall be of the traveling
nut or permanently lubricated worm gear reducer type suitable for continuously
buried and submerged use. All actuator gearing shall be totally enclosed in a
rugged case that is both water tight and lubricant tight.
Actuators shall be fully grease packed and totally sealed by gaskets, O-
rings, or similar means before shipment. A gasketed removable cover plate shall
be provided for maintenance purposes. Actuators shall have a built in packing
leak bypass to eliminate possible leakage into the actuator housing. Stuffing
boxes are not acceptable.
Manual valve actuators shall be capable of withstanding an input torque
of four hundred and fifty foot-pounds (450 ft-lbs) against the open and closed
stops. The valve disc shall be moved through its full stroke with a minimum
number of turns of the operating shaft consistent with the torque limitations.
The valve actuator mechanism shall be self-locking and shall hold the
valve disc rigidly in any intermediate position between full open and fully closed
without creeping or fluttering. Machining and fitting of all parts shall be held to
close tolerances to reduce backlash and to keep lost motion to a minimum.
The actuator shall be equipped with a standard water works two inch (2”)
square wrench nut. The actuator shall open the valve left (counterclockwise),
and shall be furnished with a position indicator if installed in a vault. Provide
valve operating nut extensions in accordance with Standard Drawing W-308 in
Section 38 of these Standard Specifications when installed
valve operating nut is in excess of thirty inches (30”) below finish grade.
Valve Exterior Coating: The exterior of the butterfly valves shall be shop
coated with two part liquid epoxy per AWWA C550. The coating shall have a
nominal thickness of eight (8) mils. Machine finished bearing surfaces shall not
be painted. Exposed machined surfaces shall be covered with slush grease or
other readily removable protective coating before shipment.
Valve Interior Coating: All interior ferrous surfaces of the butterfly
valves, including the disc, which are exposed to fluid flow shall be factory coated
10-35
10-29 BUTTERFLY VALVES & FLEXIBLE COUPLINGS (Transmission) (cont.)
with a two part liquid epoxy coating conforming to AWWA C 550 for potable
water. The coating shall have a nominal thickness of eight (8) mils.
With no exceptions, all damage to coating incurred during shipping shall
be repaired with the original coating material only. The coating shall be
NSF/ANSI 61 certified.
Bolts and Nuts: Bolts connecting valves to main shall be carbon steel
ASTM A 307, Grade B. Nuts shall be heavy hex nuts conforming to ASTM A 563,
Grade C3. Bolts that thread into the valve body shall have the same thread pitch
as the valve body.
3. Flexible Couplings
Flexible couplings suitable for water main applications shall be as
manufactured by Smith Blair, Inc., Series 411 or 413, or Dresser Industries, Inc.,
Style 38 or 162, or an approved equal. The steel middle ring of the flexible
coupling shall be lined and coated with fusion bonded epoxy per AWWA C 213.
The flexible couplings shall be installed with provision for thrust restraint
ties attached to the water main pipe. The thrust restraint ties on the pipe shall
be welded lugs, lugs cast integrally with the pipe, or friction collars. Anchor
studs placed perpendicular to the long axis of the pipe are unacceptable.
Resistance to hydraulic thrust shall be adequate to sustain a force developed by
a test pressure of two hundred and twenty five pounds per square inch (225 psi).
Flanged coupling adapters shall be Smith Blair 913, Romac Style FC400 or
equal for steel piping with insulating gasket. Couplings shall be provided with
thrust ties attached to the pipe with welding lugs, cast-in-place lugs, or friction
collars. Lugs shall have a minimum thickness equal to that of adjacent flange
and shall have holes the same size as those on the flange. Anchor studs placed
perpendicular to the longitudinal axis of the pipe are unacceptable.
10-30 APPURTENANCES
i. Air Vacuum and Release Valves
Combination air vacuum and release valves for water transmission mains
shall be two (2”) or four inches (4”) in size. The air vacuum and release valves
shall have cast iron bodies and be equal to APCO Valve and Primer Corporation,
Model 145C for the two-inch (2”) valve and Model 149C for the four-inch (4”)
valve.
10-36
ii. Blind Flanges and Dished Heads
Blind flanges and dished heads for water transmission mains shall conform
to the requirements of AWWA C 207 and NSF/ANSI 61. Design pressure
classification shall be equivalent to that of the immediately adjacent pipe,
valve, or appurtenance. Blind flanges and dished heads shall be epoxy coated.
The epoxy coating shall have a minimum thickness of eight (8) mils and shall
conform to the requirements of AWWA C 213. Temporary blind flanges and
dished heads that are used during construction of the transmission main do not
need to be coated when approved by the Engineer.
10-31 FIRE HYDRANTS
All Standard (Low Risk) fire hydrants shall be as specified herein unless
otherwise indicated on the Plans or Special Provisions.
1. All fire hydrants shall conform to AWWA C 502 for Dry-Barrel Fire Hydrants
as currently in effect or amended and ANSI 61. An Affidavit of Compliance
as per Section 1.7 of AWWA C 502. Standard shall be furnished with all
hydrants or groups of hydrants. The Certificate of Compliance shall
provide assurance that all material and manufacturing requirements have
been met and head losses are within specified limits.
2. Table 3 of AWWA C 502 is amended to limit loss of head (drop in pressure)
to a maximum of three pounds per square inch (3 psi) at a flow rate of
one thousand gallons per minute (1000 gpm) through one four and one-
half inch (4½") diameter pumper outlet nozzle.
3. Markings-All fire hydrants shall be clearly and permanently marked so as
to be readily discernable and legible after hydrants have been installed.
Such marking should include:
a. Name of manufacturer
b. Model name or number
c. Size of main valve opening
d. Date of manufacture
e. Direction of operation
f. Ground or bury line (mark to reflect point of bury to
maximize breakaway features.)
10-37
10-31 FIRE HYDRANTS (cont.)
4. Two (2) copies of operating manuals and/or descriptive literature shall be
furnished with all fire hydrants or groups of hydrants supplied by the same
manufacturer. The manuals or literature shall include assembly drawings,
schedule of parts, maintenance instructions, and complete tool kits.
5. A complete tool kit for those fire hydrants requiring special tools shall be
provided.
6. In addition to the above, Standard fire hydrants shall meet the following
requirements:
a. Size and Type of Inlet Connection:
i. Standard Hydrants-Dimension of the foot piece shall be as
required to fit cast or ductile iron pipe of six inches (6")
nominal inside diameter.
ii. Connection-Type of inlet connection for standard shall be
either mechanical joint or “push-on” rubber ring. If the
“push-on” rubber ring type is used the foot piece shall be
provided with lugs for harnessing the hydrant to the branch
or lead connection pipe or fitting.
b. Breakaway Features-A frangible section immediately above the
ground or bury line is required. If breakable features depend upon
bolts of reduced cross-section, hollowed out bolts will not be
permitted.
c. Number and Size of Outlet Nozzles Standard Hydrants Two (2) hose
nozzles each with a nominal inside diameter of two and one-
half inches (2½") and one (1) pumper nozzle with a nominal inside
diameter of four and one-half inches (4½").
d. Outlet Nozzle Arrangement- Standard Hydrant-Nozzle arrangement
requires that the two (2) two and one-half inch (2½") diameter hose
nozzles be opposite (180°) of each other. The single four and one-
half inch (4½") diameter pumper nozzle shall be at right angles
(90°) to the hose nozzles. The horizontal centerline of all nozzles
shall be on the same plane and not less than sixteen inches (16")
above the hydrant ground flange or bury line.
10-38
10-31 FIRE HYDRANTS (cont.)
e. Three hundred sixty Degree (360°) Nozzle Rotation-Nozzles, or the
entire above ground section, shall allow three hundred sixty degree
(360°) rotation to the exact desired position after installation.
f. Outlet Hose Nozzles and Threads-Hose nozzles shall be made of
Grade I. VII, or X bronze. The hose nozzles shall be fastened into
the hydrant outlet tap by a thread of not less than seven and one
half (7½) threads per inch. A pin shall be employed to prevent the
threaded outlet hose nozzle from turning or backing out. The cap
or hose accepting end of the outlet nozzles shall be threaded with
National (American) Standard Fire-Hose Coupling Screw Threads.
g. Nozzle Cap Materials-Grey cast or ductile iron caps with a recess at
the inner end of the thread to retain a gasket. Caps shall be
securely chained to the hydrant barrel with a metal chain having
links made from stock not less than one-eighth inch (⅛") in
diameter. The attachment shall permit free rotation of the cap.
h. Size of Hydrant- Nominal diameter of main valve shall be a
minimum of five inches (5").
i. Main Valve Seat and Seat Ring-Shall be bronze to bronze in hydrants
which have the main valve assembly in the lower end of the barrel.
Threads shall be isolated from the waterway by O-ring seals.
j. Size and Shape of Operating Nut and Outlet Nozzle Cap Nuts shall
be the National standard 1½-inch pentagonal, full section without
undercutting or hollowing out. A threaded hole not to exceed one-
quarter inch (¼") in diameter will be allowed in the operating nut
for lubrication purposes. Any such hole shall be plugged flush with
the top of the operating nut and be water tight.
k. Operating Stem, Nut, and Lubricate Reservoir-The nut shall be
made of bronze. Threads shall be lubricated by an oil or grease
reservoir sealed by double O-rings, top and bottom to prevent
intrusion of moisture and dirt. Length of operating stem surface in
contact with O-ring seals shall be protected by a bronze sleeve.
A weather shield shall be provided to prevent dirt and moisture
from entering between the sides of the operating nut and the hold
down nut, or bonnet opening. Wet top hydrants are not
acceptable.
10-39
10-31 FIRE HYDRANTS (cont.)
l. Direction of Rotation: Hydrants shall open left (counter clockwise).
m. Stuffing boxes, if used, shall be provided with O-ring seals.
n. Barrel Drain Outlet-None required. If hydrant is provided with such
an outlet, it must be plugged with a threaded bronze or cast iron
plug.
o. Toggle Joint Hydrants-Shall be provided with bronze parts as
follows: nozzles, lower threaded stem or spindle, stem nuts, seat
ring, gate pins, cotter pins, main valve gate threaded stud, and
nut.
p. All nozzles, caps, operating nuts, O-rings, friction bearing threaded
surfaces, and grease fittings shall be lubricated with the
appropriate factory recommended lubricating material. All
reservoirs designed to hold a designated quantity of lubricant shall
be filled to maximum capacity.
7. A coat of aluminum exterior paint shall be applied as a color or finish coat
over the primer coat on the top (above ground) section. All hydrant
bonnets shall be painted with OSHA approved safety paint. The color shall
be based on the diameter of the main that the hydrant is connected to,
as follows:
Red: for 6” and smaller mains
Yellow: for 8” 10” mains
Green: for 12” and larger mains
8. Bolts shall be carbon steel ASTM A 307, Grade B. Nuts shall be heavy hex
nuts conforming to ASTM A 563, Grade C3.
10-32 VALVES
1. Gate valves shall be cast iron, bronze disc, parallel seat, and non-rising
stem with a two inch (2") square operating nut. Valves shall conform to
AWWA C 500. All interior and exterior ferrous surfaces shall be and coated
with factory applied epoxy in accordance with AWWA C 550. Minimum
thickness shall be eight (8) mils.
10-40
2. Resilient Seated gate valves shall be cast iron, non-rising stem with a
two inch (2") square operating nut. Valves shall conform to AWWA C 509.
All interior and exterior ferrous surfaces shall be and coated with factory
applied epoxy in accordance with AWWA C 550. Minimum thickness shall
be eight (8) mils.
3. Valves provided shall open left (counter clockwise), and shall have bonnet
and valve body markings in accordance with the indicated AWWA
standards. Unless otherwise directed, furnish valves with flange,
mechanical, and/or push-on joints in accordance with the plans and
special provisions. Provide valve operating nut extensions in accordance
with Standard Drawing W-308 in Section 38 of these Standard
Specifications when installed valve operating nut is in excess of thirty
inches (30”) below finish grade.
4. Swing check valves are contained on an approved listing maintained by
the Department of Utilities. Alternate swing check valves shall be added
to this list upon review, test and acceptance by the Utility Department.
5. Bolts shall be carbon steel ASTM A 307, Grade B. Nuts shall be heavy hex
nuts conforming to ASTM A 563, Grade C3.
10-33 VALVE BOXES AND COVERS, DROP CAPS, AND SERVICE VALVE BOXES
Valve boxes and valve box covers for streets and alleys, and drop caps in
public utility easements shall conform to Standard Drawing W-303. The castings
shall be ductile iron with a minimum tensile strength of twenty five.
thousand pounds per square inch (25,000 psi). Riser sections shall be (8”)
diameter SDR 35 PVC pipe.
Service valve boxes shall be in conformance with Standard Drawings W-
305 and W-307. The riser portion shall be as shown.
10-34 WATER SERVICE CONNECTION MATERIALS
Water service material shall be either copper or polyethylene tubing. The
Department of Utilities maintains a listing of approved water service connection
fittings which establish a standard of material quality. Fitting used shall be
limited to those on the list. Alternate material may be added to this list upon
review, testing and acceptance by the Department of Utilities.
Copper service tubing shall conform to ASTM B 88, Type K, soft tempered.
10-41
Polyethylene tubing shall be two hundred pounds per square inch (200
psi), SDR-9 conforming to ASTM D 2737 and AWWA C 901 standards. Tubing shall
be copper tube size and shall be manufactured for use with compression or
Mueller Insta-tite fittings. Stainless steel insert stiffeners shall be used at all
compression joints. Insert stiffeners shall be flared at one end and beveled at
the approximately forty five degrees (45°) at the other end. Stiffeners shall be
supplied by the fitting manufacturer. Tubing shall be clearly marked showing
manufacturer’s trade name, nominal size, type of material, pressure rating, and
the seal of approval of an accredited testing laboratory.
Threads for underground water service connection fittings shall conform
to AWWA C 800 Threads for Underground Service Line Fittings.
10-35 JOINT MATERIALS FOR CLAY PIPE
Joint materials for vitrified clay pipe shall be an approved type of factory-
made mechanical compression joint conforming to the requirements of ASTM C
425. Banded rubber couplings and sleeves conforming to ASTM C 425 are
acceptable.
10-36 JOINT MATERIALS FOR CONCRETE PIPE
Joint materials for concrete pipe shall be rubber gasket joints conforming
to the requirements of ASTM C 443 and shall be flexible and able to withstand
expansion, contraction, and settlement. All rubber gaskets shall be stored in as
cool a place as practicable, preferably at 70º F. or less, and in no
case shall the rubber gaskets be exposed to the direct rays of the sun. Rubber
gaskets, of the type requiring lubrication, shall be lubricated with the lubricant
recommended and supplied by the manufacturer of the pipe.
10-37 JOINT MATERIALS FOR MANHOLES
Joint materials for precast reinforced concrete manhole sections shall
conform to one of the following:
1. Mortar proportioned as one (1) cubic foot of Portland Cement to two (2)
cubic feet of concrete sand. All mortar shall be used within thirty (30)
minutes after the mixing water has been added.
2. Preformed plastic sealing compound shall conform to Type 1 Rope Form,
one and one-half inch (1½") diameter, Federal Specification SS-S-210A.
10-42
10-38 FENCING
CHAIN LINK
1. All chain link fence and gates shall conform to the requirements set forth
in Section 80-4 of the State Specifications and the Chain Link Fence
Manufacturers Institute Product Manual (Standard Industrial), except as
herein modified or as modified in the special provisions.
2. The carbon content of steel posts shall not exceed 0.82 percent (.82%).
3. The fence shall be constructed zinc coated fabric as shown on the Plans
or specified in the Special Provisions.
4. Chain link fence fabric shall meet the requirements of zinc-coated steel
chain link fence fabric, ASTM A 392 with Class I zinc coating. Unless
otherwise indicated on the Plans or in the Special Provisions, the fabric
shall be a two inch (2") mesh of nine (9) gauge wire, with a minimum
breaking strength of twelve hundred and ninety (1,290) pounds. Selvage
shall be twisted top and knuckled bottom.
FENCE MEMBER
DIMENSION O.D.
SECTION TYPE
MINIMALWEIGHT
LBS./LINEAL FOOT
Line Post
2.375”
2.375”
Sch. 40 pipe
Hi-strength tubing
3.65
3.12
Terminal,
Corner,
Latch Posts
2.875”
2.875”
Sch. 40 pipe
Hi-strength tubing
5.79
4.64
Horizontal,
Diagonal
Braces, Top
Rails
1.660”
1.660”
Sch. 40 pipe
Hi-strength tubing
2.27
1.82
Gate Frames
2.375”
2.375”
Sch. 40 pipe
Hi-strength tubing
3.65
3.12
Gate Posts:
Gate Width
Up thru 6’
2.875”
2.875”
Sch. 40 pipe
Hi-strength tubing
5.79
4.64
Over 6’ thru 12’
4.500”
4.000”
Sch. 40 pipe
Hi-strength tubing
10.70
4.64
Over 12’ thru 18’
5.563”
Sch. 40 pipe
14.62
Over 18’ to 24’
Max
6.625”
Sch. 40 pipe
18.97
10-43
10-38 FENCING (cont.)
5. Posts and rails shall be as specified above, unless otherwise indicated on
the Plans or specified in the Special Provisions. Contractor shall have the
option of section types to be used with the condition that the option
exercised shall be uniform throughout the project.
6. Round posts, rails and /or braces shall be Schedule 40 pipe or high strength
tubing as follows:
a. Schedule 40 sections shall be standard weight, hot dipped
galvanized steel pipe in conformance with ASTM F 1083, with not
less than 1.8 oz/sf Grade E zinc.
b. High strength tubing shall be steel pipe, cold-formed and welded
per ASTM F 1043, Group 1C, minimum yield strength 50,000 psi
steel. The external coating shall be Type B zinc, with a polymer
film, 0.90 oz/sf minimum zinc, with a chromate conversion and
verifiable polymer film. The internal coating shall be Type B, 0.90
oz/sf minimum zinc, or zinc pigmented 81% nominal coating with
0.30 mils minimum thickness.
c. Zinc weight shall be determined in accordance with ASTM A 90.
7. Fittings shall be hot-dip galvanized and shall be of malleable, cast iron,
or pressed steel. Cap shall be hot dip galvanized steel sized to post
dimension, and shall be retained to posts with powder actuated Hilti or
comparable Zink coated fasteners.
8. Barbed wire shall be Class 3, zinc coated, 12.5 gage wire with four point
round, 14 gage barbs at 5-inch spacing in accordance with ASTM A 121.
9. Fabric is to be fastened to line posts top and bottom rails with 9 gage
galvanized tie wires spaced approximately fourteen inches (14") apart
10. Unless otherwise set forth in the Special Provisions all fence shall be
constructed with a top rail, and a bottom tension wire.
11. A Certificate of Compliance shall be furnished to the Engineer prior to the
installation of any chain link fencing, gates or components stating that the
steel and protective coatings comply with the above requirements. Said
Certification shall be in accordance with the provisions of Section 6,
Control of Materials”, of the State Specifications.
10-44
10-38 FENCING (cont.)
POST AND CABLE FENCE
1. Post shall be 6” X 6" x 6’ Douglas fir post pressure treated for
underground use. The post shall not have significant splintering. If the
contractor cuts the Douglas fir post they must seal in all areas which
have been cut with Thompson’s Water Seal Advanced Clear Multi-Surface
Waterproofer or approved equal.
2. Cable shall be galvanized barrier cable, steel strand, and zinc plated to
protect it from corrosion per ASTM A475 sixed as shown on the plans.
3. All bolts and cable clamps shall be galvanized steel to minimize rust.
4. Concrete Footing shall be Portland Cement Concrete Class "C",
conforming to Section 10-1/5 of the Standard Specifications. Concrete
footings shall be installed at all end posts, at bends or at the locations
specified on the plans.
10-39 SOIL AMENDMENT
Soil amendment shall be of the type specified by the engineer, unless
otherwise indicated in the Special Provisions. Soil amendments shall be installed
per the soils analysis recommendations.
10-40 IRON SULFATE
Iron Sulfate shall be ferric sulfate in pelleted or granular form as need to
correct any deficiencies that have been identified in a soil analysis for a site.
Iron Sulfate shall conform to the requirements of the Agricultural Code of
the State of California unless otherwise indicated in the Special Provisions.
10-41 COMMERCIAL FERTILIZER
Commercial fertilizer shall be uniformly sized, homogenous pelleted form
and shall be guaranteed to comply with recommendations to correct any
deficiencies that have been identified in a soil analysis specified in the Special
Provisions. Commercial fertilizer shall be as specified in the Special Provisions.
10-42 SEED
Seed shall be labeled in accordance with the California Department of
Agriculture State Seed Law and Regulations effective on the date of invitation
for bids. Seed which has become wet, moldy, or otherwise damaged in transit
or in storage will be subject to test at the discretion of the Landscape Architect
10-45
or of the Engineer.
Seed shall be supplied in unopened containers by a commercial seed
dealer. It may be either mixed or in separate containers for each lot. Seed shall
be as specified in the Special Provisions.
10-43 PLANTS
Plants shall be the variety and sizes shown on the Plans and shall conform
to the requirements of these Specifications.
Contractor shall place an order for the required number of plants including
a reasonable number of replacement plants within ten (10) working days after
they have received notice of award of the Contract. Contractor shall submit a
copy of the order showing the number of plants ordered, from whom ordered
and the anticipated delivery date, and request for substitutions for all plant
materials that are unavailable to the Landscape Architect within fifteen (15)
working days after award of the Contract. No substitutions will be made that
are not requested as specified above.
All plants shall comply with Federal and State laws requiring inspection
for plant diseases and infestations. Any inspection certificates required by law
shall accompany each shipment of plants and certificates shall be delivered to
the Landscape Architect.
Contractor shall obtain clearance from the County Agricultural
Commissioner as required by law before planting plants delivered from outside
the County. Evidence that such clearance has been obtained shall be filed with
the Landscape Architect.
All plants furnished by Contractor shall be true to type or name as shown
on the Plans and shall be tagged in accordance with the standard practice
recommended by the American Association of Nurserymen.
Plants furnished by Contractor shall be healthy, shapely and well rooted.
Roots shall show no evidence of having been restricted or deformed at any time.
Plants shall be well grown, free from insects, disease or mechanical injury. No
plants shall be transported to any planting area that is not thoroughly wet
throughout the ball of earth surrounding the roots.
Plants shall be inspected by the Engineer prior to planting. Any plants
rejected shall be removed from the site and replaced by Contractor, at his
expense.
10-46
10-44 PLASTIC IRRIGATION PIPE
Plastic pipe for irrigation systems shall be polyvinyl chloride (PVC) plastic
pipe extruded from one hundred percent (100%) virgin material and shall conform
to ASTM D 2241.
Plastic pipe on the supply side of the irrigation control valve shall be one
or more of the following types as indicated in the Special Provisions.
1. 2” or smaller shall be PVC-1120 Schedule 40 solvent weld pipe.
2. 2½" or larger shall be PVC-1120 Schedule 40 integrally molded ring-tite
pipe, or
3. PVC-1120 Class 315.
Plastic pipe on the discharge side of the irrigation control valve shall be
PVC-1120 Class 200 solvent weld pipe.
10-45 PLASTIC POTABLE PIPE
Plastic pipe for potable water systems within City parks and recreation
areas and where designated on the Plans, shall be polyvinyl chloride (PVC) plastic
pipe extruded from one hundred percent (100%) virgin material conforming to
ASTM D 2241. Plastic potable pipe one and one-half inches (1½") and smaller
shall be PVC Class 315 solvent weld; two inches (2") and larger shall be Schedule
40 PVC.
10-46 PLASTIC IRRIGATION PIPE FITTINGS
Fittings for PVC plastic pipe shall be rigid polyvinyl chloride, Schedule 80
high impact fittings upstream of the automatic control valve and Schedule 40
fitting downstream from the automatic control valve. Fitting 2” and less shall be
solvent weld type fitting, fittings 2 ½” and larger shall be ring-tite fittings.
Plastic fittings shall have a higher bursting pressure rating than the pipe which
they join.
All joints utilizing ring-tite fittings and pipe shall be sealed with rubber
rings. Fittings shall be of the joint design as recommended by the manufacturer.
Ring type plastic pipe and fittings shall be assembled with a non-toxic lubricant
as recommended by the manufacturer.
1. 2" or smaller shall be PVC-1120 Schedule 40 solvent weld pipe.
10-47
2. 2½" or larger shall be PVC-1120 Schedule integrally molded ring-tite pipe,
or approved equal.
10-47 ELECTRIC AUTOMATIC CONTROLLER
The irrigation system controller shall be a microprocessor based/micro
electronics solid-state type, capable of fully automatic or manual operation of
the system. It shall be housed in a wall mountable, weatherproof, lockable steel
cabinet.
The controller shall operate on a minimum of 117 volts A.C. power input
and be capable of operating up to two 23 volt A.C. electric remote control valves
per station. The controller shall have a reset circuit breaker to protect it from
field wire short circuits entering the controller.
The controller shall be a State approved Water Wise Controller and it shall
have a maximum of 24 stations. Each station of the 4 station and 6 station
models shall have the capability of being programmed to operate for 0 to 60
minutes in 1 minute increments or 0 to 6 hours in 1 hour increments. Each station
of the 8 station and 12 station models shall have the capability of being
programmed to operate for 0 to 99 minutes in one minute increments or 0 to 9.9
hours in 0.1 hour increments. The controller shall have two independent
programs with three automatic starts per day for each. Each station on the
controller shall be assignable to either or both programs. The controller shall
have 14-day programming for flexibility in programming day starts. During
operation, the controller shall provide a monitoring readout indicating station in
operation and time remaining. The controller shall have a 12-hour AM/PM clock.
The 6, 8, 12 and 24 station models shall have a master valve/remote pump
start circuit for use with a mainline master valve to pressurize system when the
irrigation cycle starts, or to activate a remote pump start relay to the pump
during the irrigation cycle.
The controller shall be capable of being operated manually at any time.
A manual “single station” operation for programmed time or new time setting
shall be possible without affecting the original program.
The controller shall have a factory preset back-up program for standby
operation in the event of a program loss and a battery back-up circuit to maintain
program during power loss.
The controller shall be as specified in the Special Provisions.
Electric Controller Enclosure Cabinet shall be as shown on the Standard
Drawings in Section 38 of these Specifications. Cabinet shall be fabricated from
10-48
12 gauge stainless steel. Joints shall be seam welded and external welds ground
smooth to a minimum one-eighth inch (⅛") radius.
10-48 IRRIGATION CONTROL CONDUCTORS
Irrigation Control Conductors shall be underground feeder types (U.F.)
with 4/64" minimum thickness of TW grade polyvinyl chloride insulation.
Control conductors shall be No. 14 AWG, unless otherwise indicated in the
Special Provisions. Insulation shall be any color except white.
Neutral conductors shall be No.12 AWG, unless otherwise indicated in the
Special Provisions. Insulation shall be white.
All irrigation control wires shall be installed in a minimum of a 9” round pull box
or within the irrigation controller valve box. No splice will be allowed that are
not placed in a pull box. Control wires spices shall have a direct bury splice kit
installed at each splice. The splice kit shall consist of a high impact, UV-resistant
polypropylene tube filled with moisture-resistant grease.
10-49 BACKFLOW PREVENTION ASSEMBLY
Backflow Devices are contained on a listing of approved backflow
prevention devices. Backflow devices used shall be limited to those on the list.
The list of approved backflow devices is available from the Engineer or from the
Customer Service Office of the Utilities Department. Alternate backflow devices
shall be subject to approval by the City Cross-connection Control Specialist.
Metal Backflow Enclosures shall be an insulated enclosure and lockable per
Placer Waterworks, Inc. or approved equal.
10-50 ELECTRIC REMOTE CONTROL VALVES-SIZES ¾" TO 2"
Electric remote control valves shall have a brass or bronze body with
straight or angle pattern. Valves shall be normally closed and shall be the same
size as the pipeline which they control, unless otherwise indicated in the Special
Provisions.
Electric remote control valves shall be capable of withstanding a working
pressure of two hundred pounds per square inch (200 psi). Valves shall be
completely serviceable from the top without removing the valve body from the
system and shall have a wheel or nut type manual adjustment feature to regulate
flow from fully open to closed. The adjustment shall remain in set position when
the valve is operated manually or automatically. The adjustment feature shall
regulate automatic closing time to not less than four (4) seconds. Each valve
10-49
solenoid shall be designed for operation on a 24 volt 60 cycle AC circuit at a 3.1
watt maximum. All valves shall have a shut off ball or gate valve on the mainline
side of the water flow adjacent to each valve.
10-51 MANUAL CONTROL VALVES
Manual control valves shall be straight or angle pattern globe valves of
brass or bronze construction with replaceable compression discs and shall be of
the same size as the pipeline which said valve serves, unless otherwise shown on
the Plans. Control valves shall be capable of withstanding a working pressure of
two hundred pounds per square inch (200 psi).
10-52 IRRIGATION VALVE BOXES
Irrigation valve boxes shall be one of the following types; as indicated on
the Plans or in the Special Provisions, or directed by the Engineer:
1. Portland cement concrete boxes with a one piece concrete or cast iron
cover, rated for an H2O traffic loading.
2. Plastic boxes conforming to ASTM D 638, tensile strength 3400 psi and
impact strength of 1.5 pounds per inch. All plastic valve box lids shall have
a bolt to secure the lid to the box.
Valve box extensions shall be of the same type as the valve box and all
covers shall be lockable and be legibly marked “Water or Irrigation.”
10-53 QUICK COUPLING VALVES
Quick coupling valves shall be brass or bronze construction, single slot
type with one inch (1") threaded pipe connection and one inch (1") key
connection, guaranteed to withstand normal working pressure of one hundred
and fifty pounds per square inch (150 psi) without leakage. Quick couplers shall
be installed with swing joint assembly and shall be installed a minimum of one
foot (1') from curbs and walks where applicable. Installed per the plans.
10-54 ELECTRONIC MARKER SYSTEM (EMS)
Electronic marker systems shall consist of a two-part system: Marker
Locator and Markers.
Marker Locator: The EMS II shall consist of a CB-radio sized electronics
package (4 lbs.) with a shoulder strap and a lightweight (1.5 lbs.) hand-held
antenna probe. The electronics package shall produce an audible pulsating signal
and have a meter indicating signal strength simultaneously. The probe shall
10-50
operate on eight (8) standard “C” cell alkaline batteries, produce a ticking sound
when it is on, and transmit low frequency radio signals to the marker.
Markers: The EMS electronic markers shall be air core based and shall be
reusable, with passive-tuned coil antennas encased in waterproof, high-stress,
crack-resistant polyethylene, impervious to minerals, chemicals or temperature
extremes. The markers shall be the mini-markers, approximately 8-¼" in
diameter, color-coded and tuned to the frequency for water. The markers shall
be buried approximately two inches (2") above the valve cover.
10-55 GROUT
This section specifies grout for uses other than masonry.
1. All grouts shall conform to applicable portions of the following:
ASTM C 33 Concrete Aggregates
ASTM C 40 Organic Impurities in Fine Aggregates for Concrete
ASTM C 88 Soundness of Aggregates by Use of Sodium Sulfate or Magnesium
Sulfate
ASTM C 117 Material Finer Than 75 um (No. 200) Sieve in Mineral Aggregates
by Washing
ASTM C 136 Sieve Analysis of Fine and Coarse Aggregates
ASTM C 150 Portland Cement
ASTM C 289 Potential Reactivity of Aggregates (Chemical Method)
ASTM C 494 Chemical Admixtures for Concrete
ASTM C 881 Epoxy-Resin-Base Bonding Systems for Concrete
ASTM D 2419 Standard Test Method for Sand Equivalent Value of Soils and Fine
Aggregate
ASTM E 329 Inspection and Testing Agencies for Concrete, Steel, and
Bituminous Materials as Used in Construction
CRD-C621 Corps of Engineers Specification for Nonshrink Grout
a. These provisions shall pertain to dry pack, cement, non-shrink,
pressure and epoxy grouts, including adhesive capsules and polymer
concrete.
b. Portland cement portion of grout shall be ASTM C 150 Type II or
Type V, low alkali, containing less than 0.60 percent alkalies.
Aggregate in grout shall be non-reactive and shall be washed before
use. When sources of aggregate are changed, test reports shall be
provided for the new material. The tests specified shall be
performed prior to commencing grout work.
10-51
10-55 GROUT (cont.)
c. The fine aggregate portion of grout shall be hard, dense, durable
particles of either sand or crushed stone regularly graded from
coarse to fine and shall conform to ASTM C 33 as modified herein.
When tested in accordance with ASTM C 136, gradation shall be
such that one hundred percent (100%) by weight will pass a
standard No. 8 mesh sleeve and no less than forty-five percent
(45%) by weight will pass a standard No. 40 mesh sieve.
d. Variation from the specified gradations in individual tests will be
acceptable if the average of three consecutive tests is within the
specified limits and the variation is within the permissible variation
listed below:
U.S. standard sieve size
Permissible variation in
individual tests, percent
30 or coarse
2
50 or finer
0.5
e. Other tests shall be in accordance with the following specifications:
Test
Test Method
Requirements
Organic Impurities
ASTM C 40
Color lighter than standard
Amount of Material
Passing No. 200 Sieve
ASTM C 117
3% maximum by weight
Soundness
ASTM C 88
10% maximum loss with
sodium sulfate
Reactivity
ASTM C 289
Innocuous aggregate
Sand Equivalent
ASTM D 2419
Minimum 80
2. Grout admixtures shall conform to the following:
a. Admixtures shall be compatible with the grout. Calcium chloride or
admixtures containing calcium chloride are not acceptable.
Admixtures shall be used in accordance with the manufacturer's
recommendations and shall be added separately to the grout mix.
10-52
10-55 GROUT (cont.)
Water reducing retarder shall be ASTM C 494 Type D and shall be
Master Builders Pozzolith 300-R, Sika Corporation Plastiment, or
equal. Lubricant additive for cement pressure grouting shall be
Intrusion Prepakt Intrusion Aid, Sika Intraplast N, or equal.
b. Water for washing aggregate, for mixing and for curing shall be free
from oil and deleterious amounts of acids, alkalies, and organic
materials; shall not contain more than 1000 mg/1 of chlorides as
Cl, nor more than 1300 mg/1 of sulfates as SO
4
; and shall not
contain an amount of impurities that may cause a change of more
than twenty-five percent (25%) in the setting time of the cement
nor a reduction of more than five percent (5%) in the compressive
strength of the grout at fourteen (14) days when compared with
the result obtained with distilled water. Additionally, water used
for curing shall not contain an amount of impurities sufficient to
discolor the grout.
3. Drypack Grout
a. Drypack grout shall be used for built-up surfaces, setting
miscellaneous metal items and minor repairs and shall be a mixture
of approximately one (1) part cement, 1-1/2 to two (2) parts sand,
water reducing retarder, and sufficient water to make a stiff
workable mix.
b. Surfaces required to be built up with drypack grout shall be
roughened with a wire brush, cleaned, and immediately coated
with an acrylic bonding agent such as Burke Acrylic Bondcrete, or
equal, at the rate of 200 sq. ft. per gallon. Follow with placement
of the grout after a minimum of one hour and after the film is dry
to the touch. Install bonding agent in strict accordance with
manufacturer's instructions. The drypack grout shall be applied in
bands or strips to form a covering of the required thickness. The
covering shall be smooth. Construction joints in the grout shall be
sloped and shall be cleaned and wetted before application is
resumed.
c. Drypack grout shall be cured as for Cast-In-Place Concrete. Grout
shall not be placed during freezing weather unless adequate
protection is provided.
10-53
10-55 GROUT (cont.)
4. Cement Grout
a. Cement grout shall be used for filling nonbearing portions of
equipment pads and pressure grouting and shall be a mixture of one
(1) part cement, two (2) parts sand, proportioned by volume,
admixtures for pressure grouting, and sufficient water to form a
workable mix.
b. Except for the specialized equipment for pressure grouting,
mixing, and placing apparatus shall be similar to that normally
used for cast-in-place concrete. Grout shall be mixed for a period
of at least one (1) minute. Diluted grout shall be agitated to keep
ingredients mixed.
5. Nonshrink Grout
a. Nonshrink, nonmetallic aggregate grout shall be used for the
bearing surfaces of machinery and equipment bases, column base
plates and bearing plates. Nonshrink metallic aggregate grout shall
be used for setting anchor bolts and grouting reinforcing steel
holes. Nonmetallic aggregate grout shall be Five Star Products, Inc.
Five Star Grout, Master Builders Masterflow 928, Burke Company
Non-Ferrous, Non-Shrink Grout, or equal. Grout shall meet the
requirements of ASTM C1107 and shall be placed in accordance with
manufacturer's instructions.
b. Holes required for grouting shall be blown clean with compressed
air and left free of dust or standing water. Horizontal holes for
grouting shall be drilled at a slight downward angle to facilitate
holding the grout until setting is complete. Bolts or reinforcing
steel installed in horizontal grout holes shall be bent slightly
accordingly.
6. Epoxy Grout
a. Epoxy grout shall be used for repairing cracks by pressure grouting
or gravity flow, repairing structural concrete, and may be used for
setting reinforcing dowels or anchor bolts into holes for grouting.
Except as noted below, epoxy grout shall be a high modulus, two
(2) component, moisture insensitive, one hundred percent (100%)
solids, thermosetting modified polyamide epoxy compound. The
consistency shall be a paste form capable of not sagging in
10-54
10-55 GROUT (cont.)
horizontal or overhead anchoring configurations. Material shall
conform to ASTM C 881 Type 1, Grade 3, such as Master Builder
Concresive 1440 series, Sika Corporation Sikadur Hi-Mod Series,
Adhesive Technology Corporation Solidbond 200 or equal, and shall
have a heat deflection temperature in excess of 130 degrees F.
b. Epoxy for pressure grouting/crack injection shall be a two (2)
component, moisture insensitive, high modulus, injection grade,
one hundred percent (100%) solids, blend of epoxy-resin
compounds. The consistency shall be as required to achieve
complete penetration in hairline cracks and larger. Material shall
conform to ASTM C 881 Type 1 Grade 1, such as Sika Corporation
Sikadur 52, Master Builders Concresive LPL, Adhesive Technology
Corporation SLV 300 series, or equal.
c. Concrete shall be primed in accordance with the grout
manufacturer's instructions.
d. Use of epoxy grout for anchorage of bolts or reinforcing dowels shall
be subject to the following conditions:
e. Use shall be limited to locations where exposure, on an
intermittent or continuous basis, to acid concentrations higher than
ten percent (10%), to chlorine gas, or to machine or diesel oils, is
extremely unlikely.
f. Use shall be limited to applications where exposure to fire or
exposure to concrete or rod temperature above the product's heat
deflection temperature or 120 degrees F (whichever is less) is
extremely unlikely. Overhead applications (such as pipe supports)
because of the above concerns, shall be disallowed.
g. Approval from Engineer for specific application and from supplier
of equipment to be anchored, if applicable.
h. Anchor diameter and grade of steel shall be per contract documents
or per equipment supplier specifications. Anchor shall be threaded
or deformed full length of embedment and shall be free of rust,
scale, grease, and oils. Embedment depth and hole diameter shall
be as specified. Holes shall have rough surfaces, such as can be
achieved using a rotary percussion drill. Holes shall be blown clean
with compressed air and be free of dust or standing water prior to
application of grout. Anchor shall be left undisturbed and unloaded
10-55
for full curing period. Anchors shall not be placed in concrete below
twenty-five degrees (25°) F.
10-56 POLYMER CONCRETE (FOR RESURFACING OR PATCHING)
Polymer concrete (for resurfacing or patching) shall consist of a liquid
binder and dry aggregate mixed together to make a mortar or grout of a
consistency as required for the application. The liquid binder shall be a chemical
and oil resistant, stress relieved, low modulus, moisture insensitive, two-
component epoxy-resin compound. The consistency shall be similar to
lightweight oil for proper mixing with aggregate. Material shall conform to ASTM
C 881 Type 3 Grade 1, such as Sika Corporation Sikadur Lo-Mod series, Adhesive
Engineering Concresive 1470, Adhesive Technology Corporation 400 series, or
equal.
The aggregate shall be oven dry in sealed packages until time of mixing
and shall be of size and consistency compatible with recommendations of
manufacturer of liquid binder for intended application.
Primer, if required for polymer concrete, shall be provided per
manufacturer's recommendation.
10-57 ADHESIVE CAPSULES FOR DOWEL ANCHORAGE
Adhesive resin capsules may be used for setting and anchoring reinforcing
dowels or anchor bolts into predrilled holes in concrete.
Adhesive resin capsules shall consist of sealed glass capsules containing
pre-measured amounts of a polyester or vinylester resin, quartz sand aggregate
and a hardener contained in a separate vial within the capsule. Adhesive
capsules shall be Hilti HVA Capsules, Molly Parabond Capsules, or equal.
10-58 PRESSURE GROUTING
Pressure grouting equipment shall include a mixer and holdover agitator
tanks and shall be designed to place grout at pressures up to fifty (50) psi.
Gauges shall be provided to indicate pressure used. The mixer shall be provided
with a meter capable of indicating to 1/10 of a cubic foot the volume of grout
used.
Grouting, once commenced, shall be completed without stoppage. In case
of breakdown of equipment, the Contractor shall wash out the grouting system
sufficiently to ensure fresh grout and adequate bond and penetration will occur
upon restarting the grouting operation. Grout pressure shall be maintained until
grout has set.
11-1
Section 11
PRECONSTRUCTION PHOTOGRAPHS
11-1 REQUIREMENT
Preconstruction photographs are required when specifically called for in
the special provisions or on the plans.
11-2 SPECIFICATION
When pre-construction photographs are required, Contractor shall provide
the Engineer in an email, cloud share file, thumb drive, or other approved
method and the photo shall be a jpg or pdf format. The photographs shall be
taken at one hundred foot (100’) intervals, or closer as necessary to document
existing conditions, along the route of the project before any work is started.
Each view shall contain the date, project name, lateral or street, and station.
This data shall not block the important areas of the picture and should be of the
smallest size possible consistent with legible presentation of the required
information when a 4” X 6” print is viewed.
All prints shall show good details in both shaded and sunlit areas. Digital
photos are used a minimum resolution of 4 mega pixels is required.
At the option of Contractor, a video recording in an acceptable digital
format may be submitted in lieu of pre-construction photographs. All essential
features of the project area are to be recorded and all orientations of the view
recorded in an accurate manner satisfactory to the Engineer.
Contractor shall submit the pre-construction photographs or digital video
recording to the Engineer for review and approval prior to the starting of work.
11-3 PAYMENT
Payment for preconstruction photographs shall be at the lump sum price
bid and shall include full compensation for providing all labor, materials, tools,
and equipment necessary to furnish the required products.
12-1
Section 12
CLEARING AND GRUBBING, AND TREE REMOVAL
12-1 TREES
Unless specifically indicated on the Plans or set forth in the Special
Provisions no trees may be removed without direct authority of the Engineer.
For the purposes of this section trees shall be considered as those having
a trunk diameter of four inches (4”) and greater measured at a height of four
and a half feet (4’-6”) above the ground.
In cases where tree removal is shown on the Plans or is called for by the
Special Provisions the Contract may either require a lump sum price for removal
of all trees or a unit price per each tree.
12-2 CLEARING AND GRUBBING
1. General
Clearing and grubbing shall consist of removing all objectionable material
from within the rights-of-way, construction areas, or other areas that may be
specified in the Special Provisions or as indicated on the plans which interferes
with the work.
2. Vegetation and Debris
All vegetation such as weeds, grass, shrubbery, roots, and stumps and
debris such as broken concrete and trash shall be removed. Tree branches which
extend over roadways shall be trimmed to provide a minimum vertical clearance
of fourteen feet (14’). Contractor shall have a California, C61 license, allowing
him/her to perform D49 tree work and an arborist certified by the International
Society of Arboriculture (ISA) on staff. All work shall be supervised by an ISA
Certified Arborist and shall comply with the American National Standards
Institute (ANSI) Standard Practices for Tree Care Operations (ANSI A300), the
American National Standards Institute (ANSI) Safety Requirements for
Arboriculture Operations (ANSI z133)and the City of Sacramento Tree Ordinance
Title 12.56-12.. Trees, shrubbery, lawns, and other vegetation adjacent to the
work that is not to be removed shall be protected from injury or damage resulting
from Contractor’s operations.
12-2
3. Existing Facilities
Existing facilities such as pavements, curbs, gutters, sidewalks, lawn
sprinklers, mailboxes, fences, pipes, and culverts that interfere with the work
shall be removed under the item of clearing and grubbing unless the Plans or
Special Provisions provide for separate items.
The methods of removing existing facilities shall conform to Section 13 of
these Specifications.
4. Disposal
Materials resulting from clearing and grubbing operations and that are
not to be salvaged or otherwise used shall be disposed of outside the project
limits at an appropriate site and at the expense of Contractor.
12-3 PAYMENT
In a lump sum contract, all clearing and grubbing is included in the lump
sum bid. In unit price contracts, payment for clearing or for clearing and
grubbing shall be at the lump sum price bid and shall include full compensation
for all work required to complete this item. Payment for tree removal will be
either at the lump sum price bid or at the price bid per each tree to remove as
indicated in the Contract Documents. Where no separate bid item is included for
tree removal, tree removal shall be included in "clearing” or “clearing and
grubbing”.
13-1
Section 13
EXISTING FACILITIES
13-1 PROTECTION
Existing facilities within the rights-of-way and construction areas that do
not interfere with the work shall be protected from damage. Existing
improvements, utilities, and adjacent property shall be protected from damage
resulting from Contractor's operations. All trees, lawn, shrubbery, fences, walls,
irrigation systems, and other improvements including, but not limited to,
existing pavements, sidewalks, street improvements and underground utilities
and other improvements not to be removed shall be protected from damage by
Contractor throughout the construction period.
Contractor shall be responsible for repairing damage to existing
improvements or replacing in kind at the Engineer’s option.
All signs and street marking damage due to Contractor’s operation shall
be replaced in kind by Contractor. In the case of partial damage to lane stripes
and traffic lettering the whole stripe or letter shall be replaced. Temporary
markings and striping shall be installed within three (3) working days of damage.
All painted or other disfiguring marks on the pavement, sidewalk or gutters shall
be removed by Contractor before the work has been accepted.
13-2 MAINTAINING WATER, SEWER, AND DRAINAGE FLOWS
Contractor shall be responsible for maintaining all existing water, sewer,
and drainage facilities within the limits of the project until new improvements
are complete and functioning.
Contractor may elect to cut existing water service laterals and/or sewer
services or tunnel beneath them. All water service laterals or sewer services cut
by trench excavation or other construction activities shall become the
responsibility of Contractor to repair. Maximum time of interruption of water
service to any residence or business shall be four (4) hours. Any cut sewer
services shall be replaced or repaired by nightfall of the same day per Standard
Drawings S-230, S-260, and S-265 of Section 38 of the Standard Specifications.
Should Contractor choose to cut existing water service laterals or sewer
services, Contractor shall notify the Engineer at least three (3) working days in
advance and shall give residences and businesses twenty-four (24) hour notice of
interruption of service.
13-2
Should Contractor desire City forces to cut and repair existing water,
sewer, or drain services, Contractor shall contact the Engineer at least three (3)
working days in advance to schedule and coordinate the work. No compensation
will be paid to Contractor for the repair by City crews of any water service
laterals or sewer services accidentally or purposely cut by Contractor and all
such work performed by City crews at the request of Contractor shall be at
Contractor's expense. Any work performed or materials provided by City crews
to repair and maintain existing drainage systems shall be at Contractor's expense
or shall be deducted from amounts owed to Contractor.
Whenever, in the opinion of the Engineer, there arises an emergency
situation within the limits of the project that involves maintenance of water,
sewer, or drainage, or a situation that poses a danger to the public safety, or
inconvenience and/or unreasonable nuisance to the general public, City's forces
may be called upon to perform any work necessary to relieve the emergency.
Contractor's attention is directed to Section 5-12 "Provisions for Emergencies."
If such emergency is the result of negligence by Contractor, the cost of
any corrective measures taken or work performed by City crews shall be billed
directly to Contractor or may be deducted from any payments owed to
Contractor. The performance of such emergency work by the City forces shall
not relieve Contractor of any responsibilities, obligations, or liabilities under the
contract for the project.
Should it become necessary for Contractor to temporarily divert or convey
flows carried by existing water, sewer, or drainage systems (which include, but
are not necessarily limited to, pipelines, channels and pump stations),
Contractor shall prepare a detailed, effective plan including, at minimum, the
quantity of flow to be conveyed and/or the volume to be impounded, the
number, size, and material type of any pipes, the size and configuration of any
channel, the size and configuration of any impoundment basin, all pumping
information (if applicable), the point of discharge and discharge details.
The plan shall be submitted to the Engineer for approval a minimum of
ten (10) working days prior to the start of any work affected thereby and
Contractor shall not begin such work until the plan is approved and is on file with
the Engineer.
No separate payment will be paid to Contractor for maintenance of
existing facilities; the cost of this work shall be included in the various contract
items of work.
13-3
13-3 REMOVING/RELOCATING
Existing facilities that interfere with the work shall be removed, reset,
relocated, adjusted, or otherwise worked on as specified herein, on the Plans,
or as directed by the Engineer. Removed facilities that are not to be salvaged or
otherwise used shall be disposed of away from the project. Holes or depressions
resulting from the removed facilities shall be filled, compacted, and brought to
grade at the direction of the Engineer.
1. Asphalt and Concrete
Asphalt and concrete such as pavements, curbs, gutters, and
sidewalks that are to be removed shall be cut to neat, straight lines
with an approved saw or other means acceptable to the Engineer.
Where the edge of the pavement removal is within two (2) feet of
existing building, curb and gutter, or existing pavement edge, the
remaining pavement shall also be removed and replaced. The exact
limit of the asphalt and concrete to be removed shall be determined in
the field by the Engineer. Any temporary surface placed shall be
marked with the Contractor’s name until such time as final restoration
has been placed to the City’s satisfaction.
2. Mailboxes
Existing mailboxes and supports shall be removed and reset
where shown on the Plans or as directed by the Engineer. Existing posts
shall be removed and transported from the job site and replaced with
4 X 4 pressure treated Douglas fir posts conforming to the provisions of
Section 82, “Signs and Markers” of the State Specifications. The
mailboxes shall be suitably mounted on a platform which shall be set
three and one-half feet (3½’) to four feet (4’) above the ground. Posts
shall be set at least two feet (2’) in the ground and firmly positioned
by tamping. Existing newspaper receptacles shall be attached to new
posts.
Existing mailbox supports constructed of material other than
normal 4 X 4 wooden posts shall be stacked in the owner’s yard for his
recovery. Contractor shall replace with 4 X 4 wooden posts as described
above.
3. Fences
Fences shall be relocated where shown on the Plans or as
directed by the Engineer. Fence shall be relocated to provide three foot
13-4
(3’) minimum clearance from relocated or new fire hydrants. Replace
only deteriorated fence parts.
The intent of this specification is for Contractor to relocate the
fence in a more suitable location without completely rebuilding it and
with an absolute minimum of effort and expense. It may not be known
how much of any type of fencing Contractor will be required to replace.
Contractor shall submit a unit price per lineal foot of fence to replace
regardless of type or quantity.
4. Sprinklers and lights
Lawn sprinkler system pipes, heads, and yard lighting systems
shall be relocated and re-plumbed to insure continued operation to an
equal or better condition.
5. Pipes and Culverts
Pipes and culverts that are no longer to be used shall be removed
if they are within two feet (2’) of sub-grade. Such pipes that are lower
than the aforementioned, shall be removed or the ends shall be plugged
with concrete at the option of Contractor. Concrete plugs installed in
the ends of abandoned sewer or storm drain lines shall be Class “C” or
“D” concrete that extends at least two feet (2’) into the pipe from the
exposed end. Refer to Section 27-3 for capping the ends of water mains.
6. Abandonment of water service
Abandon the water service by closing corporation stop and
crimping and cutting water service adjacent to the distribution main.
7. Existing Utilities
Unless otherwise noted, the location, alignment, and depth of
existing underground utilities as shown on the Plans is taken from public
records and no responsibility is assumed for the accuracy thereof. For
the most part, underground utility services are not shown on the Plans.
Attention is directed to the provisions in Section 6-19, "Main and Trunk
line Utilities." The cost of relocating existing overhead and/or
underground utilities not specified on the plans to be relocated, but
which Contractor elects to relocate or cut and reconnect at his/her own
convenience shall be borne by Contractor.
13-5
13-4 PAVEMENT FOR TRENCH SURFACE RESTORATION
Contractor shall restore surfaces in kind (using the same material as
existing) unless otherwise noted on the Plans or Special Provisions.
Any temporary surface placed shall be marked with the Contractor’s
name until such time as final restoration has been placed to the City’s
satisfaction.
Asphalt pavement surface restoration for trenches shall conform to the
applicable provisions of Sections 10, 22, 26 and 27.
Restoration of existing concrete pavement shall consist of a minimum of
six (6) inches of Portland cement concrete. Portland cement concrete pavement
and its placement shall conform to the requirements of Sections 10 and 19.
13-5 PAYMENT
There will be no separate payment for existing utilities work as described
in this section, but full compensation will be considered as included in the bid
for items of work Contractor deems appropriate.
14-1
Section 14
EARTHWORK, EXCAVATION, EMBANKMENT AND SUBGRADE
14-1 ROADWAY EXCAVATION AND BACKFILL
In the Contract this item shall consist of excavating, removing, and
satisfactory disposal of all material within the limits of the work for roadways,
drainage channels, ditches, and any other work as may be specified in the Special
Provisions or shown on the Plans. Suitable excavated material may be used for
embankment and for backfilling. The rough excavation shall be carried to such
depths that sufficient material will be left above the finished grade to allow for
compaction to the required grade. Should Contractor excavate below the
designated lines he will be required to replace the material with suitably
compacted import material or Class “D” Concrete as determined by the
Engineer, without cost to the City.
No excavation shall be started on a project until approval has been given
by the Engineer. This approval is to assure all necessary surveys, cross sections,
and measurements which may be required for determining the quantities
removed are performed.
If all or part of the excavated material is to be used as fill, and preparation
for the fill placement has not been made, the Engineer may require the
stockpiling of this material. The Engineer shall have the right to select excavated
material to be used in fill.
Payment for excavation shall be based on cross section measurements
taken prior to the beginning of work and the final lines and grades of the finished
section. Payment shall be made per cubic yard of material excavated in
accordance with the Plans.
14-2 STRUCTURE EXCAVATION AND BACKFILL
All compaction test results and test agent information shall be submitted to the
Engineer for review and approval. Placement of forms, foundations, or footings
shall not begin until the City has received written verification that the
compaction test results meet the requirements of this specification.
Structure excavation shall consist of excavation performed to place
structures such as footings, walls, manholes, junction boxes, etc.
Payment for structure excavation and backfilling shall be considered as
included in the prices paid for the various items of work involved and no separate
payment will be made therefore.
14-2
Excavation for placement of manholes will be paid for under the price bid
for manholes, complete in place.
Backfill material shall be specified in the Special Provisions or indicated
on the Plans. The backfill material shall be compacted by mechanically tamping
in maximum eight-inch (8”) layers so as to achieve a minimum relative
compaction of ninety-five percent (95%).
Material excavated in excess of that required for backfilling will be
disposed of away from the site of the work, unless otherwise permitted by the
Engineer.
14-3 TRENCH EXCAVATION AND BACKFILL
Trench excavation shall consist of the excavation required to install
pipelines and its cost will not be paid for separately but compensation will be
included in the price bid for placing pipe.
Before excavation of the pipe trench in fill areas of roadway
embankments, the fill area or embankment shall be completed to a height above
the pipe invert grade line of not less than twice the internal pipe diameter or to
final fill or embankment subgrade, whichever is lower, but in no case less than
twelve inches (12”) above the top of the pipe. Such embankment shall be
compacted to a minimum relative compaction of ninety percent (90%) for a
distance on each side of the pipe equal to a least two (2) pipe diameters. The
remainder embankment shall be compacted as specified elsewhere in these
Specifications for the type of construction being pre-formed, or as specified in
the Special Provisions or the Plans.
Backfill shall be placed as shown on Standard Drawing T-80, shall be
provided by Contractor and shall be placed in accordance with these Standard
Specifications and the pipe manufacturer’s recommendations. Initial backfill
shall be the material between the top of the bedding material and six inches (6”)
above the top of the bell or barrel if the pipe does not have a bell.
Initial backfill shall be placed immediately after pipe joints have been
completed, inspected, and passed by the Engineer. The material shall be
carefully placed so as not to disturb or damage the pipe and shall be brought up
evenly on both sides. Initial backfill material shall be placed in layers not
exceeding eight inches (8”) in depth before compaction at or near optimum
moisture content. Contractor shall place initial backfill by shovel slicing,
tamping, and/or vibratory compaction in order to produce firmly compacted
material under the haunches of the pipe. Compaction shall be by mechanical
pneumatic or vibratory compaction equipment approved by the Engineer. Care
shall be used to avoid dislodging the pipe. No wedging or blocking of the pipe
shall be permitted. Ponding and jetting methods of achieving compaction shall
14-3
not be allowed. The compacted material must achieve a relative compaction of
at least ninety percent (90%) as determined by ASTM D 698.
When the bedding material for the pipe consists of crushed rock, sand
shall not be used as initial backfill material.
Unless otherwise approved by Engineer, trench backfill, as shown on
Standard Drawing T-80, shall be provided, and placed to grade by Contractor, in
accordance with these Standard Specifications and the pipe manufacturer’s
recommendations. Trench backfill shall be the material between the initial
backfill and the top of trench or sub-grade. The material for trench backfill may
be of job excavated, native material provided that such material is free of
organic materials or other unsuitable materials as determined by the Engineer
that may cause voids or depressions to develop during or after placement of the
backfill. Rocks, stones, and solid earth chunks exceeding three inches (3") in
greatest dimension shall be removed from the trench backfill material.
Unless otherwise indicated on the Plans or specified in the Special
Provisions, trench backfill material shall be placed in layers not exceeding eight
inches (8”) in depth before compaction at or near optimum moisture content.
Until the total backfill above the top of the pipe exceeds three feet (3’),
machine-placed backfill material shall not be allowed to “freefall” more than
two feet (2’).
Unless otherwise shown on the Plans or specified in the Special Provisions,
compaction of trench backfill material shall be by mechanical pneumatic or
vibratory compaction equipment. Minimum relative compaction of trench
backfill material shall be ninety percent (90%) when tested according to ASTM D
1557, except that the top six inches (6”) below the subgrade shall be compacted
to a relative compaction of ninety-five percent (95%). Trenches in easements
outside the street rights-of-way may be compacted to ninety percent (90%)
relative compaction throughout the depth. Compaction testing will be performed
by the Engineer and the cost thereof will be borne by the City, except that
retests of areas which fail to meet the required compaction will be charged to
Contractor and deducted from any payment due Contractor for work performed
under the terms of the Proposal.
Ponding and jetting methods of achieving compaction are not allowed.
Refer to Section 10-16 Controlled Density Fill (CDF) regarding approval
and mix design requirements for use of CDF, CLSM, and/or RFF as an alternate
to granular material for initial backfill and trench backfill materials.
14-4 TEMPORARY PAVING
Unless stated otherwise in Contract documents, at the end of the day and
14-4
prior to opening to traffic, trenches shall be temporarily paved to provide a
smooth riding surface. The paving material may be asphalt concrete or
temporary paving, “cut back” or other Engineer approved material. Contractor
may use non-skid plates to cover trenching when approved by the Engineer.
Contractor shall nail down plates, and at edges Contractor shall create and
maintain a uniform taper using temporary paving to ensure a smooth traveling
surface over the plate.
Cutback shall be placed on the completed aggregate base course,
constructed per the Plans and Special Provisions and shall be placed so that the
compacted thickness is not less than two inches (2”).
Compaction of temporary paving shall be performed using steel wheel
rollers or mechanical equipment approved by the Engineer. Compaction by wheel
rolling with backhoes or other rubber tire construction equipment shall not be
allowed. The temporary paving shall be placed and maintained so that the
maximum deviation does not exceed one-half inch (½”) using a ten (10) foot
straight edge placed in any direction. If, in the opinion of the Engineer, the
temporary paving is not properly maintained, Engineer may direct Contractor to
install permanent asphalt concrete pavement at no additional cost to the City of
Sacramento.
14-5 EMBANKMENT AND FILL
Fill on a roadway will normally be made with material excavated on the
same work unless otherwise indicated by the Special Provisions or Plans.
Fill will be paid for per cubic yard measured in place by computing the
yardage between the original ground elevation and the final grades as shown on
the Plans.
Tests performed to determine relative compaction shall be performed
using the following methods:
1. ASTM D 1557 laboratory test for maximum dry density at optimum
moisture
2. ASTM D 2922 field test for in-place wet density by nuclear methods.
3. ASTM D 3017 field test for in-place moisture content by nuclear
methods.
Relative compaction shall mean the ratio of the field dry density to the
laboratory maximum dry density expressed as a percentage.
14-5
In general, construction of fill shall be in accordance with the methods
set forth in the State Specifications. The relative compaction shall be at least
ninety percent (90%), unless otherwise indicated.
14-6 LANDSCAPE FILL
The contractor shall provide the engineer a soil analysis report for
proposed landscape fill material. Landscape fill shall consist of fertile, friable
soil of loamy character. It shall be obtained from well-drained arable land
outside of the project limits and shall be free from subsoil, refuse, roots, heavy
or stiff clay, stones larger than one inch (1”) in size, coarse sand, noxious weeds,
such as Bermuda, Nut Grass and Morning Glory, sticks, brush, litter and other
deleterious substances. Topsoil shall be capable of sustaining healthy plant life.
Landscape fill will be paid for per cubic yard, measured in place by
computing the yardage between the original ground elevation and the final
grades as shown on the Plans; which price shall include full compensation for all
labor, equipment and materials necessary for placement of landscape fill. The
relative compaction shall be eighty-five percent (85%), unless otherwise
indicated.
14-7 SUBGRADE
Sub-grades for pavement, curb and gutter, sidewalk, lined channels and
ditches, or for rock base under pavements shall be finished accurately and true
to the lines and sections shown on the Plans, within a tolerance of ±.05 feet.
The top six inches (6”) of sub-grade immediately prior to placing subsequent
material thereon shall have a relative compaction of not less than ninety-five
percent (95%). The sub-grade shall be free of segregated material and shall be
smooth and true to the required grade and cross section. Contractor shall repair,
at his expense, any damage to a prepared sub-grade caused by his operations or
by use of public traffic. No material shall be placed upon the prepared sub-
grade until it is in a condition meeting the requirements specified. Unless
otherwise provided by the Special Provisions, the finishing of sub-grade will not
be paid for as a separate item but this work will be included by Contractor under
such items as Contractor deems appropriate.
14-8 UNSUITABLE MATERIAL/IMPORT
1. Definition
Unsuitable Material for roadway sub-base and trench backfill is defined
as soil the Engineer determines to be:
a. Loose, unstable or yielding, or
14-6
b. Unable to be compacted to specified density using ordinary
methods at optimum moisture content, or
c. Contains visible or excessive deleterious material as determined by
the Engineer, or
d. Too wet to be properly compacted and circumstances prevent
processing suitable in-place drying prior to being used as backfill;
or
e. Otherwise unsuitable for planned use.
2. Handling Trench Unsuitable Material
Whenever the bottom of the trench is soft or rocky, or rendered not
suitable by the Engineer for pipe bedding, the unsuitable material shall be
removed to a minimum depth of six inches (6”), or deeper as determined by the
Engineer, for pipelines or twelve inches (12”) for manholes or appurtenant
structures. Whenever excavated native soil is rendered by the Engineer to be
unsuitable for trench strata backfill, Contractor shall remove and replace with
import material approved by the Engineer.
For drainage, sewer and water pipelines the unsuitable material shall be
replaced with Class 2 aggregate base or approved equal and shall be compacted
to 90% relative compaction. For manholes and appurtenant structures, the
unsuitable material shall be replaced with material subject to the approval of
the Engineer. The Engineer may direct the Contractor to furnish and place
geotextile fabric below the bedding materials. The geotextile material shall be
a non-woven fabric equal to or exceeding the properties listed in the table
below.
14-7
REQUIRED NONWOVEN GEOTEXTILE PROPERTIES
Physical
Property
Test Method
Acceptable
Minimum Test
Results
Tensile strength, lb
ASTM D 4632
200 lbs.
Elongation, %
ASTM D 4632
50%
Permittivity, sec-1
ASTM D 4491
1.5 sec
-1
Puncture strength, lb
ASTM D 4833
120 lbs.
Mullen Burst strength,
psi
ASTM D 3786
380 psi
The cost to remove and replace unsuitable bedding material to the above
specified depths shall be included in the specific bid item cost. Excavation of
unsuitable material beyond these depths, so ordered removed by the Engineer,
will be paid as extra work as provided in Section 4 unless otherwise specified in
the Special Provisions.
The cost to haul and replace native soil that is unsuitable for trench strata
backfill shall be a separate bid item that includes the import material price and
the transporting expenses for both unsuitable and the import material. The cost
to replace unsuitable material rendered unsuitable due to any act or omission of
Contractor or due to inclement weather shall be borne by Contractor and there
will be no compensation therefore.
Excavated unsuitable material shall be the property of Contractor and
shall be disposed of away from the project site. For off site disposal, Contractor
shall have written permission from the owner upon whose property the disposal
is to be made before any material is deposited thereon.
The quantity of unsuitable material/import for trenches shown on the Proposal
is for bidding purposes only. The unit price indicated will not be adjusted
because the actual quantity varies from the quantity shown on the Proposal.
14-8
Payment for handling Unsuitable Material/Import shall be at the contract unit
price bid per tonnage of import.
3. Handling Roadway Unsuitable Material
For road sub-grades unsuitable material shall be replaced with pit run
base, aggregate base Class II, cement treated bases, lime treated bases, and
with geogrid.
Payment for handling Roadway Unsuitable Material/Import shall be at the
contract unit price bid per ton, shall be based solely on the tonnage of import,
and shall include full compensation for furnishing all labor, materials, tools and
equipment, and for performing all work necessary to complete this item in place.
As an alternate the Engineer may direct Contractor to furnish and place
geotextile fabric below the bedding materials. The geotextile material shall be
a high modulus woven fabric, and shall be inert to commonly encountered
chemicals, rot-proof, and resistant to ultraviolet light, insects, and rodents. The
geotextile fabric shall have a minimum grab tensile strength of two hundred
pounds (200 lbs.) in any direction as measured in accordance with ASTM D 4632,
a Mullen burst strength of at least four hundred pounds per square inch (400 psi)
per ASTM D 3786, and an Equivalent Opening Size no larger than the U.S.
Standard Sieve Number 50 as determined by ASTM D 4751. Geotextile fabric shall
be Mirafi 600X or equal. Each roll of fabric shall be handled and placed in
accordance with the manufacturer’s recommendations. Furnishing and placing
of geotextile fabric will be paid for as extra work as defined in 4-6, “Extra Work
Force Account” unless otherwise indicated.
Where geogrid is utilized Contractor shall furnish equipment required for
satisfactory progress and completion of the project. Before placement of the
geogrid, the site shall be cleared of all topsoil, trees, stumps, rocks, and other
debris. The grade shall be reasonably smoothed, minimizing all ruts, depressions,
and other distortions that would inhibit smooth and proper placement of the
geogrid. Geogrid shall be placed in accordance with the suppliers installation
recommendations, but in no case shall grid ties be placed less than twenty feet
apart or grid overlaps be less than two feet.
Geogrid shall be laid either at the elevation and alignment as shown on
the Plans or to the limits approved by the Engineer in the field and shall be
oriented such that the roll length runs parallel to the roadway. When geogrid
rolls are placed side-by-side, or end-to-end, they shall be overlapped a minimum
of two feet or a greater distance recommended by the supplier and approved by
the Engineer. Overlap geogrid in the direction that fill will be spread. Geogrid
material shall be tensioned by hand and secured to the ground surface.
Care shall be taken to ensure that geogrid sections do not separate at
overlaps during construction. Placement of geogrids around corners may require
14-9
cutting of geogrid product and diagonal overlapping to ensure that excessive
buckling of grid material does not occur. No more than two layers of geogrid are
to be placed in direct contact with one another.
When very soft subgrade soils are encountered, fill material placed over
the geogrid shall be back dumped from trucks and bladed onto the geogrid in
such a manner that the fill rolls onto the geogrid ahead (e.g. by gradually raising
the dozer blade while moving forward), Geogrid installation procedures shall be
performed so that the geogrid does not “roll” or substantially deflect ahead of
the operation and possibly fold over onto itself as this undermines the structural
integrity of the geogrid. Care shall be taken during the initial lifts to avoid failing
the weak structure of the subgrade by preventing heavy equipment from placing
the initial lifts. On firmer but still structurally unsuitable subgrades, pneumatic
tired vehicles may operate directly upon the geogrid at slow speeds, less than 5
MPH, provided the geogrid does not require a protective coating.
Tracked construction equipment shall not operate directly on the geogrid.
A minimum fill thickness of 6 inches is required prior to operation of tracked
vehicles over the geogrid. Care shall be taken by the operators to avoid sudden
sharp turning. Fill material shall be placed over the geogrid to depth and
dimensions shown on the plans or as approved by the Engineer. The backfill
material placed in contact with the geogrid will be the approved aggregate base
material or a material with a maximum aggregate size of one and one-half inches
(1 ½”) and approved by the Engineer. For damaged or torn geogrids, or for
geogrids with protective coatings, any damage to the coating incurred during
transportation, storage or installation shall be repaired or replaced to the
satisfaction of the Engineer by Contractor at their expense. The coating shall be
restored to its original condition.
14-9 PAYMENT
Payment shall be at the unit price per cubic yard and shall include full
compensation for furnishing all labor, materials, tools, equipment and
incidentals, and for doing all work involved in the installation, and all other
necessary work as directed by the Engineer to conform with this item.
15-1
Section 15
WATER USED IN CONSTRUCTION
15-1 WATER USED IN CONSTRUCTION
Elsewhere in these Specifications there is specified the quality of water
used for concrete. This paragraph is intended to cover only water used in
construction.
The application of water shall be under the control of the Engineer at all
times and shall be applied in the amounts and at the locations designated by the
Engineer or as specified.
At the option of Contractor, excavation areas may be watered prior to
excavating the material.
All equipment used for the application of water shall be equipped with a
positive means of shut off.
Unless otherwise permitted by the Engineer, at least one mobile unit with
a minimum capacity of 1,000 gallons shall be available for applying water on the
project at all times.
Water for compacting embankment material, sub-base, base and surfacing
material, and for controlling dust shall be applied by means of pressure-type
distributors that will insure a uniform application of water.
If Contractor elects to do so, he may use chemical additives in water used
for compaction. If such additives are used, furnishing and applying the additives
shall be at Contractor’s expense. The right is reserved by the Engineer to
prohibit the use of a particular type of additive, to designate the locations where
a particular type of additive is to be used, if the Engineer has reasonable grounds
for believing that such use will be in any way detrimental to the work.
Arrangements for obtaining water needed for construction purposes must
be made with the supplying agency. Proof of such arrangement, including
method of reimbursement, shall be subject to inspection and approval by the
Engineer.
15-2
Unless otherwise approved by the Department of Utilities, connections to
the City’s water distribution system used to fill tank trucks or other such
equipment, shall include an air gap to separate the water supply from the
equipment to be filled. The Air-gap separation shall be at least double the
diameter of the supply pipe, measured vertically from the flood rim of the
receiving vessel to the supply pipe; however, in no case shall this separation be
less than one inch (1”). In no case will a direct connection to the City’s water
supply be allowed.
Water used in construction, including compacting fill, preparing sub-
grade, dust control, mixing concrete, concrete curing, laying and compacting
any type of base material, settling backfill in trenches or at structures, or water
used for any other purpose shall be provided and paid for in accordance with the
Department of Utilities “Water Hydrant Policy”. A copy of said policy is available
at Customer Services, 1395-35
th
Avenue.
15-2 PAYMENT
There will be no separate payment for water used during construction,
but the price therefore shall be considered included in whatever items
Contractor deems appropriate.
16-1
Section 16
STORMWATER QUALITY CONTROL
16-1 WASTEWATER AND GROUND WATER DISCHARGES
Contractor shall be responsible for the control, removal, and disposal of
any groundwater that may be encountered in the course of excavating and
backfilling trenches, placing pipe, or constructing any other improvements
associated with the project. Unless approved in writing by the Engineer,
groundwater and/or water from trench dewatering shall be free of sediment and
other construction materials before entering the City sewer or storm drain
system. Approval from the City’s Department of Utilities will need to be
obtained prior to any pumping or discharging of water to the City storm drain or
sewer system.
Issues which require the regulation of groundwater discharges include:
influence on existing or unknown contaminate plumes, exceeding sewer and
drainage capacity, excessive demands on facility infrastructure, pumping costs,
and maintenance worker safety.
It is the responsibility of the contractor to verify that groundwater is free
of contamination through a regular monitoring program.
All Groundwater discharges within the City of Sacramento must be
arranged through the Department of Utilities, (916)808-1400, 1395 35
th
Avenue,
Sacramento CA 95822.
DISCHARGE TO SEWER SYSTEM
If 25,000 gallons of water per day, or more, is discharged to the City’s
Combined Sewer/Stormwater System, or Separate Sewer System, Contractor will
be required to obtain a discharge permit from the Sacramento County Regional
Sanitation District Industrial Waste Section (916-875-6470). The City will
reimburse Contractor for fees paid to the County to obtain a discharge permit,
but Contractor shall be responsible to pay any fines levied if Contractor does not
comply with the permit requirements.
All new discharges to the City of Sacramento’s combined or separated
sewer sytems must be regulated and monitored by the Department of Utilities
(refer City Council Resolution #92-439). Groundwater discharges to the City’s
sewer system are defined as follows:
1. Construction dewatering discharges
2. Treated or untreated contaminated groundwater cleanup discharges
16-2
3. Uncontaminated groundwater discharges
Currently, two types of groundwater discharges to the combined and
separate sewer system are recognized by the Department of Utilities, which are:
limited discharges and long-term discharges. These types of discharges are
described as follows:
1. Short Term discharges”
Short term discharges are discharges of 30 days duration or less and must
be approved through the Department of Utilities by an approval letter.
2. “Long-term discharges”
Long term discharges are discharges of greater duration than 30 days.
Long-term discharges must be approved through the Department of Utilities and
the City Clerk through the MOU process.
DISCHARGES TO THE STORM DRAINAGE SYSTEM
Any discharges to the separate storm drainage system must be secured
with an individual National Pollutant Discharge Elimination System (NPDES)
permit from the Central Valley Regional Water Quality Control Board (Water
Board) and an MOU from the City. The NPDES permit must be received prior to
the City issuing an MOU to discharge to the City’s storm drainage system.
16-2 STORMWATER QUALITY
These requirements consist of regulations contained in the National
Pollution Discharge Elimination System (NPDES) Municipal Stormwater Permit
issued to the City and the City’s Stormwater Management and Discharge Control
Ordinance.
Contractor shall comply with all City and County of Sacramento air
pollution control rules, regulations, ordinances, and statutes which apply to any
work performed pursuant to the contract, including any air pollution control
rules, regulations, ordinances, and statutes, specified in the Government Code.
Contractor shall be responsible for the control of dust within the limits of the
project at all times including weekends and holidays in addition to normal
working days. Contractor shall take whatever steps are necessary or required by
the Engineer to eliminate the nuisance of blowing dust to prevent sediment,
debris, or litter from entering the City storm drain system.
16-3
16-3 EROSION, SEDIMENT, AND POLLUTION CONTROL
Contractor shall be responsible for the implementation and maintenance
of erosion, sediment and, pollution control measures, otherwise known as Best
Management Practices (BMPs), within the limits of the Work site and all areas
impacted by the project at all times during the course of construction, including
evenings, nights, weekends and holidays in addition to the normal working days,
in accordance with the provisions of Chapter 15.88 of the Sacramento City Code.
Contractor shall provide the following erosion, sediment, and pollution
control Best Management Practices (BMPs) when and where applicable:
Contractor shall place Filter Bags in and Gravel bags around any storm
drain inlets which receive runoff from the limits of the construction zone,
including storage and staging areas. Alternative storm drain inlet protection
BMPs may be used with approval of the Engineer. (See Section 38, drawings Q-
20 and Q-30)
Contractor shall cover all stockpiles prior to a forecasted rain event
and/or place gravel berms (or approved equal) around material piles as required
to prevent migration of material to gutters or storm drains.
Contractor shall keep gutter flowlines unimpeded and free of soil, debris,
and construction materials at all times.
Contractor shall install and maintain an effective construction entrance
at any soil to concrete/asphalt interface used by Contractor vehicles and
equipment in accordance with Section 38, drawing Q-10.
Contractor shall place silt fences, fiber rolls or approved equal at any soil
to concrete/asphalt interface at which soil may be washed onto the
concrete/asphalt in accordance with Section 38, drawings Q-40 and Q-50.
Wash water, slurry and sediment from concrete or asphalt saw-cutting
operations shall not be allowed to enter the City storm drain system, but instead
must be collected and disposed of, by Contractor, in a manner approved by the
Engineer.
Contractor is required to implement, at a minimum, the following
housekeeping practices:
16-4
Site Cleanup:
Contractor shall be responsible for the control of dust, mud and debris
resulting from Contractor's operations within the limits of the project at all times
including weekends and holidays in addition to normal working hours. Contractor
shall take whatever steps are necessary or required by the Engineer and daily
clean up throughout the project shall be required as Contractor progresses with
the work.
Daily or as needed, all paved areas within the limits of the project shall
be cleaned and free of sediments, asphalt, concrete and any other construction
debris. Contractor shall not clean sediment and debris from the street by using
water to wash down streets.
Spillage of earth, gravel, concrete, asphalt, or other materials resulting
from hauling operations along or across any public traveled way shall be removed
immediately by Contractor at their expense. If site is not kept sufficiently clean,
the City will take measures to clean it and subtract the cost thereof from
payments owing the Contractor.
Solid Waste Management:
Contractor shall maintain a clean construction site. Contractor shall
provide designated areas for waste collection. The waste collection areas shall
be leak-proof containers with lids or covers. Site trash shall be collected daily
and placed in the disposal containers. Contractor shall make arrangements for
regular waste collection. Contractor shall also regularly inspect the waste
disposal areas to determine if potential pollutant discharges exist.
Hazardous Material Storage and Delivery Area:
Contractor shall provide one central hazardous material storage and
delivery area (HMSDA) for the duration of the project. Examples of hazardous
materials include pesticides and herbicides; fertilizers; detergents; petroleum
products; acids; lime; glues; paint; solvents and curing compounds. This area
shall be protected such that polluted runoff will not be allowed to leave the
HMSDA site. Contractor shall regularly inspect the HMSDA site to ensure that any
hazardous or non-hazardous materials have not spilled.
Concrete Waste Management:
Contractor shall arrange for concrete wastes to be disposed of off-site or
in one designated on-site area. Concrete wastes, including left-over concrete
and material from washing out the concrete truck, shall not be disposed or
washed into the storm drain system. A designated on-site concrete waste
16-5
containment area shall be provided. The site shall be bermed and lined to keep
concrete waste from leaving the containment area. The dried concrete waste
shall be removed and disposed of properly by Contractor at their expense.
Spill Prevention and Control:
Contractor shall be responsible for instructing employees and sub-
contractors about preventing spills of hazardous materials such as equipment
fuel, and about controlling spills if they occur. Proper spill control and cleanup
materials and procedures shall be kept on site near the storage and equipment
fueling areas and updated as materials change on site. Contractor is strictly
responsible for the prevention, clean-up and consequences of any hazardous
materials spills.
Throughout the duration of the project, Contractor shall inspect and
maintain, in effective condition, all erosion, sediment, and pollution control
BMPs before and after each storm event and as needed. Contractor shall
immediately correct or replace any ineffective BMPs.
More information about required Best Management Practices and proper
Housekeeping Practices can be obtained by referring to the City of Sacramento's
Administrative and Technical Procedures Manual for Grading, Erosion and
Sediment Control available at https://www.cityofsacramento.org/-
/media/Corporate/Files/DOU/Specs-Drawings/Sediment-control-
manual.pdf?la=en
Contractor shall prepare and submit an erosion, sediment and pollution
control plan (ESC Plan) to the Engineer for review. The submittal shall include
a description of all pollutants to be managed during construction, and all
activities that could potentially impact a waterway. Detail plan of areas to be
disturbed and staging areas. All proposed BMP measures to be implemented to
mitigate pollutants and activities listed. The ESC Plan shall be submitted a
minimum of 48 hours prior to start of the work. Contractor shall not begin work
until an accepted ESC Plan is on file with the Engineer. The erosion, sediment
and pollution control plan shall be updated as necessary and re-submitted to the
Engineer.
16-6
16-4 ENFORCEMENT
Per City Code Sections 15.88, 13.16 and 1.28, Contractor shall be subject
to Notice of Violations (NOVs) resulting in possible Stop Work Orders and
Administrative Penalties of up to $4,999 per day for non-compliance of this
section of the Special Provisions.
Per the State’s Porter Cologne Water Quality Act, Contractor shall also be
subject to inspection by Staff from the Central Valley Regional Water Quality
Control Board who have the authority to issue Notices of Violation (NOVs) and
Penalties of up to $10,000 per day for non-compliance. Contractor shall be liable
for any fines issued to the project by the State or Federal Government for NPDES
non-compliance due to Contractor negligence.
The City reserves the right to take corrective action and withhold the
City’s costs for corrective action from progress payments or final payment in
accordance with Section 7, Retention of Sums Charged against Contractor, of the
Agreement. Any fines, including third-party claims, levied against the Agency as
a result of Contractor’s non-compliance are Contractor’s sole responsibility and
will be withheld from progress payments or final payment in accordance with
Section 7, Retention of Sums Charged against Contractor, of the Agreement.
16-5 PAYMENT
There will be no separate payment for Water Quality Control and the cost
therefore shall be considered included in whatever item Contractor deems
appropriate.
17-1
Section 17
LAYING AGGREGATE BASE
17-1 LAYING AGGREGATE BASES
Aggregate bases shall be placed on the prepared sub-grade to such a depth
that when thoroughly compacted it will conform to the grades and dimensions
shown on the Plans. The material shall be placed from vehicles through an
approved spreader box or other device. At locations which are inaccessible to
spreading equipment, the material may be spread by any means to obtain the
specified results. Material shall be placed and compacted in layers not to exceed
six inches (6”).
Segregation of the material shall be avoided and the material, as spread,
shall be free from pockets of rock or fine material. Segregated material must
be remixed by harrowing and blading.
After placing the material and shaping it by blade the compaction shall be
accomplished by tandem steel-wheel rollers weighing not less than 12-tons. In
lieu of tandem steel-wheel rollers, a pneumatic-tired roller of either the single
or double-axle type may be used. A pneumatic-tired roller must have a width
not less than four feet (4’) nor more than seven feet (7’). The space between
the side walls of adjacent tires shall not be greater than five inches (5”), and on
the double axle type the rear tires shall be staggered with relation to the front
tires. Such a roller will be equipped with mechanical means of distributing the
contact pressure uniformly among all tires and all tires shall be uniformly
inflated. The roller must be so constructed that the weight per tire can be varied
between 1000 and 2000 lbs. The operating weight of a pneumatic roller shall be
subject to the control of the Engineer. Alternative compacting equipment may
be used when approved by the Engineer.
Areas inaccessible to the roller shall be compacted by power tamping until
the base material is compacted to a relative compaction of at least 95 percent.
Aggregate bases shall be compacted to a minimum relative compaction of
ninety-five percent (95%) in accordance with the testing requirements of Section
14-5 of these Specifications.
The surface after compaction shall be tight and smooth and conform to
the requirements of Section 26 of the State Specifications. All water applied to
the aggregate base as it is placed on the job shall conform to Section 15 of these
Specifications.
17-2
17-2 PAYMENTS
Payment for laying aggregate base shall be either at the contract price
bid per ton or per cubic yard delivered to the job and placed according to the
Plans and Specifications. Quantities of aggregate base to be paid for by the cubic
yard will be calculated on the basis of the dimensions shown on the Plans
adjusted by the amount of any change ordered by the Engineer. No allowances
will be made for any aggregate base placed outside said dimensions unless
otherwise directed by the Engineer.
The weight of material to be paid for will be determined by deducting from the
weight of material delivered to the work, the weight of water in the material,
at the time of weighing, as determined by California Test 226, in excess of one
percentage point more than the optimum moisture content as determined by
ASTM D 1557. The weight of water deducted as provided herein will not be paid
for.
Payment shall include full compensation for furnishing the material,
placing it on the roadway, applying water, compacting the material, finishing
the surface, and furnishing all labor and equipment necessary to perform the
work.
17-3 LAYING ROAD-MIXED AND PLANT-MIXED CEMENT TREATED BASES
Road-mixed and plant-mixed cement treated bases shall be spread and
compacted in accordance with Section 27 of the State Specifications.
17-4 LAYING ROAD-MIXED AND PLANT-MIXED CEMENT TREATED BASES
Road-mixed lime treated base shall be constructed in accordance with
Section 24 of the State Specification.
Lime to be mixed with the existing material shall conform to the
requirements set forth in Section 10-10 of these Specifications.
The percentage of hydrated lime to be added by weight shall be as set
forth in the Special Provisions.
Removal of rocks greater than two and one-half inches (2½”) in size shall
be included in the cost of the base in place.
17-3
Lime treated base shall be compacted to a minimum relative compaction
of ninety-five percent (95%) in accordance with Section 14-5 of these
Specifications.
Lime treated base shall be paid for at the contract price bid per square
yard which shall include full compensation for furnishing all labor, materials,
tools, equipment and incidentals, and for doing all work involved in constructing
lime treated base, complete in place, as shown on the Plans and as directed by
the Engineer.
18-1
Section 18
HEADERS
18-1 GENERAL DESCRIPTION
Headers shall be placed upon an approved subgrade prepared in
conformance with the requirements of Section 14 of these Specifications.
Headers shall be set so that the top edge does not vary more than one-quarter
inch (¼”) from a true, straight line in the length of the header, and shall be
placed to the required grade and alignment of the edge of the finished
pavement. They shall be supported so that during the entire operation of placing,
rolling, and finishing the pavement, they will not, at any time, deviate laterally
more than one-quarter inch (¼”) or vertically more than one-eight inch (⅛”)
from proper line and grade.
18-2 HEADER JOINTS
Header joints shall be so designed that a non-yielding support is obtained
and double supporting stakes shall be provided at the joints. Headers shall be
spliced with a section of pressure treated Douglas Fir four feet (4’) in length,
shall be the same cross sectional dimension as the header and shall be nailed
lengthwise, lapping the joints.
18-3 HEADER MATERIAL
Headers shall be pressure treated Douglas Fir, in accordance with
Standard Grading Rules of the West Coast Lumbermen’s Association, and shall
consist of at least two inch thick nominal lumber. Their depth shall be equal to
the specified depth of the edge of the asphalt pavement plus at least one half
the depth of the aggregate base material, but shall not be less than six inches
(6”) deep. Timbers with rounded edges, ends or corners, or split ends, shall not
be used. Trex Header or approved equal shall have minimum of a one foot (1’)
metal stakes installed at three feet (3’) on center. The header shall be secured
to the stake with a minimum of two galvanized or deck coated screws.
Headers shall be secured by nailing to pressure treated Douglas Fir side
stakes spaced not more than four feet (4’) apart and driven vertically in such a
manner that their tops shall be one inch (1”) below the top edge of the header.
These stakes shall not be less than nominal 2x3 lumber, and shall be driven a
minimum of eighteen inches (18”) below the subgrade elevation. The length and
depth shall be increased when the character of the soil is such that it will not
provide sufficient rigidity.
18-2
18-4 CONCRETE HEADERS
Concrete header shall be placed on native undisturbed grade or for
disturbed area the subgrade shall have a compaction rate of 85%. The curb shall
be a minimum of 6” wide and 6” thick. It shall be made out of Portland cement
concrete Type II, Class “C” and in conformance with Section 10-5. Metal
reinforcement is required to be installed in the curb and it needs to be a
minimum of #3 rebar running continuously throughout the length of the curb. At
joints or at beaks on the rebar the contractor shall overlap the sections of rebar
thirty (30) times the width of the rebar.
Expansion joints and score line shall conform with Section 24-6 of these
specifications. Expansion joints shall be placed at twenty feet (20’) on center
and score lines at ten feet (10’) on center.
18-5 MANTENANCE OF HEADERS
Headers must be trued up and maintained to the required line and grade
for a distance of at least one (1) day’s run ahead of the placing of asphaltic
concrete. When headers do not conform to the correct line and grade, or have
become loose, this shall be considered sufficient cause to stop work until the
fault is corrected to the satisfaction of the Engineer.
18-6 PAYMENT
Payment for headers shall be either at the lump sum price bid or the
price bid per lineal foot, as indicated in the contract documents, and shall
include full compensation for furnishing all labor, materials, tools, equipment,
processing and incidentals and for doing all work involved in placing and
maintaining headers.
19-1
Section 19
PORTLAND CEMENT CONCRETE PAVEMENT, JOINTS AND CURING
19-1 GENERAL DESCRIPTION
Portland Cement concrete pavement shall be constructed to the
dimensions, lines and grades shown on the Plans. Unless otherwise provided in
the Special Provisions, the pavement shall be constructed of Class “B” concrete,
conforming to the requirements of Section 10-5 of these Specifications. Unless
otherwise indicated in the Special Provisions, the Portland Cement used in the
concrete shall be Type II as described in Section 10-1 of these Specifications.
19-2 SUBGRADE
Sub-grade for concrete pavement shall be prepared as specified in Section
14-7 of these Specifications. Sub-grade shall also be free of all loose and
extraneous material when concrete is placed thereon and shall be uniformly
moist. Any excess water on the surface shall be removed prior to placing
concrete as directed by the Engineer.
19-3 SIDE FORMS
Side forms shall be furnished and installed in accordance with Section 18
of these Specifications.
19-4 CONCRETE CUTTING
Where new concrete is to join existing concrete, the existing concrete
shall be cut to a true line to a minimum depth of one and one-half inches (1½”)
with a power driven abrasive type saw.
19-5 EXPANSION JOINTS IN ALLEY PAVEMENT
An expansion joint shall be placed ten feet (10’) from each end of the
work and every twenty feet (20’) there from and at other places shown on the
Plans. The expansion joint material shall be not less than three-eighths inch
(⅜”) in thickness and shall conform to Section 10-4 of these Specifications.
19-6 PLACING CONCRETE PAVEMENT
Contractor shall make adequate advance arrangements for preventing
delay in delivery and placing of the concrete. An interval of more than 45
minutes between placing of any 2 consecutive batches or loads shall constitute
cause for stopping paving operations, and Contractor shall make a contact joint
19-2
at his expense at the location and of the type directed by the Engineer in the
concrete already placed.
Slip-form paving and finishing machines shall be in satisfactory adjustment
and operational condition. Prior to placing concrete, Contractor shall
demonstrate proper adjustment of all screeds and floats on slip-form pavers by
measurements from grade stakes driven to known elevation. Satisfactory
operation and adjustment of all propulsion and control equipment, including pre-
erected grade and alignment lines, shall be demonstrated by moving slip-form
pavers and finishing machines over a five hundred foot (500’) length of prepared
sub-grade with all propulsion and control equipment fully operational.
Unless otherwise required by these Specifications, the Plans or the Special
Provisions, pavement shall be constructed in twelve foot (12’) traffic lane widths
separated by contact joints, or monolithically in multiples of twelve foot (12’)
traffic lane widths with a longitudinal weakened plane joint at each traffic lane
line.
All concrete shall be placed while fresh. The use of water for retempering
any concrete will not be permitted. The temperature of the concrete mix at the
time of placement shall not exceed 90° F.
19-7 FINISHING CONCRETE PAVEMENT
The surface of the concrete shall be finished smooth and true to grade
with wooden floats. Floats shall be operated from the end of the pavement and
parallel with the centerline of the pavement by means of a long handle.
The edge of the float shall be used to cut down all high areas and the
material so removed shall be floated into the depressions until a true surface is
obtained.
Finishers and floatmen shall be required to remain at work, after placing
of concrete has stopped, long enough to complete the finishing of the pavement
when the concrete has hardened sufficiently.
19-8 CURING PORTLAND CEMENT CONCRETE PAVEMENT
The curing of Portland Cement concrete pavement shall be with a
pigmented sealing compound as specified in Section 10-6 of these Specifications.
The application of the sealing compound shall be in accordance with the
requirements of Section 90, “Concrete,” of the State Specifications.
19-3
19-9 PROTECTION OF PAVEMENT
Contractor shall protect the surface of the concrete pavement against all
damage and markings, both from pedestrian and other traffic. Barriers shall be
placed at the proper locations to protect the concrete from traffic.
The concrete pavement shall be maintained at a temperature of not less
than 45°F for 72 hours after placement. When required by the Engineer,
Contractor shall submit a written outline of his proposed methods for protecting
the concrete pavement and maintaining the required temperature.
When required by the Special Provisions, bridges or other devices of the
type shown on the Plans, or approved by the Engineer, shall be installed across
the pavement to provide crossing for the public and private traffic such as will
prevent damaging or marking the pavement.
The crossing devices shall be maintained in satisfactory condition
throughout the period of use at any location, and, when no longer required, shall
be removed by and become the property of Contractor.
After the Engineer has ordered the pavement opened to traffic,
Contractor will not be held responsible for damage resulting from its use by
public traffic, provided, however, that Contractor shall be liable for any damage
to the newly laid pavement caused by his operations or due to an inferior
product.
19-10 PAVEMENT DAMAGE AND REPAIR
All damage done to or openings cut in concrete pavement or alley
crossings during the progress of the work shall be repaired by Contractor under
the direction of the Engineer, using for such repairs, materials conforming to the
requirements of these Specifications.
19-11 PAYMENT
Clearing, grubbing, and tree removal prior to grading for laying of
concrete pavement shall be paid for as set forth in Section 12 of these
Specifications.
Excavation and fill will be paid for as provided for in Section 14 of these
Specifications.
Sub-grade preparation shall be paid for in accordance with Section 14-7
of these Specifications.
19-4
Payment for portland cement concrete pavement shall be per cubic yard
of concrete required to construct the pavement to the lines, grade and to the
thickness shown on the Plans. Should the sub-grade be low or irregular, thus
requiring additional yardage above that computed from the thickness specified
on the Plans, no allowance shall be made for such additional concrete yardage.
The price paid per cubic yard for furnishing and placing portland cement
concrete in pavements shall include full compensation for preparing and finishing
the sub-grade, cutting existing concrete, furnishing and placing the concrete,
furnishing and placing pre-molded joint filler, furnishing and installing expansion
joint material, finishing concrete surface, furnishing and applying curing
compound and bond breaker, protecting the pavement, repairing any damage
thereto before final acceptance and all other labor and materials to complete
the work.
20-1
Section 20
CONCRETE IN STRUCTURES
20-1 GENERAL
“Concrete in structures” shall mean concrete placed in structures such as
culverts, headwalls, retaining walls, drop inlets, pump sumps, drain inlets, slabs,
foundations and other concrete structures. Concrete in structures shall be Class
“B” unless otherwise indicated. Concrete in pavements, curbs, gutters, and
sidewalks, shall be specifically excluded from this section.
The publications referred to hereinafter form a part of this specification
to the extent referenced. The publications are referred to in the text by the
basic designation only. The latest edition of publications in effect at the time of
bid shall govern.
American Concrete Institute (ACI) Standard:
ACI SP-15 Field Reference Manual: Standard Specifications for
Structural Concrete with Selected ACI and ASTM references.
ACI 211 Recommended Practice for Selecting Proportions for
Concrete.
ACI 301 Structural Concrete for Buildings.
ACI 302 Guide for Concrete Floor and Slab Construction.
ACI 304 Guide for Measuring, Mixing and Placing Concrete.
ACI 305 Hot Weather Concreting.
ACI 306 Cold Weather Concreting.
ACI 309 Consolidation of Concrete.
ACI 318 Building Code Requirement for Reinforced Concrete, with
Commentary.
ACI 347 Guide to Formwork for Concrete
ACI SP-4 Publication 4 Formwork for Concrete
20-2
American Society for Testing and Materials (ASTM) Standards:
ASTM C 31
Method of Making and Curing Concrete Test Specimens.
ASTM C 33 Concrete Aggregates.
ASTM C 39 Compressive Strength of Cylindrical Concrete Specimens.
ASTM C 94 Ready Mixed Concrete.
ASTM C 143 Slump of Portland Cement Concrete.
ASTM C 150 Portland Cement.
ASTM C 171 Sheet Materials for Curing Concrete.
ASTM C 172 Method of Sampling Freshly Mixed Concrete.
ASTM C 192 Making and Curing Concrete Test Specimens in the
Laboratory.
ASTM C 227
Test for Potential Alkali Reactivity of Cement-Aggregate
Combinations.
ASTM C 231 Air Content of Freshly Mixed Concrete by the Pressure
Method.
ASTM C 260 Air Entraining Admixture for Concrete.
ASTM C 289 Test of Potential Reactivity of Aggregates.
ASTM C 295 Petrographic Examination of Aggregates.
ASTM C 309 Liquid Membrane Forming Compounds for Curing
Concrete.
ASTM D 98 Calcium Chloride.
ASTM D 1785
Poly (Vinyl Chloride 40, 80 and 120.) PVC Plastic Pipe,
Schedules
ASTM C 138 Unit Weight, Yield and Air Content of Concrete
ASTM C 173 Air Content of Concrete by the Volumetric Method
20-3
U.S. Dept. of Commerce, National Bureau of Standards Publications,
Product Standards:
PS1 Construction and Industrial Plywood
West Coast Lumber Inspection Bureau (WCLB) Standard:
No. 16 Standard Grading and Dressing Rules for Douglas Fir,
Western Hemlock, Western Red Cedar, White Fir, and Sitka
Spruce Lumber.
National Forest Products Association (NFPA):National Design Specification for
stress grade lumber and its fastening.
Western Wood Products Association (WWPA): Western Lumber Grading Rules.
Concrete shall also conform to Section 10 of the Standard Specifications.
Notes pertaining to concrete on the Plan sheets are a part of these
Specifications.
Contractor shall submit the following in accordance with Section 5-7:
1. Proposed mix designs, including admixtures and curing material
2. Certificate of Compliance that concrete meets the specified requirements
and delivery tickets for all concrete delivered to the project site.
3. Shop Drawings including:
a. Formwork:
Drawings of all formwork showing form plywood patterns,
formwork, and ties.
b. Concrete placement:
Vertical limits of concrete placements horizontal lifts, and
construction joints.
20-4
c. Shoring:
Drawings and structural calculations showing members,
connections, and anchorage of the proposed shoring system. Calculations
and drawings shall be stamped by a Civil Engineer currently licensed in
the State of California.
20-2 FOOTINGS
Footing elevations shown on the Plans shall be considered as approximate
only and only when excavation is completed and the character of the supporting
natural ground is ascertained can the elevation of the bottom of footings be
determined by the Engineer.
20-3 DRAIN INLETS
Drain Inlets shall conform to the Standard Drawings contained within
Section 38 of these Specifications.
Concrete for drain inlets shall be Class “A” or “B”, and shall conform to
Section 10 of these Specifications. The concrete box portion of the drain inlet
shall be cast to the proper grade in a maximum of two (2) placements of
concrete. Use of grout to adjust the drain inlet frame to the proper grade will
not be permitted without specific approval of the Engineer.
Reinforcing bar supports or other approved means shall be used to hold
the frame at proper grade during final placement of concrete. Broken pieces of
concrete, or other debris, shall not be used for this purpose. At the option of
Contractor, drain inlets may be furnished and installed as precast units, or the
units may be combined precast and cast-in-place structures, provided the
structures in place substantially conform to cast-in-place construction as
specified in these Specifications.
20-4 CONCRETE FORMWORK
Forms shall be designed, constructed, and maintained so as to insure that
after removal of forms, the formed concrete will have true surfaces free of
offset, waviness or bulges, and will conform accurately to the indicated shapes,
dimensions, lines, elevations, and positions.
Form shall be provided with accessories and openings in forms as required
for placement of equipment and materials. Remove forms after concrete has
cured.
Unless otherwise specified or approved by the Engineer, form materials
shall be as follows:
20-5
1. Plywood:
PS 1, B-B Plyform Class 1, EXT-APA, edge-sealed, 5/8" thick when studs
are spaced 12" on center and 3/4" thick when studs are spaced 16" on center. As
an alternate OSB may be used, of equal quality, strength and dimensions.
2. Wood strips for forming reveals, chamfers and quirks:
Any close grain hardwood or softwood, free of knots.
3. Framing lumber:
Douglas Fir "Standard" grade, sized to uniform width and depth.
4. Sheathing:
Douglas Fir "Construction" grade boards and sheathing, 10" maximum
width.
Form accessories shall be as follows:
1. Form Ties:
Ties for concrete building structures, exposed to view shall be adjustable
type, arranged to leave no metal within 1" of surface. They shall have no lugs,
cones, or other devices that will leave holes larger than 1" diameter in exposed
concrete surfaces. In all other instances, “Snap” ties and spreaders shall be used
with approved clamps or separate metal spreaders. Do not use wood spreaders
or wire ties.
2. Form Coatings:
Burke Concrete Accessories, Inc.'s "Burke Release", Nox-Crete, or
approved equal. Apply per manufacturer's printed instructions.
Contractor shall provide openings for mechanical and electrical work and
work of other sections shall place items to be incorporated in concrete and
support on formwork and shall seal forms around openings to prevent concrete
seepage.
The design and engineering of all formwork, falsework and shoring, as well
as its construction and protection, is Contractor's responsibility and shall conform
to ACI 347 unless otherwise directed or approved.
20-6
Forms for exposed concrete surfaces shall be designed and constructed so
that the formed surface of the concrete does not undulate excessively in any
direction between studs, joists, form stiffeners, form fasteners, or wales.
Undulations exceeding either 3/32 inch or 1/270 of the center to center distance
between studs, joists, form stiffeners, form fasteners or wales will be considered
to be excessive.
Forms shall be constructed to provide concrete conforming to dimensions
shown, and to tolerance limits listed in ACI 301 "Specifications for Structural
Concrete for Buildings".
Installation of forms shall conform to ACI 301, 347, P4 and this section.
Forms shall be designed for easy removal. Contractor shall not pry against face
of concrete, shall use wooden wedges only, and, in order that reused forms will
not contain patches resulting from alterations, forms for concrete exposed-to-
view shall be reused only on identical sections.
Forms shall not be used if there is any evidence of surface wear or tear
which would impair the quality of the exposed-to-view concrete. Forms shall be
thoroughly cleaned and re-lubricated before reuses. Formwork for exposed-to-
view concrete shall be observed continuously while concrete is being placed to
see that there are no changes of elevation, plumbness, or camber. If, during
construction, any weakness develops and the falsework shows any undue
settlement or distortion, the work shall be stopped, the affected construction
removed, if permanently damaged, and the falsework strengthened.
Forms shall be substantial, true to line and level, sufficiently tight to
prevent leakage and shall conform to indicated dimensions. Locate form ties for
exposed concrete in straight horizontal and vertical lines and as indicated on
Drawings and specified herein. Provide cleanout holes at bottom of forms.
Remove debris before concrete is placed. Construct forms for exposed surfaces
so that joints in forms are either horizontal or vertical and are located to the
pattern indicated.
External corners on all concrete shall be formed with chamfer strips in
corners of forms to form bevel at external angles. All form joints in forms for
exposed-to-view concrete shall be sealed with specified form tape to prevent
leakage. Camber soffits to accommodate anticipated deflections caused by wet
concrete and construction loads. Provide positive means of adjustment for
shores and struts. Take up settlement as concrete is placed.
20-5 REMOVAL OF FORMS
Remove forms, shoring and bracing carefully to avoid damage to fresh
concrete, but not before concrete is capable of self support and support of
20-7
construction loads. Do not pull tie rods until concrete is hard enough to permit
withdrawal without damage to concrete. Pull ties that are entirely withdrawn
from wall toward inside face.
Regardless of strengths attained by concrete, leave forms in place for
following periods when supporting:
1. Vertical surfaces: 3 days minimum
2. Slabs, on grade: 7 days minimum
3. Beams, girders and elevated slabs: 15 days minimum, but do not remove
vertical support until concrete has reached its 28-day strength.
Before reuse of plywood forms, thoroughly clean, sand and recoat them
with form coating. Do not reuse plywood that has torn grain, patches, worn
edges, damaged phenolic resin covered surfaces, or other defects which would
impair texture of finished surface. Other wood forms shall be prepared for reuse
by thorough cleaning and recoat with form coating. Repair damaged forms and
replace loose or damaged boards.
Live loading of new construction while reshoring is under way is not
permitted. Do not over stress new construction by over tightening reshores.
Leave reshores in place until concrete has reached its specified 28-day strength.
Reshore floors that support shores under wet concrete, or leave original shores
in place. Reshores shall have at least half the capacity of the shores above and
be distributed in approximately the same pattern. Leave these reshores in place
until freshly placed concrete has reached 75% of its specified 28-day strength.
For concrete exposed-to-view in completed structures use specified "B-B"
or better plyform plywood or phenolic resin covered form board.
For concealed concrete, plywood, lumber or steel is acceptable. Footings
may be poured directly against earth banks where soil conditions are such that
vertical banks will remain stable during placing operations. Earth forms at walls
are not permitted.
20-6 REINFORCEMENT
Reinforcement shall conform to Section 21 of the Standard
Specifications.
20-7 DESIGN OF MIXES
Contractor shall be responsible to design concrete mixtures resulting in
20-8
the required 28-day compressive strength and other required characteristics.
Design of mixes shall be in accordance with Section 10.
20- 8 PREPARING TO PLACE CONCRETE
Contractor shall provide inserts, required or shown on the Plans:
embedded items, including installation of work built into concrete such as
waterstop sleeves, anchor bolts, wood nailers, reglets, frames and sleeves for
piping, conduit and fittings. Forms shall be cut and reinforced as required to
accommodate them. No concrete shall be placed until all inserted items are
installed in their proper locations, secured against displacement, cleaned,
inspected and approved. Furnish ties and supports necessary to keep embedded
items in place when concrete is placed.
Contractor shall remove excess water from forms before concrete is
deposited, and shall remove hardened concrete, debris, and foreign materials
from interior of forms and from surfaces of mixing and conveying equipment.
Prior to placing concrete, Contractor shall wet wood forms sufficiently to
tighten up cracks and shall wet all other materials sufficiently to reduce suction
and maintain concrete workability.
Contractor shall lightly dampen subgrade no more than 24 hours in
advance of concrete placement, but do not muddy. Reroll where necessary for
smoothness and remove loose earth material.
Set screeds for flatwork placement at walls and at maximum of 8-foot
horizontal distance between adjacent screeds.
Concrete shall not be placed during rainy weather unless approved
measures are taken to prevent damage to concrete.
20- 9 FLATNESS TOLERANCE FOR FLOOR SLABS
Finish slabs monolithically. Uniformly slope floor slabs to provide positive
draining of indicated areas. Special care shall be taken so that a smooth, even
joint is obtained between successive pours.
Finished surfaces shall be true plane surfaces with no deviation in excess
of 1/8 inch measured using a 10 feet long straight edge.
Replace or repair any slab which fails to meet this standard. If slabs fail
to drain as indicated, remove drains and faulty floor section and refinish topping
so that it drains according to the Drawings. No deviations will be allowed.
20-9
20-10 PLACING CONCRETE
Place concrete only after subgrade, forms, and reinforcement have been
approved. Limit free vertical drop in concrete walls or columns to three (3) feet.
In other concrete, limit the drop to five (5) feet. Deposit concrete in horizontal
layers not more than 18" deep and continue pouring until section is completed.
Control rate of pouring and depth of layers so that each layer will be covered
within one hour after it is poured. Pour columns to top and allow to settle two
(2) hours before additional concrete is placed. Place concrete continuously
between pour joints.
Grout mix shall be regular concrete mix with ½ the large aggregate
omitted. Use to cover the following before additional concrete is placed:
1. Flat form surfaces next to congested steel.
2. Construction joints.
3. Top of column and wall footings.
4. On surfaces where concrete has set.
Vibration and tamping shall be performed as concrete is placed in forms,
to work concrete around reinforcing steel, built-in items and into corners and
angles. Extra care shall be given to work architectural concrete around inserts,
reveals, quirks, corners and plastic cones of ties to preclude rock pockets, air
pockets, and other defects, and to produce sharp corners, edges and smooth
surfaces. Provide mechanical vibrators operated by experienced workers for
agitating concrete in forms. Vibrate thoroughly within five (5) minutes after layer
is placed. Carry vibration well into previous layer. Vibrators shall not be used
to transport concrete inside forms. Internal vibrators shall maintain a speed of
not less than 7,000 impulses per minute when submerged in concrete.
Supplement vibration by suitable methods to eliminate voids along forms for full
depth of layer as directed. Do not allow vibrators to strike overlaid plywood
surfaces. Do not use vibrators to work concrete along forms. Keep at least one
spare vibrator on job at all times while concrete is being placed. Comply with
ACI Committee 309 Consolidation of Concrete, Committee Report.
Upon completion of a pour and after concrete has partially hardened,
wash scum or laitance off concrete surface with stiff brush and stream of water.
When work is resumed, brush clean with wire brushes or sandblast, then place
fresh concrete.
The following applies when pumping concrete:
20-10
1. General:
Do not use aluminum or aluminum lined pipe. Prevent concrete from
contacting aluminum fittings
2. Mix:
Do not add more water to mix unless approved by the Engineer. Check
that the mix design entered on delivery ticket complies with that ordered.
20-11 CONSTRUCTION JOINTS
The location and design of joints not shown or specified are subject to
approval of the Engineer prior to placement of concrete.
Where Horizontal joints occur in exposed concrete, set smooth painted
wood strips in form to provide a straight and level joint in which upper pour laps
lower pour. Place concrete level with, but not above top of pour joint strip as
shown on Drawings. Allow 24 hours before concrete is placed over horizontal
joints. Remove loose material and laitance. Clean by sandblasting, or wire
brushing. Allow enough time between placing of adjacent pour sections to
provide for initial shrinkage. Horizontal joints will not be allowed in beams,
girders and slabs unless otherwise indicated.
Vertical joints not shown on the Drawings shall be so made and located as
to least impair the strength of the structure and shall be approved by the
Engineer prior to placement of concrete.
20-12 EXPANSION JOINTS AND RUBBER WATERSTOPS
When premolded joint filler is shown on the Plans or specified, the filler
shall be placed in correct position before concrete is placed against the filler.
The edges of the concrete at the joint shall be edger finished. Unless otherwise
provided in the Special Provisions, expansion joint material shall be as specified
in Section 10-4 of these Specifications.
Neoprene or rubber water stops shall be placed where shown on the Plans,
and shall conform to the requirements of Section 51, “Concrete Structures,” of
the State Specifications.
20- 13 CURING OF CONCRETE
Concrete shall be cured in accordance with Section 90, “Concrete,” of the
State Specifications.
20-11
20- 14 SURFACE FINISHES OF CONCRETE STRUCTURES
The ordinary surface finish required on concrete structures shall be that
obtained by careful forming, proper consolidation and even texture of concrete.
Immediately after forms have been removed, all form bolts shall be cut
off one inch (1") below the finished surface of the structure or snap ties removed.
Remove honeycombed and other defective concrete to sound concrete, but not
less than 1" deep. Make the walls of the cut area perpendicular to the surface.
Do not feather out the edges. Dampen the patch area and the adjacent area six
(6) inches around the patch area. Brush the patch area with a bond of neat
cement and water paste and apply patching mortar when the water sheen is off
the bond. The holes remaining shall be filled with cement mortar using one (1)
part cement to two (2) parts sand with the least water required to produce a
workable mass. Rework this mortar until it is the stiffest consistency that will
permit placing. After entirely filling voids, strike off the mortar slightly higher
than the surrounding surface, let set for one hour and finish flush with the
surrounding surface.
Any defects in the concrete surface caused by poor material in the forms,
poor form construction, or by voids or pockets in the concrete, yet are not
sufficiently severe to cause rejection of the pour, will be repaired and finished
to make the surface finish uniform. The Engineer will direct Contractor to
correct such defects and they shall be repaired without extra compensation.
The surface finish of any structure may be given further treatment if such
a requirement is called out on the plans or by the Special Provisions.
20-15 FINISHING FORMED SURFACES
Finish formed surfaces by removing any and all fins. The tolerances of
finished formed surfaces shall conform to ACI 301.
20-16 FLATWORK
Place floor slabs on grade in alternate strips. Place each unit against
construction joint forms with formed control joints perpendicular to the poured
strips. Pour slabs-on-grade against a moist subgrade. Wet the subgrade the day
before placing concrete. Moisten subgrade just ahead of concrete as it is placed.
Do not place concrete in standing water. Provide new, clean cut, sharp-edged
wood headers at construction joints of suspended slabs. Deposit concrete
evenly, consolidated with mechanical vibrators, particularly at side forms, and
screed to indicated elevations and contours. Maintain full indicated thickness of
slab over all parts of cambered support. Concrete shall be compacted with a
grid tamper to eliminate voids and pockets and to produce a uniformly dense
20-12
slab. Where ground slabs are left to receive deferred finishes, provide protection
against contamination from time of placing concrete until time of placing finish.
Remove contamination mechanically leaving a clean surface.
Joint location and detail shall be as indicated. Tooling is required at
control and pour joints.
Control joints
After concrete surface is screeded, cut concrete with a cutting bar, or
other approved tool, approximately 1/4" thick x 2" deep. Form straight clean
lines. After slot is formed in stiff concrete, insert 1/8" thick x 1-1/2" strip of
tempered hardboard or plastic joint form zip strip. Butt strips neatly to line and
flush with concrete surface. Finish slab flush with top of hardboard strips
without tooling.
2. Construction joints:
Form construction joints with 2" nominal dressed lumber, or approved
steel forms. Provide enough stakes to prevent sagging and misalignment under
construction loads. Leave forms in place as long as possible and remove without
chipping the edge of the slab. Protect the slab edge until the adjacent slab is
placed.
3. Expansion joints
Provide sponge neoprene joint filler where shown on the Drawings. Place
filler to provide space for sealant as indicated. Seal joints with specified sealant
per manufacturer's printed instructions. Thickness of filler material is indicated.
Contractor shall apply a medium broom finish just after final troweling to
all flat slabs not specified to receive another finish.
Where wood float finish is indicated, screed slabs to elevations indicated.
Compact with motor driven disk type compactor float and bull float to smooth,
even surface. Perform final finishing with wood hand floats to give finished
surface uniform, slightly roughened texture.
Where steel trowel finish is indicated, tamp fresh concrete with a grid
tamper enough to raise a thin bed of mortar to surface. Before finishing, remove
any excess water. Level and compact with motor drive disk type compactor
float. Immediately after floating, the surface shall be further leveled and
compacted with a motor driven rotary trowel with flat-pitched blades. Final
troweling shall be done with steel hand trowel after surfaces have become hard
enough to produce a hard, dense, smooth, burnished surface.
20-13
20-17 GROUTING AND DRYPACKING
Grout shall consist of one (1) part cement, two (2) parts sand and
sufficient water that the grout will just flow under its own weight. Water
reducing and workable agent may be added at Contractor's option.
Drypack shall consist of one (1) part cement, 2 parts sand, with just
enough water to bind the materials together.
Dampen surfaces before grouting and slush with neat cement. Force grout
into place and rod so as to fill all voids and provide uniform bearing under plates.
Provide smooth finish on exposed surfaces and damp cure for at least three (3)
days.
Non-shrink grout shall be used exclusively under structural steel base
plates in accordance with manufacturer's printed instructions.
When concrete overlay bonding is required, the surface of the existing
concrete is to be roughened by sandblasting to remove loose material, rust and
oils. Sufficient cement matrix should be removed to expose surface aggregates
and to form a roughened surface for bonding. Clean with a high pressure water
jet and allow to surface dry. Immediately apply an acrylic bonding agent such
as Burke Acrylic Bondcrete at the rate of 200 sq. ft. per gallon and follow with
placement of the concrete overlay after a minimum of one hour and after the
film is dry to the touch. Install bonding agent in strict accord with
manufacturer's instructions.
20-18 WEEP HOLES IN WALLS
Weep holes or drains in walls shall be provided as shown on the Plans and
with drain rock backing or as indicated. Placement of the drain rock behind the
weep hole shall be made in a manner satisfactory to the Engineer.
20-19 CONCRETE PLACED UNDER WATER
Unless specifically indicated on the Plans or called for by the Special
Provisions, no concrete may be poured underwater without approval of the
Engineer. When underwater placement of concrete is so approved, the
placement shall be by approved tremie or bottom dump bucket. The consistency
of the concrete shall be varied to suit this type of placement and must meet the
approval of the Engineer. Underwater pours shall be continuous until completed.
Pouring of concrete in running water will not be permitted.
20-14
20-20 QUALITY CONTROL
The Engineer will be responsible for the routine quality control testing of
concrete mixes. Contractor shall assist the Engineer in obtaining samples of fresh
concrete.
Slump Test: Slump test shall be performed at the job site by the Engineer
in accordance with ASTM Test Method C 143.
Compressive Strength Tests: Each day concrete is poured, the Engineer
shall mold four concrete test cylinders in accordance with ASTM C 31. Contractor
shall pay for the service of an independent testing company to cure and test the
concrete cylinders in accordance with ASTM C 39 and C 172. Cylinders shall be
tested at 7 days, 14 days, 21 days, and 28 days. Methods of sampling and
testing concrete mixtures shall include but not be limited to the following:
Composite Samples: ASTM C 172.
Specimen Preparation: ASTM C 31.
Compressive Strength: ASTM C 39.
Air content: ASTM C 173 or C 231.
Slump: ASTM C 143.
Unit Weight: ASTM C 138
Evaluation and acceptance of concrete and concrete structures shall be
in accordance with Chapters 17 and 18 of ACI 301.
Any retesting and inspection of concrete due to inadequacy, deficiency,
failure, or removal shall be done at Contractor’s expense.
20-21 MEASUREMENT OF QUANTITIES
The volume of concrete to be paid for shall be determined by computation
from the dimensions of the structures as shown on the Plans and as amended by
approved change order. No deduction will be made for volume of reinforcing
steel.
20-22 PAYMENT FOR CONCRETE IN STRUCTURES
The price bid per cubic yard for concrete in structures shall include full
compensation for all excavation and backfill, unless there is a separate payment
for that item, for furnishing and building all necessary forms, for furnishing and
20-15
placing all concrete, for furnishing and placing all reinforcing steel, for furnishing
and placing expansion joint material and rubber water stop if shown on the Plans,
for curing the concrete, for weep holes in walls, for finishing all concrete
surfaces, and for doing such other work as may be necessary to construct
concrete in structures as indicated on the Plans and in the special provisions.
Unless otherwise indicated in the Special Provisions payment for drop
inlets shall be at the unit price bid per each and shall include full compensation
for excavation, backfill, furnishing all material, labor, tools and equipment and
doing all work necessary for construction, complete in place.
21-1
Section 21
PLACING STEEL REINFORCEMENT
21-1 MATERIALS
Provide reinforcing steel as shown on the Plans. Conform to Section 10-23
of these Standard Specifications except as modified herein. All materials covered
by this Section shall be manufactured in the United States.
The publications referred to hereinafter form a part of this specification
to the extent referenced. The publications are referred to in the text by the
basic designation only. The latest edition of publications at the time of bid shall
govern.
American Concrete Institute (ACI) Standard
ACI 318 Building Code Requirements for Reinforced Concrete.
ACI SP-66 ACI Detailing Manual.
American Welding Society (AWS)
AWS D 12.1
Welding Reinforcing Steel, Metal Inserts and Connections
in Reinforced Concrete Construction.
Concrete Steel Reinforcing Institute (CRSI)
1 MSP Manual of Standard Practice
1 SPLBK Reinforcement Anchorages and Splices
1 PLACE Placing Reinforcing Bars
Use galvanized steel chairs and accessories or plastic coated units for work
exposed to view, weather, or moisture so that finished surfaces will not be
marred or stained; use precast concrete only (no metal), suitably sized for load
distribution, in slabs-on-grade. Use no supports of wood or other cellulose
material.
21-2 SUBMITTALS
Before starting concrete work, submit shop drawings in accordance with
Section 5. Comply with requirements of ACI 318, ACI SP-66, CRSI 1MSP, CRSI
21-2
1SPLBK, and CRSI 1DET. Show bar size, dimensions, bends, placing, and
construction joint details. Submit drawing showing locations of any construction
joints not shown on the plans. Maximum submittal drawing size shall be 22-
inches by 34-inches. Submit type, size, and location of all slab and bar supports.
Hooks, lap splices, bends and offsets shall be in accordance with the drawings.
Obtain approval before shop fabrication. Such approval is intended only as an
additional precaution against errors, and shall not be construed as relieving
Contractor of his responsibilities for the accuracy of the information.
Submit Certificate of Compliance stating that reinforcement complies
with specified requirements. Reinforcing steel shall be properly identified.
Contractor shall bear costs for test of steel by an approved laboratory if the
reinforcing steel is not properly identified.
21-3 CLEANING
Reinforcing steel, before being placed in the forms, shall be thoroughly
cleaned of loose mill and rust scale, mortar, oil, dirt, and of coatings of any
character which would reduce or destroy the bond. Clean surfaces to be welded
of loose scale and all foreign material. Clean welds each time electrode is
changed. Chip burned edges clean before welds are deposited.
21-4 BENDING
Bending and Forming: Fabricate indicated size bars into shapes and
lengths shown on approved shop drawings by methods not injurious to materials.
Do not heat reinforcement for bending. Bars with kinks or bends not in schedule
will be rejected
Reinforcing steel shall conform accurately to the dimensions shown on the
Plans. The term “standard hook” used herein shall conform to ACI SP-66.
Bends for all bars other than stirrups, tie hooks, and standard hooks shall
have diameters on the inside of the bar not less than allowed by the above
references.
21-5 PREPARATION FOR PLACING
Bundle reinforcement and tag with suitable identification to facilitate
sorting and placing, and transport and store at site so as not to damage material.
Prior to installation of reinforcing steel work, Contractor shall inspect
surfaces to receive work, and arrange for satisfactory correction of defects in
workmanship and material that could have adverse affect on reinforcing steel
work.
Contractor shall receive approval in writing from the Engineer of all
reinforcing work prior to ordering concrete for placement.
21-3
21-6 PLACING
Conform to CRSI 1 MSP, and CRSI 1 PLACE except as modified herein.
At each location during concrete placing, inspect reinforcement and
maintain bars in correct positions. Templates to maintain the correct position of
reinforcing may be required. Contractor shall install templates, if required by
the inspector, at no additional cost to the City.
Reinforcing bars shall be firmly and securely held in place at the
intersections by wiring with No. 14 or No. 16 wire and by using concrete or metal
chairs, spacers, metal hangers, supporting wires, and other approved devices of
sufficient strength to hold the reinforcement in its proper place as the concrete
is poured. These supporting devices and the wire shall be furnished by Contractor
at his own expense.
The clear distance between parallel bars shall not be less than two and
one-half (2½) diameters of the bar with a minimum of two inches (2”).
Reinforcing bars shall have a minimum concrete cover of not less than twice the
bar diameter and in no case less than one and one-half inches (1½”). The
concrete cover of slab steel may be less than this minimum if so shown on the
Plans. Reinforcing bars shall have a minimum concrete cover of three inches
(3”) from edges that are placed against earth or that are to be submerged in
water.
Wire mesh used for reinforcement shall be rolled flat before placing
concrete unless shown differently on the Plans. Mesh reinforcement shall be
held firmly in place against vertical or transverse movement by means of devices
satisfactory to the Engineer.
21-7 WELDS AND SPLICING
Reinforcing bars for beams and for longitudinal slab spans shall not be
spliced, except as shown on the Plans. Splices of tensile reinforcement at
points of maximum stress shall be avoided. Where bars are spliced, they shall
be either lapped at least forty-five (45) bar diameters for No. 8 bars and
smaller and sixty (60) bar diameters for Nos. 9, 10, and 11 bars. No lapped
splices will be permitted at points where the section is not sufficient to provide
a minimum distance to two inches (2”) between the splice and the nearest
adjacent bar or the surface of the concrete.
In lapped splices, the bars shall be placed in contact and wired together
in such a manner as to maintain a clearance of not less than the minimum clear
distance to other bars and the minimum clear distance to the surface of the
concrete. Splices shall be staggered at least the length required for a lapped
21-4
splice and not more than one-third (1/3) of the bars may be spliced at one
location provided the specific clearances are maintained.
Where wire mesh reinforcement is spliced, it shall be lapped at least the
dimension of one (1) mesh.
21-8 PAYMENT FOR PLACING STEEL REINFORCEMENT
Payment for reinforcing steel shall not be made separately unless so
indicated by the Special Provisions, but shall be included in other bid items and
shall include full compensation for furnishing all steel, for cutting and bending,
for placing, for furnishing all wire, stirrups, hangers, and placement devices for
cleaning the reinforcement, and for insuring the proper placement of the steel
reinforcement in the finished structure.
22-1
Section 22
ASPHALTIC CONCRETE
22-1 ASPHALTIC CONCRETE TYPE AND MIX DESIGN
Asphaltic concrete shall be Type A (coarse) or as designated on the Plans
or specified in the Special Provisions, and shall conform to the provisions of
Section 39 of the State Specifications.
Asphaltic concrete shall be produced in conformance with the
requirements of a job-mix formula. The job-mix formula will take into
consideration the quality of the aggregate, the type of asphalt binder material,
the immersion compression retention index, the void relationships and other
criteria, and said job-mix formula shall be the responsibility of Contractor. The
amount of asphalt binder material, as a percentage of the total weight of the
mixture shall be determined by California Test 367.
Contractor shall be responsible for designing a job-mix formula by the
material supplier or through an approved testing laboratory, and shall submit it
to the Engineer for approval ten (10) working days prior to any mixing and/or
placing of asphaltic concrete.
During the production of either mineral aggregate or asphaltic concrete,
the Engineer or Contractor may request that adjustments be made in the job-
mix formula. Such request shall be in writing and substantiated through the
material supplier or an approved testing laboratory. Consideration will be given
promptly to such request.
22-2 MATERIALS FOR ASPHALTIC CONCRETE
Aggregate material shall conform to the requirements of Section 39 of the
State Specifications for three-quarter inch (¾") maximum aggregate for major
streets and one half inch (½”) for residential streets or as determined by the
Engineer. Where two lifts are placed, the Engineer may require that the base
course be ¾" maximum aggregate and the surface course be ½”maximum
aggregate. Consideration shall be given to percentage of heavy vehicles and bus
stop locations.
Paving asphalts shall meet the requirements of Section 10-18 of these
Specifications.
Unless otherwise indicated on the Plans or in the Special Provisions,
asphalt binder to be mixed with aggregate shall be steam-refined paving asphalt:
PG 64-10 or PG 64-16 for residential and collector streets and PG 70-10 for on/off
22-2
ramps, Intersections, arterials, and thoroughfares. Use ARHM-GG (Asphalt
Rubber hot Mix Gap Graded) with PG 64-16 for overlays, unless otherwise
indicated.
22-3 MIXING EQUIPMENT FOR ASPHALTIC CONCRETE
Mixing equipment shall conform to that specified in Section 39 of the State
Specifications.
22-4 GENERAL REQUIREMENTS FOR PLACING ASPHALT CONCRETE AND ASPHALT
CONCRETE OVERLAYS
Contractor shall notify the public seventy-two (72) hours prior to the start
of work by placing door hangers to all business and residences that may be affected
by the work as determined by the Engineer. Contractor may be required to contact
business owners in person to explain the work schedule as determined by the
engineer. No work shall be permitted until the public has been notified.
If Required by the Engineer, Contractor shall notify the following City
departments and agencies seven (7) days prior to performing the work: Public
Works Solid Waste Division (Street Cleaning Section), Public Works Parking
Division, Public Works Street Maintenance Section (Traffic Signs and Markings
Section and Traffic Signals and Lighting Section), Police Department
Communications Center, Fire Department Communications Center, and
Sacramento Metro Regional Transit (bus stops and light rail). If required,
Contractor shall contact the appropriate representative of each City department
or agency, and provide a work schedule in writing.
Contractor shall be responsible for trimming of trees necessary to perform
the work as determined by the Engineer. Contractor shall obtain a tree-trimming
permit from City Tree Services Division prior to trimming trees.
Contractor shall be responsible for removing all yard waste and debris
effecting the work at his expense. Yard waste shall not be relocated to planter
strips, pedestrian areas, or other areas not approved by the Engineer. Garbage
cans that are temporarily removed from the street shall be placed back in their
original position at the end of the workday.
Contractor shall be responsible for removing all vegetation from the
roadway surface and edge of pavement, and sweeping in advance of placing the
pavement operation (prior to tack coat) to the satisfaction of the Engineer.
Contractor shall clean, sweep, and maintain the cleanliness of the streets
to be paved to the satisfaction of the Engineer throughout the course of the
work. Materials spilled or dispersed as a result of the work on adjacent streets
22-3
shall also be cleaned at the expense of Contractor. The street shall be swept
with a mechanical type pickup machine and shall be left thoroughly clean and
clear of any pavement grindings at the end of each working day. The machine
shall spray adequate amounts of water to control dust.
Contractor shall remove and dispose of existing pavement markers prior
to placing asphalt. All thermoplastic limit lines, crosswalks, and legends applied
to the road surface shall be scarified prior to placing the overlay. Excess crack
seal shall be removed as directed by the Engineer.
Contractor shall place temporary pavement delineation necessary for the
safety of vehicular and pedestrian traffic. Temporary pavement delineation
layout shall be approved by the Engineer.
All manholes and utility covers concealed with asphalt concrete shall be
carefully referenced out (“cross-tied”) prior to the placement of asphalt by
Contractor. All exposed survey monuments shall be referenced out prior to the
overlay, covered by an appropriate method approved by the Engineer, and
uncovered after the overlay without disturbing or damaging the survey
monument. All relevant iron (manholes, water valves, etc.) shall be lowered prior
to pavement planing as directed by the Engineer. Contractor shall submit “cross
ties” to the Engineer prior to the lowering of iron.
Contractor shall coordinate the removal of on-street parking with the
Engineer Seventy-two (72) hours prior to the start of work in accordance with
Section 6-18 of these specifications.
22-5 PAVEMENT KEYCUTTING, CONFORMS, AND PLANING
Where specified by the Engineer, pavement planing shall be done to
profile the street to a planer surface. The general depth of planing shall be
equal to the depth of the overlay unless otherwise approved by the Engineer.
Where specified by the Engineer, pavement keycutting shall be done to
provide a key wedge against existing gutter lips. Asphalt concrete removal shall
be to a minimum depth of one and a half inch (1½") adjacent to the lip and shall
be tapered to the existing pavement grade over a distance of eight feet (8')
minimum, from the gutter lip. At cross streets, where the condition of the side
street is very good, pavement keycutting shall continue in a straight line from
curb line to curb line parallel to the direction of work as directed by the
Engineer.
At the beginning and ending limits of pavement keycutting, a planed
pavement conform shall be constructed to the drawings shown in Section 38 of
these Standard Specifications or as directed by the Engineer. At cross streets,
22-4
where the condition of the side street is poor, planed pavement conforms shall
be done between the lip of the main street to the curb return of the side streets.
When the beginning or ending limit of work is a crossing street, a fifty feet (50')
planed conform extending to the round corner of the crossing street shall be
constructed except that an eighteen foot (18') planed pavement conform shall
be constructed on residential streets. The conform shall span the full width of
the street for a distance of fifty feet (50') back from the limit line or feature
resulting in the discontinuity in the work. At bridge decks, the conform shall
span the full width of the street for a distance of fifty feet (50'). The depth of
cut shall be equal to the depth of overlay at the limit of work and shall be
progressively decreased to zero (0") over the conform length.
Where specified by the Engineer, pavement planing shall be done to retain
the existing street elevation. The depth of planing below the gutter lip shall be
equal to the specified thickness of asphalt concrete. The depth of planing at the
centerline shall be equal to the specified thickness of asphalt concrete to be
placed on the street, and shall increase from the lip of gutter to the street
centerline linearly should the specified depths differ.
Contractor shall exercise care to avoid damaging the gutter lips during the
grinding operations. Damaged gutter lips which have spalls in excess of one inch
(1") deep by five inches (5") long shall be repaired at Contractor's expense.
Grinding operations shall be completed to the satisfaction of the Engineer
prior to beginning the paving operation.
Contractor shall remove existing asphalt concrete from the top of the
gutter pan and from the face of gutter lip as directed by the Engineer.
The grindings shall become the property of Contractor and disposed of off-
site.
At the end of the workday, there shall not be any elevation difference
between planed pavement and unplaned pavement in the traveled vehicle lanes
and all curb ramps. Any differences that parallel the centerline of the street in
a longitudinal direction shall be sloped by either a temporary asphalt plant mix
cut back or additional planing, to produce a bevel within the planed pavement.
The slope of either the cutback or the bevel shall be not greater than one-inch
(1") vertical in twelve inches (12") horizontal. Other than for curb ramps,
elevation differences between planed pavement and lips of gutters are not
required to be sloped.
Elevation differences perpendicular to the centerline of the street, in a
transverse direction, or elevation differences between the planed street and
22-5
cross-streets, shall be sloped as directed by the Engineer with cutback and shall
not exceed one inch (1") vertical in twelve inches (12") horizontal.
If Contractor fails to slope elevation differences as required by these
Special Provisions, Contractor shall pay administrative penalties of $500 per each
infraction per each calendar day elevation differences are not sloped.
Not more than three (3) calendar days shall elapse between the time
pavement planing and/or pavement keycutting begins on any particular section
of roadway and the time that the asphalt concrete surfacing is placed unless
approved by the Engineer.
22-6 PLACING
Placing of asphaltic concrete shall conform to the requirements of Section
39 of the State Specifications. The maximum paving lift shall be three inches (3")
thick.
Contractor shall fill and level all surface irregularities and ruts to ensure
compliance with specified tolerances.
Contractor shall use a thirty foot (30') leveling ski on the free floating edge
unless otherwise approved.
Before placing asphaltic concrete surface course on an asphaltic concrete
base course, a tack coat shall be applied unless otherwise approved.
The material shall be brought to the site of the work in suitable vehicles
so equipped that they will operate properly with the spreading equipment being
used. The Engineer shall have the right to remove any vehicle from service which
is not operating satisfactorily in the spreading of the material. Tarpaulins shall
be provided for all trucks and shall be used whenever the Engineer may direct.
Asphaltic concrete shall not be placed on a wet base or subgrade, and the
ambient air temperature shall be 50°F. and rising. The temperature of the mix
shall not exceed 320°F. nor shall it be laid at a temperature below 250°F unless
authorized by the Engineer.
When base course and surface course are used, the extent to which the
base course may be laid ahead of the surface course, and the requirement for a
tack coat, shall be determined by the Engineer.
22-6
22-7 TACK COAT
Tack coats shall be in conformance with the requirements of Section 39
“Paint Binder (tack coat)” of the State Specifications. A tack coat shall be applied
to all planed surfaces, paved surfaces to be resurfaced, vertical surfaces of existing
pavements, curbs, gutters, and construction joints, and other surfaces as directed
by the Engineer.
Tack coats shall be SS-1 asphalt emulsion unless otherwise approved. The
proportion of SS-1 and water shall be 80/20, or as determined by the engineer, and
shall be applied to the surface at an application rate from .02 to 0.10 gallons per
square yard. Typical application rates vary from .05 gallons per square yard for
smooth finished surfaces to .10 gallons per square yard for planed pavement
surfaces.
Prior to applying tack coat, the street surface shall be swept clean by
brooming or washed clean to the satisfaction of the Engineer. The length of the
tack coat placed in advance of the paving operation shall be determined by the
Engineer to minimized degradation of the tack coat by vehicular traffic. The street
surface shall also be free of moisture and dry to the satisfaction of the Engineer.
Under cold weather conditions, the Engineer may approve the use and
application rate of PG 64-10 or PG 64-16 paving asphalt as a tack coat.
22-8 SPREADING AND COMPACTING
Spreading and compacting requirements shall be in conformance with
Section 39 of the State Specifications except as noted herein. Compaction shall
be subject to density testing as defined in Section 22-9 and 22-10 of these
specifications in accordance with California Test Methods 304 and 308.
Contractor shall furnish a minimum of two (2) ten (10) ton steel wheel
rollers and one (1) twelve (12) ton pneumatic tired roller unless otherwise
approved by the Engineer. Vibratory rollers may be substituted when approved
by the Engineer.
The initial or breakdown rolling of surface course shall be followed by
additional rolling consisting of three (3) complete coverage with a pneumatic-tire
roller, while the temperature of the mixture is at or above 150° F. The final rolling
of surface course shall be performed with a ten (10) ton, two (2) axle tandem
roller.
The rolling of the asphaltic concrete material shall commence
immediately after its placement. Rolling shall continue until all ruts and surface
imperfections are eliminated and the proper degree of compaction is achieved.
22-7
Finish rolling shall be accomplished with a steel wheel tandem roller. A vibrating
roller may be used as the finish roller provided that it meets the requirements
for a finish roller as herein specified and is operated with the vibratory unit
turned off. Rolling shall commence at the lower edge and shall progress toward
the highest portion, except that when compacting layers which exceed 0.25-foot
in compacted thickness rolling shall commence at the center and shall progress
outwards.
At the commencement of the asphaltic concrete paving operations,
Contractor shall cooperate with City forces in establishing and agreeing upon a
rolling pattern that will insure the obtainment of the maximum possible density
in the compacted asphaltic concrete surface. Once the rolling pattern is
established, Contractor shall follow this pattern unless otherwise directed by the
Engineer.
The City will perform compaction testing at no cost to Contractor.
Contractor shall cooperate fully with City forces to take such tests, and shall
make all provisions to allow the Engineer to sample the asphaltic concrete
mixture from the completed surface immediately following placement by the
lay-down machine.
When a straightedge twelve feet (12') long is laid on the finished surface
and parallel with the center line, the surface shall not vary more than 0.01-foot
from the lower edge of the straightedge. The transverse slope of the finished
surface shall be uniform to a degree such that no depressions greater than 0.02-
foot are present when tested with a straightedge twelve feet (12') long laid in a
direction transverse to the center line and extending from edge to edge of a
twelve foot (12') traffic lane. Contractor shall conform to the tolerance
requirements of this specification unless otherwise approved by the Engineer in
writing prior to the start of work. Contractor shall request information regarding
tolerances for streets having a parabolic section prior to the start of work.
Contractor shall place asphalt such that its finished surface is ¼ to ½ inches
above the gutter lip.
Pavement surface shall be deemed unacceptable should the surface hold
water, the pavement ravel, an uneven gradation of mix be visible, or cracking
occur during rolling. Pavement shall be removed by surface planing (a minimum
depth of one and one-half inches (1½") when using one-half inch (½") mix, and
two inches (2") inches when using three-quarter inch mix), and repaved to the
satisfaction of the Engineer. Areas to be removed and replaced will be
determined by the Engineer. Should a significant amount of surface be deemed
unacceptable, the entire travel lane shall be resurfaced. A series of spot patches
will not be accepted. The mix design used during resurfacing shall be the same
as the adjacent pavement.
22-8
Pursuant to Section 5-14 of these Specifications, the Engineer will have
the right and authority, but shall not be obligated, to retain imperfect work
instead of requiring the imperfect work to be removed and reconstructed. Patch
paving of imperfect work will not be allowed, and the amount of the deduction
shall be based on full travel lane widths from beginning to end of the work limits
or two nearest intersections as determined by the Engineer.
22-9 PAVEMENT DENSITY TESTING
Pavement density will be determined by comparing the average density
of cores taken from the compacted pavement to the maximum theoretical
density as determined by ASTM D 2041. As required by the Engineer, the
pavement will be inspected on a lot basis. A lot will consist of either five hundred
(500) tons of asphalt for a surfacing project or four hundred (400) lineal feet of
pavement for a trenching project. One sample shall be taken from each lot on a
random basis. One laboratory-compacted specimen shall be prepared from each
lot.
Cores for determining the density of compacted pavement will be taken
on a lot basis with a minimum of three cores per lot. The density of each core
shall be determined per ASTM D 2726-89. The cores shall be four inches (4”) in
diameter.
Contractor shall plug core holes taken by the material tester with asphalt
compacted greater than ninety percent (90%) of relative compaction if cores are
taken the same day as Contractor’s paving operations. The core holes shall be
plugged prior to the end of the workday. If required to facilitate the taking of
cores, Contractor shall leave lane closures in place for a reasonable period of
time (approximately thirty minutes after pavement has cooled enough to drive
on).
22-10 PAY FACTORS
For all asphalt pavement subject to acceptance testing, the lot will be
paid for using the following pay factors:
22-9
In Place relative Compaction
Payment Factor
97.1% or higher (over-
asphalted mix)
90%
92% 97%
100%
89%-91.9% (marginal air voids)
85%
88.9%or less (unacceptable air
voids)
Not acceptable (60% if otherwise
approved)
The amount paid shall be at the unit price bid times the pay factor. For
lots with average densities of 91.9% or less, the Engineer reserves the right to
deem the lot as not acceptable and require the work to be removed and
reconstructed. Unless otherwise approved by the Engineer, lots with average
densities of less than 89% relative compaction shall be removed and
reconstructed.
22-11 PAVEMENT REINFORCING FABRIC
Pavement reinforcing fabric shall be non-woven polyester, polyproplyene,
or polypropylene/nylon materials conforming to the requirements of the below
indicated ASTMs:
Weight, Oz./sq.yd.
ASTM D 5261 3.0 to 8.0
Grab Tensile Strength
(1-inch grip), Pounds
ASTM D 4632 90 min.
Elongation at Break, Percent,
ASTM D 4632 50 min
Fabric Thickness Mils.,
ASTM D 5199 12 to 100.
The fabric shall retain the physical properties listed herein after being in
contact with asphalt concrete at temperatures of up to 325° F. for five (5)
minutes (±15 seconds).
Pavement reinforcing fabric shall be accompanied by a Certificate of
Compliance signed by the manufacturer stating that the fabric complies with
these Specifications. The fabric shall be protected from exposure to ultraviolet
rays and kept dry until placed. Before spreading asphalt binder, large cracks,
22-10
spalls and chuckholes shall be repaired as directed by the Engineer and such
repair work will be paid for as extra work-force account as provided in Section
4-6 of these Specifications.
Immediately prior to placing the fabric, an asphalt binder shall be applied
to the street surface. Asphalt binder for pavement reinforcing fabric shall
conform to the provisions of Section 10-18 of these specifications and shall be
the same grade of the mix design.
Asphalt binder for pavement reinforcing fabric shall be applied at an
approximate rate of 0.25 gallons per square yard of surface covered. The width
of the asphalt binder spread shall be the width of the fabric mat plus three inches
(3”) on each side. Asphalt binder shall be applied at a temperature of not less
than 290° F.
The fabric shall be stretched, aligned and placed with no wrinkles that
lap. The test for lapping shall be made by gathering together the fabric in a
wrinkle. If the height of the doubled portion of extra fabric is one-half inch (½”)
or more, the fabric shall be cut to remove the wrinkle then lapped in the
direction of paving. Laps in excess of two inches (2") shall be removed.
If manual lay down methods are used, the fabric shall be unrolled,
stretched, aligned and placed in increments of approximately thirty feet (30’).
Adjacent borders of the fabric shall be lapped two to four inches (2-4”).
The preceding roll shall lap two to four inches (2-4”) over the following roll in
the direction of paving at ends of rolls or at any break.
Seating of the fabric with rolling equipment after placing will be
permitted. Turning of the paving machine and other vehicles shall be gradual
and kept to a minimum to avoid damage.
A small quantity of asphalt concrete may be spread over the fabric
immediately in advance of placing asphalt concrete surfacing in order to prevent
fabric from being picked up by construction equipment.
Public traffic shall not be allowed on the bare reinforcing fabric, except
that public cross traffic shall be allowed to cross the fabric, under traffic control,
after Contractor has placed a small quantity of asphalt concrete over the fabric.
Care shall be taken to avoid tracking binder material onto the pavement
reinforcing fabric or distorting the fabric during seating of the fabric with rolling
equipment.
22-11
22-12 PAYMENT FOR ASPHALTIC CONCRETE
Payment for asphaltic concrete pavement shall be at a price per ton of
delivered and place material or at a price per square foot for finished pavement.
The method used on any work will be shown by the list of quantities on the
Proposal and by the type of unit price requested in the Proposal.
Payment for asphaltic concrete pavement by either of the above two
methods, as may be specified in the Proposal for that particular work, shall
include full compensation for furnishing and placing the material without
additional compensation. Tack coat, where required, shall also be furnished
without additional compensation and as part of the bid per ton or per square
foot of asphaltic concrete pavement.
Payment for pavement key cutting shall be at the unit price per lineal foot
of street surface planed and shall include full compensation for furnishing all
labor, materials tools, equipment and incidentals, and for doing all work involved
in placing pavement reinforcing fabric, complete in place, as specified herein.
Payment for pavement conforms and pavement planing shall be at the unit
price per square yard and shall include full compensation for furnishing all labor,
materials, tools, equipment and incidentals, and for doing all work involved in
placing pavement reinforcing fabric, complete in place, as specified herein.
Payment for pavement reinforcing fabric shall be at the unit price bid per
square yard of street surface actually covered as determined by the Engineer,
and shall include full compensation for furnishing all labor, materials, tools,
equipment and incidentals, and for doing all work involved in placing pavement
reinforcing fabric, complete in place, as specified herein.
Payment for full compensation for advance spreading of asphalt concrete
over the fabric and for furnishing and placing the asphalt binder in accordance
with the requirements of this Section shall be considered as included in the
contract prices paid per ton for asphalt concrete surfacing and no additional
compensation will be allowed therefore.
23-1
Section 23
BITUMINOUS SEALS
23-1 BITUMINOUS SEAL TYPES AND MIX DESIGN
Bituminous seals shall conform to the requirements of Section 37 of the
State Specifications except as noted herein. Bituminous seal types shall be
produced in conformance with the requirements of a job-mix formula. The job-mix
formula will take into consideration the quality of the asphalt emulsion, aggregate,
mineral filler, and specified additives.
Contractor shall be responsible for designing a job-mix formula by the
material supplier or through a testing laboratory capable of performing the
applicable International Slurry Seal Association (ISSA) tests, and shall submit it to
the Engineer for approval ten (10) working days prior to the start of work.
During the course of the work, the Engineer or Contractor may request
that adjustments be made in the job-mix formula. Such request shall be in
writing and substantiated through the material supplier or an approved testing
laboratory. Consideration will be given promptly to such request. Bituminous seal
types and typical uses are as follows:
1. Sand Seal
Sand seals shall be used to seal pavement cuts such as recent trench
excavations and after the raising of utility covers.
2. Slurry Seal (Type 2)
Slurry Seals, Type 2, shall be used to extend the life of existing
residential streets in good condition.
3. Slurry Seal (Type 3)
Slurry Seal, Type 3, shall be used to extend the life of existing
major streets in good condition.
4. Seal Coat (Chip Seal)
Seal Coat, Chip Seal, shall not be used, except as the base course
of a cape seal.
23-2
5. Cape Seal
Cape Seal shall be used to extend the life of existing streets in fair
condition.
23-2 SAND SEALS
1. Asphalt Emulsion
The emulsified asphalt shall be SS-1 unless otherwise approved. The
proportion of SS-1 and added water shall be 80/20, or as determined by the
engineer. The resulting mixture shall contain one part of asphalt emulsion
(which contains up to 43 percent added water) and not more than one part of
total added water. Under cold weather conditions, the Engineer may approve the
use of viscosity grade AR-4000 paving asphalt as a base material for sand seals.
2. Sand
Sand shall be free from dirt and other deleterious substance.
23-3 SLURRY SEALS
1. Asphalt Emulsion
The emulsified asphalt shall be designated as grade PMCQS-1h. The
polymer within the asphalt emulsion shall be, at the option of Contractor, either
Neoprene, SBR, EVA or SBS. Solid polymers such as EVA or SBS shall be
adequately blended into the asphalt prior to emulsification. If a liquid latex such
as Neoprene, SBR or similar is used, the latex shall be “co-milled” into the
emulsion through the water phase during manufacturing. Each load of polymer
asphaltic emulsion shall have a certificate from the asphalt emulsion
manufacturer guaranteeing that either asphalt blending or “co-milling”
processes were used. The certificate shall also state the percentage of the solid
rubber polymer added by weight of the asphalt as well as the composition of the
polymer. The addition of latex to the emulsion after emulsion manufacturing is
prohibited. The polymer modified asphalt emulsion shall conform to the
following specifications:
23-3
TEST TEST METHOD REQUIREMENT
Tests on emulsion:
Min. Max.
Viscosity SSF, @ 77◦ F, seconds AASHTO T 59 15 90
Settlement, 5 days, % AASHTO T 59 -- 5
Storage Stability Test, 1 day, % AASHTO T 59 -- 1.0
Distillation: Oil distillate by AASHTO T 59 -- 3
volume of emulsion, %
(Residue by Low-Temperature)
Vacuum Distillation, % ASTM D 244. 133-137 57 --
Tests on residue using CTM 331
Penetration, 77°F, 100 grams for AASHTO T 59 40 65
5 seconds, dmm
Solubility in Trichloroethylene, % ASTM D 2042 97.5 --
Ductility, 77°F, 5cm/min, cm AASHTO T 51 60 --
(RTFO Aged Residue)
Ring & Ball Softening Point, ◦ F AASHTO T 53 123 --
Polymer Content, % Solid polymer CTM 401 3.0 --
content based on weight of asphalt.
Torsional Recovery, % CTM 332 18 --
2. Mineral Aggregate
Slurry seal aggregate for all roads shall conform to ISSA Type II aggregate
and shall be manufactured crushed stone such as granite, slag, limestone, chat,
or other high quality aggregate, or combination thereof. To assure the material
is totally crushed, 100% of the parent aggregate shall be larger than the largest
stone in the gradation to be used.
When tested in accordance to AASHTO T27 (ASTM C 136) and AASHTO T11
(ASTM C 117), the aggregate gradation (including the mineral filler) shall be
within following bands.
Type II Slurry Seal (residential streets)
Sieve Sizes Passing Percentage Stockpile Tolerance
9.5 mm (3/8”) 100 +/- 5%
4.75 mm (#4) 94-100 +/- 5%
2.36 mm (#8) 65-90 +/- 5%
1.18 mm (#16) 40-70 +/- 5%
600 um (#30) 25-50 +/- 5%
330 um (#50) 18-30 +/- 4%
150 um (#100) 10-21 +/- 3%
75 um (#200) 5-15 +/- 2%
23-4
Type III Slurry Seal (major streets)
Sieve Sizes Passing Percentage Stockpile Tolerance
9.5 mm (3/8”) 100 +/- 5%
4.75 mm (#4) 70-90 +/- 5%
2.36 mm (#8) 48-70 +/- 5%
1.18 mm (#16) 28-50 +/- 5%
600 um (#30) 19-34 +/- 5%
330 um (#50) 12-25 +/- 4%
150 um (#100) 7-18 +/- 3%
75 um (#200) 5-15 +/- 2%
After the target gradation has been submitted and identified in the mix
design, the percent passing each sieve shall not vary by more than the stockpile
tolerance and still remain within the gradation band during the application of
slurry seal. The mineral aggregate shall also conform to the following:
Test Test Method Requirements
Sand Equivalent ASTM D 2419 60 Minimum
Loss in L.A. Rattler CTM 211 10% Maximum
(100 Revolutions)
Loss in L.A. Rattler CTM 211 35% Maximum
(500 Revolutions)
Durability Index ASTM D 3744 60 Minimum
Mineral Filler - Mineral Filler shall be Portland Cement, hydrated lime,
limestone dust, fly ash or other approved filler meeting the requirements of
ASTM D 242 shall be used as required by the mix design. The mineral filler shall
be considered as part of the aggregate in calculations regarding slurry seal
asphalt content.
3. Water
The water added to the slurry seal shall be potable and free of harmful
salts and contaminates.
4. Additives
Additives may be used to accelerate or retard the mixing and setting
characteristics of the slurry seal, or to improve the resulting finished surface.
The use of additives in the slurry mix (or individual materials) shall be made
initially in quantities predetermined by the mix design with field adjustments if
required. If the use of additive during application requires a greater than + or -
1.0% deviation from the recommendations of the mix design, a new mix design
will be performed to verify system performance at higher or lower additive
levels.
23-5
Water, and additives, if used, shall be added to ensure proper workability
and:
a. Permit the unrestricted flow of traffic on the slurry seal no more
than one (1) hour after placement without the occurrence of
bleeding, raveling, separation, or other distress.
b. Prevent the development of bleeding, raveling, separation, or other
distress within fifteen (15) days after placing the slurry seal.
5. Compatibility
The Engineer may require the compatibility of the aggregate, emulsion,
mineral filler, and other additives shall to be verified by the mix design prior tot
the start of work. The Engineer may require the following tests to determine
compatibility:
TEST DESCRIPTION SPECIFICATION
ISSA TB-113 Mix Time Controllable to
180 sec minimum
ISSA TB-139 Wet Cohesion
30 minutes min 12kg-cm minimum
60 minutes min 20kg-cm minimum
ISSA TB-109 Excess Asphalt 50g/ft
2
maximum
by LWT Sand Adhesion (538g/m
2
maximum)
ISSA TB-114 Wet Stripping Pass (90% minimum)
ISSA TB-100 Wet Track Abrasion Loss 50g/ft
2
maximum
One hour soak (807g/m
2
maximum)
The Wet Track Abrasion test is used to determine the minimum asphalt
content.
Contractor may be required to have the laboratory report the quantitative
effects of moisture content on the unit weight of the aggregate (bulking effect).
The report must clearly show the proportions of aggregate, mineral filler (min.
and max.), water (min. and max.), additive(s) (usage), and asphalt emulsion
based on the dry weight of the aggregate (percentages).
6. Application
Type II slurry seal shall be placed at a rate of approximately twelve (12)
to fifteen (15) pounds per square yard. The exact rate will be as determined by
specific weight of aggregate, the surface demand of the pavement, and the size
of the largest particle size of the aggregate. Slurry seal shall not be placed when
the existing pavement or air temperature is below 55 degrees Fahrenheit (15
23-6
degrees C) and falling, or during unsuitable weather, but may be applied when
both pavement and air temperature are above 45 degrees Fahrenheit (7 degrees
C) and rising.
Unless the Engineer makes other arrangements, all intersections are to be
slurry sealed where there are two or more blocks in line. Contractor shall seal
all alley returns adjacent to streets that are to be sealed back to the property
line. Where two streets that are to be sealed intersect, Contractor shall seal
the entire pavement in the intersection, including the round corner area. Where
light rail is encountered, Contractor shall seal up to the concrete pad. Areas to
be slurry sealed that are inaccessible to the spreader box may be spread by other
approved means.
Contractor shall remove all excess material, which is placed outside
asphalt pavement areas. Hand tools shall be available in order to remove
spillage.
Where the completed slurry is not uniform in color, the street shall be
treated to eliminate the color variation at Contractor's expense. The method of
treatment will be subject to approval by the Engineer. Contractor shall repair
and reseal all areas of the streets, which have not been sealed properly or
completely at no additional cost to the City.
Contractor shall be responsible for sweeping the streets and sidewalks
which excessive raveling may occur after placing of the slurry seal, at no
additional cost to the City, as directed by the Engineer. When requested by the
Engineer, Contractor will send to the Engineer a daily report containing the
following information:
a. Tons of dry aggregate consumed that day.
b. Tons of asphalt emulsion consumed that day; and
c. Surface area covered that day.
6. Machine Calibration And Verification
Mixer-spreader trucks to be used in performance of the work shall be
calibrated in the presence of the Engineer prior to construction. Contractor shall
document the way in which the mechanical proportioning devices are calibrated
and correlated to the metered delivery of each material at various settings. No
mixer-spreader truck will be allowed to work on the project until the calibration
has been completed and accepted by the Engineer within at least one (1) working
day prior to start of work.
23-7
7. Spreading Equipment
The slurry mixture shall be uniformly spread by means of a controlled
spreader box conforming to the following requirements:
All spreader boxes over 7-1/2 feet in length shall have baffles.
Spreader box, rubber strike off, and drag mops shall be maintained in such
manner as to prevent chatter (washboarding) in the finished mat. If
washboarding occurs, that area shall be corrected to eliminate the washboard.
The rear flexible strike-off blade shall make close contact with the
pavement and shall be capable of being adjusted to the various crown slopes so
as to apply a uniform seal coat. Blades shall be changed as frequently as
necessary to prevent longitudinal scouring.
The maximum speed of the application equipment shall not be greater
than 180 feet per minute. At least two (2) operational spreader trucks shall be
available at the job site during the spreading operation except when continuous
placement type mixer-spreader trucks are used.
23-4 CHIP SEALS
1. Asphalt Emulsion
The asphalt emulsion use for chip seal shall be a cationic polymer modified
asphalt emulsion grade PMCRS-2h. The polymer in the emulsion shall be, at the
option of Contractor, either Neoprene, SBR, EVA or SBS. Solid polymers such as
EVA or SBS shall be adequately blended into the asphalt prior to emulsification. If
a liquid latex such as Neoprene, SBR or similar is used, the latex shall be “co-
milled” into the emulsion through the water phase during manufacturing.
Each load of polymer asphaltic emulsion shall have a certificate from the
asphalt emulsion manufacturer guaranteeing that either asphalt blending or “co-
milling” processes were used. The certificate shall also state the percentage of
the solid rubber polymer added to the asphaltic emulsion by weight of the asphalt
as well as the composition of the polymer. The addition of latex to the emulsion
after emulsion manufacturing is prohibited.
Cationic type asphalt emulsion Grade PMCRS-2h shall conform to the
following requirement when tested in accordance with the specified test methods:
23-8
TEST TEST METHOD REQUIREMENT
Tests on emulsion: Min. Max.
Viscosity SSF, @ 122◦ F, seconds AASHTO T 59 100 250
Settlement, 5 days, % AASHTO T 59 -- 5
Sieve Test, % AASHTO T 59 -- 1.0
Demulsibility, 35 ml. 0.8% sodium dioctyl AASHTO T 59 60 95
sulfosuccinate, %
Particle Charge AASHTO T 59 Positive
Distillation: Oil distillate by AASHTO T 59 -- 3
volume of emulsion, %
Residue by Evaporation, % CTM 331 65 --
Tests on residue from Evaporation using CTM 331:
Penetration, 77°F, 100g, 5 seconds, dmm AASHTO T 59 40 65
Solubility in Trichloroethylene, % ASTM D 2042 97.5 --
Ductility, 77°F, 5cm/min, cm AASHTO T 51 60 --
(RTFO Aged Residue)
Ring & Ball Softening Point, ◦F AASHTO T 53 123 --
Polymer Content *, % CTM 401 3.0 --
*Solid polymer content based on weight of asphalt.
Torsional Recovery, % CTM 332 18 --
2. Medium Fine Screenings
Screening shall consist of broken stone, crushed gravel, or both. At least
90 percent of the screenings, by weight, shall consist of crushed particles as
determined by CTM 205. Screenings shall be clean and free from dirt and other
deleterious substances.
The percentage composition of the screenings, by weight, shall conform
to the following grading:
Sieve Sizes Percent Passing
3/8” 100
No. 4 30 - 60
No. 8 0 - 15
No. 16 0 - 5
No. 30 0 - 3
No. 200 0 2
Screenings shall conform to the following quality requirements:
23-9
CTM Requirements
Los Angeles Rattler Loss
at 100 Revolutions 211 10% Maximum
Los Angeles Rattler Loss
at 500 Revolutions 211 40% Maximum
Film Stripping, % 302 10% Maximum
Cleanness Value 227 85 Minimum
3. Application
The chip seal asphalt emulsion application rate shall range between 0.20
and 0.35 gallons per square yard. Application of fog seal will not be required.
Each distributor truck shall be equipped, at all times, with its proper
measuring stick and calibration card. On-site calibration of distributor trucks,
for determining actual spread rate of asphalt emulsion, shall be performed when
directed by the Engineer. The Engineer may sample the asphalt emulsion at any
time during application. Samples of asphalt emulsion shall be taken from the
spray bar of a distributor truck at mid-load.
When requested by the Engineer, Contractor will send to the Engineer a
daily report containing the following information:
a. Tons of dry aggregate consumed that day.
b. Tons of asphalt emulsion consumed that day; and
c. Surface area covered that day.
4 Finishing
The Engineer shall have the final decision when traffic shall be permitted
to resume. The surface of the chip seal coat shall be swept or broomed no sooner
than 4 hours after the placement of the chip seal to maintain the surface free of
loose screenings and removal of excess screenings from all paved areas including
gutters, sidewalks and driveways until the slurry seal has been applied as
coverage. Contractor shall be responsible for any damages to the vehicles,
pedestrians and residents due to loose screenings. Contractor is responsible for
additional sweeping if requested by the Engineer.
5. Maintaining Traffic
Contractor shall place temporary C6 “LOOSE GRAVEL” with 15-MPH speed
limit signs installed at the entrance and at 150 feet intervals on both sides of the
streets.
23-10
23-5 CAPE SEALS
1 Materials
The materials for cape seal consist of those for a slurry seal placed over a
chip seal.
2. Application
The slurry seal coat shall be applied no sooner than seven (7) calendar
days and no later than fourteen (14) calendar days after the chip seal coat is
applied.
Cape seal shall be placed at a rate of approximately eighteen (18) to thirty
(30) pounds per square yards. The exact rate will be as determined by specific
weight of aggregate, the surface demand of the pavement, and the size of the
largest particle size of the aggregate.
Residual Asphalt 7.5% - 13.5% (approx. 12.0 - 22.0% emulsion)
based on dry weight of aggregate
Mineral Filler 0.0% - 2.0% Based on dry weight of aggregate.
Additives As needed to control mixing and setting times
Water As needed to achieve proper mix consistency.
Residual Asphalt 6.5% - 12.5% (approx. 10.5% - 19.5% emulsion)
Based on dry weight of aggregate
23-6 GENERAL REQUIREMENTS
Contractor shall coordinate the removal of on-street parking with the
Engineer Seventy-two (72) hours prior to the start of work in accordance with
Section 6-18 of these specifications.
Immediately prior to apply slurry or chip seal, the pavement surface shall
be cleaned by sweeping all streets with a mechanical power broom prior to
sealing or other means necessary to remove all loose particles from the
pavement. All dirt, silt, vegetation and other objectionable material that may
prevent adhesion of the seal coat to the existing pavement will be removed. The
Engineer may require particularly dirty streets to be flushed with water (City
permit is required if City Fire Hydrants are being used). The Engineer must
approve all flushing operations. Contractor shall be responsible for cleaning
sidewalks and driveways soiled by flushing operations.
23-11
Contractor shall remove thermoplastic stripes/markings, preformed
traffic stripes or markings and raised pavement markers prior to seal coat
operation. Contractor shall place temporary pavement delineation necessary for
the safe movement of vehicular and pedestrian traffic. The layout of temporary
pavement delineation shall be approved by the Engineer.
Utility covers, maintenance holes, and other permanent facilities shall be
protected from coverage by the chip seal, and referenced for prompt location
and cleaning following slurry seal operations. Contractor shall be responsible for
covering, locating, removing, cleaning and protecting the above items during and
following the cape seal operations. The methods of protection, referencing,
locating and cleaning shall be submitted by Contractor and shall be subject to
approval by the Engineer prior to any resurfacing. All protective coverings shall
be removed from maintenance hole covers, water valve boxes, and other utility
covers each day before opening the street to traffic.
Contractor at his expense shall be responsible for removing all yard waste
and debris placed in the street between the time of City pickup and the
completion of the work. Yard waste shall not be relocated to planter strips,
pedestrian areas, or other areas not approved by the Engineer. Garbage cans
that are temporarily removed from the street shall be placed back in their
original position at the end of the workday.
Contractor shall submit to the Engineer for review and approval a plan
showing traffic control measures for vehicles and pedestrians affected by the
construction work. Contractor will not be allowed to begin work until the
Engineer has approved the plan.
The traffic control plan shall show advance warning signs to minimize
public inconvenience and traffic impacts on the quality of the work. The traffic
control plan shall also include any temporary light signal modifications necessary
for the efficient movement of traffic. Two-way traffic must be maintained for
all major streets at all times, unless otherwise approved by the Engineer. Unless
otherwise approved, all streets shall have a minimum of one (1) ten (10) foot
wide lane open to traffic in each direction at all times. If Contractor cannot
maintain two lanes of traffic, the Engineer may approve the reduction of the
number of lanes to one twelve feet (12’) lane and the use of flag persons and
delineation in accordance with the Work Area Traffic Control Handbook
(WATCH). Contractor shall provide the Engineer with one week of advanced
notice for any special closure considerations, which should be included in the
required traffic control plan.
Construction operations shall be conducted in such a manner as to cause
as little inconvenience as possible to abutting property owners. All
businesses/residents shall have access to their driveways at all times. Contractor
shall not be allowed to close the entire width of streets, and shall sand driveways
23-12
as necessary during seal coat operations. Black sand shall be used for sanding
and shall be mechanically and evenly spread or broadcast.
Contractor shall schedule slurry and chip sealing such that access to an
area is maintained and that residents will be within 1000 feet of an open street
with a route out of the area being slurry sealed. However, the Engineer has the
right to modify the above criteria to accommodate the residents’ needs.
Contractor shall notify the public seventy-two (72) hours prior to the start
of work by placing door hangers to all business and residences that may be
affected by the work as determined by the Engineer. Contractor may be required
to contact business owners in person to explain the work schedule as determined
by the engineer. No work shall be permitted until the public has been notified.
If Required by the Engineer, Contractor shall notify the following City
departments and agencies seven (7) days prior to performing the work: Public
Works Solid Waste Division, (Street Cleaning Section) Public Works Parking
Division, Public Works Street Maintenance section, (Traffic Signs and Markings
Section, Traffic Signals and Lighting Section), Police Department
Communications Center, Fire Department Communications Center, Sacramento
Metro Regional Transit (bus stops and light rail). If required, Contractor shall
contact the appropriate representative of each City department or agency, and
provide a work schedule in writing.
Contractor shall clean, sweep, and maintain the cleanliness of the streets
to be paved to the satisfaction of the Engineer throughout the course of the
work. Materials spilled or dispersed as a result of the work on adjacent streets
shall also be cleaned at the expense of Contractor. The street shall be swept
with a mechanical type pickup machine and shall be left thoroughly clean at the
end of each working day. The machine shall spray adequate amounts of water to
control dust.
23-7 PLACING
Concrete bridge decks shall not be slurry sealed or chip sealed unless
otherwise directed by the Engineer.
All undulations and speed humps shall be sealed unless otherwise directed
by the Engineer.
All through driving lanes shall be spread in full lane width pulls only.
Sealing of driveway aprons, returns, and other incidental work shall be
accomplished concurrently with application of the street. The joint between
the pavement and the PCC gutter shall be slurry sealed by placing an overlap of
the lip of the gutter a minimum of 3/4 inches and a maximum of 2 inches. Chip
seal shall be applied 1” away from the gutter lips and not in the gutter pan.
23-13
When slurry or chip seal starts or finishes, a straight-line cut-off shall be
obtained by laying down a strip of building paper or other approved material.
Contractor shall remove such paper and any excess slurry or chip after the
application thereof. Edge limits of the slurry or chip on both sides of the street
shall be maintained in a neat and uniform line.
When feasible, all joints and curb lines shall be pulled by machine to keep
handwork to a minimum. Ridges or bumps in the finish surface will not be
permitted.
Building paper shall be placed at transverse joints and over previously
placed slurry seals to avoid the double placement of seals. Other methods to
avoid double placement may be used if first approved by the Engineer.
Existing blue fire hydrant locators shall be removed prior to placing of the
chip seal and slurry seal. New "raised, blue dot, hydrant marking devices" shall
be installed by Contractor after the slurry seal has been set for three (3) calendar
days, but no later than seven (7) calendar days after placement of the slurry
seal. Contractor shall place the new approved "blue dot, hydrant marking
devices" with approved two-part epoxy adhesive per the instruction and at the
locations determined by the Engineer.
23-8 PAYMENT
Measurement for payment shall be taken from edge of pavement to edge
of pavement, or from lip of the gutter to lip of gutter.
Payment for Bituminous Seals shall be at the unit price bid per square yard
and shall include full compensation for furnishing all labor, material, tools,
equipment, and incidentals to perform all work involved in slurry sealing, as
specified in these Special Provisions and as directed by the Engineer.
24-1
Section 24
CURBS, GUTTERS AND SIDEWALKS
24-1 CONCRETE IN CURBS, GUTTERS, AND SIDEWALKS
Concrete in curbs, gutters, and sidewalks shall be Class "B", as specified in
Section 10-5 of these Specifications. The cement shall be Type II as set forth in
Section 10-1 of these Specifications. Fly ash shall not be substituted for cement if
subgrade is expansive clay or if the “R Value” is ten or less.
When placing new concrete next to the existing concrete, Contractor shall
match the color of the existing concrete. The color additive and amount may
vary, and shall be approved by the Engineer prior to placing the new concrete.
Without prior approval, new concrete that does not match the color of the
existing concrete shall be removed and replaced at Contractor’s expense.
24-2 CONCRETE CUTTING
Where new concrete is to join existing concrete, the exact limits of existing
concrete removal shall be determined by the Engineer prior to saw cutting.
Concrete saws shall be water-equipped for dust control. Contractor shall take the
necessary precautions to prevent cut material and saw cutting run-off from
entering the City’s storm drain system.
24-3 SUBGRADE AND AGGREGATE BASE
Subgrade shall be prepared as specified in Section 14-7, and aggregate base
shall be prepared as specified in Section 17-1 of these specifications. A minimum
of six inches (6”) of Class 2 aggregate base shall be placed under all curb, gutter,
sidewalk and driveways, except that twelve inches (12”) of Class 2 aggregate base
shall be placed if the subgrade is expansive clay or the “R Value” is ten or less.
Prior to placing concrete, aggregate base shall be uniformly moist, and any excess
water shall be removed.
24-4 FORMWORK - NON EXTRUDED CONSTRUCTION
Forms for curb, gutter, and sidewalk shall be of a width equal to the full
depth of the curb and gutter and wood forms shall be a minimum of one and one
half inches (1 1/2") thick. Warped forms and forms not having a smooth straight
upper edge shall not be used. Benders, or thin plank forms, rigidly placed, may be
used for returns and other curves.
All forms must be carefully set to proper alignment and grades and shall be
rigidly held in place by the use of not less than five (5) pairs of stakes to every
24-2
twenty-foot (20') section, unless otherwise approved. Clamps, spreaders, and
braces shall be used when necessary to obtain tolerances specified herein.
Sidewalks shall be set with the upper edge true to line and grade and shall
be rigidly held in place by stakes placed on the outside of the forms and set flush
with the top edge of the form. The side forms shall not be removed for at least
eight (8) hours after concrete finishing has been completed.
24-5 EXTRUDED (SLIP-FORM) CONSTRUCTION
Extrusion machines shall be properly adjusted and in satisfactory operating
condition. Prior to placing concrete, contractor shall demonstrate proper
adjustment of all screeds and floats by measurements from grade stakes driven to
known elevations. Satisfactory operation and adjustment of all propulsion and
control equipment, including pre-erected grade and alignment lines, shall be
demonstrated to the satisfaction of the Engineer prior to and during the extrusion
of concrete.
Concrete used with extruded construction shall be of such consistency that,
after extrusion, it will maintain the shape of the curb section without support.
Concrete shall be fed to the machine at a uniform rate. The machine shall be
operated under sufficient uniform restraint to forward motion to produce a well-
compacted mass of concrete free from surface pits. Finishing with a brush
application of grout to repair defects will not be permitted.
Unless otherwise indicated in the Contract Documents, extruded concrete
curb shall be anchored to existing pavement by the use of dowel reinforcing, an
approved adhesive, or both, as directed by the Engineer. If an adhesive is used,
the surface shall be thoroughly cleaned prior to its application. The existing
pavement shall be cleaned by wire brush, by blast cleaning, or as approved by the
Engineer. The cleaned surface shall be free from dust, loose material, or oil. The
adhesive shall conform to Section 95, “Epoxy”, of the State Specifications.
24-6 EXPANSION JOINTS AND SCORE LINES
In curbs, gutters, and sidewalks, expansion (weakened planed) joints shall
be placed at curb returns, top of driveway transitions, light poles, fire hydrants,
beginning of drain inlet transition, other fixed objects, or where directed by the
engineer. Expansion joints shall be placed every sixty feet (60'). The joint material
shall be three-eighths inches (⅜”) thick, a minimum of two and one-half inches
(2½") deep, and shall conform to Section 10-4 of these Specifications. Expansion
joints must be at right angles to the line of the work.
Deep-score lines shall be one and one-half inches (1½") deep, one-eighth
inch to one-quarter inch (⅛"¼") in width, and placed every twelve feet (12') with
a standard four-foot (4') bite score in between. Expansion joints, score lines, and
24-3
bite scores shall conform to the Standard Drawings of Section 38 of these
Specifications.
When placing new concrete next to the existing concrete, Contractor shall
match the score lines of the existing concrete. The score lines spacing may vary
and shall be approved by the Engineer prior to placing the new concrete. Without
prior approval, new concrete that does not match the score lines of the existing
concrete shall be removed and replaced at Contractor’s expense.
24-7 FINISHING CONCRETE SURFACES
The top and exposed surface of the concrete shall be finished, whereby the
concrete is poured to form or extruded, properly screeded, floated, troweled,
edged, and smoothly finished, after which it shall be broomed with a fine hair push
broom drawn over the surface transverse to the line of work.
Non-extruded concrete shall be placed in the forms in layers not to exceed
six inches (6") and each layer shall be spaded and tamped until the concrete is
thoroughly compacted. Surfaces of non-extruded sidewalks shall be finished by
double screeding, which shall include working the concrete with a jitterbug until
the coarse aggregate is forced down into the body of the concrete and a layer of
mortar is thus forced to the top for floating, and troweling.
The top and face of the finished curb shall be true and straight, and the top
surface of curbs shall be of uniform width, free from humps, sags, or other
irregularities. Grade tolerance of the gutter flow line, lip of gutter, back of curb,
and back of sidewalk shall not exceed plus or minus 0.05-foot in any twenty-five
foot (25') length from the elevations shown on the plans. When a straightedge 10
feet long is placed on the top of a finished surface, the surface shall not vary more
than .02 feet except at grade changes or curves. Contractor shall water test the
gutter at the time of construction, and no more than .02 feet of water shall remain
shortly after water supply is stopped.
Partial concrete pours shall terminate at an expansion joint or deep-score
line. The end of such a partial pour shall be vertical and square ended. If the
partial pour is terminated at a deep-score line dowels shall be required.
24-8 CURING OF CONCRETE
Concrete shall be cured in conformance with the provisions set forth in
Section 10-6 of these specifications.
24-9 DAMAGE AND REPAIRS
Any damage done to concrete curbs, gutters, sidewalks, or driveways during
the progress of the work shall be repaired by Contractor to the satisfaction of the
24-4
Engineer. Contractor shall protect the work from graffiti and vandalism. Patching
of damaged areas shall not be allowed. Damaged or vandalized areas shall be
removed and replaced to the nearest score line as directed by the Engineer at
Contractor’s expense.
24-10 SLOPE AND WIDTH OF SIDEWALKS
Sidewalks and planting strip between curb and sidewalk shall slope
uniformly towards the street at a rate of not more than two percent (2%) and not
less than one percent (1%). The transverse slope of the finished surface shall be
uniform to a degree such that no depressions greater than 0.01-foot are present
when tested with a straightedge laid in a direction transverse to the centerline and
extending across the width of the sidewalk.
Unless otherwise shown on the Plans or by the Special Provisions, sidewalks
shall be four feet six inches (4-6”) wide and three and five eights inches (3⅝”)
thick.
24-11 DOWEL REINFORCEMENT
Dowel reinforcement shall be installed to join existing concrete to new
concrete as directed by the Engineer. A typical dowel installation consists of a No.
4 bar snugly fit or epoxied four to six inches, and spaced between 18 and 24 inches
apart, in the existing concrete. The dowels shall conform to Section 21 of these
Specifications.
24-12 CURB RAMPS AND DRIVEWAYS
Curb ramps for the physically handicapped and driveways shall be
constructed to the dimensions, lines, grades as shown on the plans, and to the
drawings shown in Section 38.
24-13 CURBS & GUTTER RECONSTRUCTION TO ACCOMMODATE DRIVEWAYS
Where curbs are removed for the purpose of constructing a driveway, the
entire curb and gutter shall be removed to the nearest score line and the gutter
rebuilt as directed by the Engineer.
24-14 PAYMENT
On unit price proposals, unit prices will be required as set forth in this
paragraph. The price bid on each of the following items shall include full
compensation for furnishing all material, labor, and equipment necessary to
construct the completed work as shown on the Plans.
24-5
1. Concrete Curb and Gutter
Payment for concrete curb and gutter will be at the price bid per lineal foot
which will include full compensation for finishing the subgrade, dampening the
subgrade, including furnishing the water; furnishing, placing, and later removing
necessary forms and form work; furnishing and finishing concrete; curing concrete;
furnishing and placing expansion joint material; furnishing and placing dowel
reinforcement; and doing such other work as may be necessary to construct the
curb and gutter complete in place as shown on the Plans.
If curbs and gutters of more than one type are specified on one job, then
separate unit prices will be bid for each type specified.
2. Sidewalks
Payment for sidewalk will be at the price bid per square foot which will
include full compensation for finishing the subgrade; dampening the subgrade,
including furnishing the water; furnishing, placing, and later removing necessary
forms and form work; furnishing concrete; furnishing and placing expansion joint
material; finishing the sidewalk surfacing; curing the sidewalk, furnishing and
placing dowel reinforcement; and doing such other work as may be necessary to
construct the sidewalk as shown on the Plans.
If sidewalk thickness varies on a job, then separate unit prices will be for
each thickness specified.
3. Curb Ramps and Driveways
There will be no separate payment for curb ramps and driveways and the
cost thereof shall be included in the price bid for sidewalk and/or curb and gutter,
unless otherwise indicated in the Special Provisions.
4. Removal of Existing Curb, Gutter, and Sidewalk
Payment for Removal of Existing Curb, Gutter and Sidewalk will be included
in the payment for “Clearing” or “Clearing and Grubbing” per Section 13. If there
is no item for “Clearing” or “Clearing and Grubbing”, payment for removal of curb,
gutter and sidewalk will be at the price bid per lineal foot and will include full
compensation for sawcutting, removal of curb, gutter and sidewalk and disposal at
an appropriate location and all other effort associated with this item.
25-1
Section 25
SANITARY SEWER AND STORM DRAIN MANHOLES
25-1 STANDARD MANHOLES
City standard manholes shall conform to Sections 10, 14, 25, and to the
drawings shown in Section 38 of these Specifications. Unless otherwise shown
on the Plans or called for in the Special Provisions, only City standard manholes
shall be used on City work.
25-2 MANHOLE CASTINGS
Castings for manhole heads and manhole covers shall conform to Section
10-25 of these Specifications. Dimensions of manhole heads and covers shall be
as shown in Section 38 of these Specifications.
25-3 CONSTRUCTION OF MANHOLES
Sanitary sewer and storm drain manholes shall be watertight structures
constructed by placing precast concrete sections on a cast in place or precast
concrete base. All construction of sewer and storm drain manholes shall be
constructed using precast concrete bases.
1. Precast Concrete Sections
Precast concrete sections shall conform to ASTM C 76 for Class III pipe, or
C478 for precast reinforced concrete manhole sections. Manhole barrels, pre-
cast bases, cones, flat top lids, and grade rings shall conform to the requirements
of ASTM C 478. Lifting holes shall be sealed with plastic sealing compound
conforming to Section 10-37 on the side facing the soil and grouted smooth on
the interior with a non-metallic, non-shrink grout in conformance with Section
10-55.
2. Cone sections
Cone sections shall be constructed of concentric cones except in the
following cases:
a. Eccentric Cone, Type 3A Manholes 8-foot deep and greater
b. Eccentric Cone, Type 4 Manholes for sewer mains 21-inch and
larger; storm mains 27-inch diameter and larger
c. Reduced Height Cone Manholes for pipe with depths of cover
measuring 30 inches to 42 inches above crown of largest
25-2
connecting pipe
d. Flat Top Lid Manholes for pipe depths of cover of 18 inches to
30 inches above the crown of the largest connecting pipe
3. Concrete Bases, General
Concrete manhole bases may be either cast in place or pre-cast of a type
and manufacture as approved by the Engineer. Unless otherwise approved by the
Engineer, a minimum of twelve-inches (12”) of Type A clean crushed rock
conforming to Section 10-14 of these Specifications shall be placed and
compacted below the base to provide a firm foundation. If subgrade cannot be
compacted using standard construction methods, it will be considered unsuitable
material and handled in accordance with Section 14-8 of these Specifications.
Stubs in the base shall match inlet pipe sizes and shall align true with all
inlet and outlet pipes (within a tolerance of ± 4 degrees). Reducers will not be
permitted. All inlet pipes that enter the manhole at the bases shall be
channelized through the manhole with smooth uniform bends toward the
direction of flow. In all cases, positive slope for all inlet pipes shall be maintained
through the manhole. Two flexible joints shall be provided outside manhole
barrel for each pipe connecting to a precast manhole base. Flexible joints shall
consist of standard bell and spigot connections. Upon written approval by the
Engineer, flexible connectors with stainless steel shear bands as manufactured
by Fernco, or equal, may be installed. Joints shall be one pipe diameter apart
and a minimum of 24-inches apart. Pipe connections to base shall be grouted in
place and made watertight.
Manhole bench shall slope upwards from the spring-line of the pipe to the
projected level of the crown of the pipe at the manhole wall, or 12 inches above
the spring-line, whichever is less. All holes, cracks, and seams shall be grouted
flush with the manhole interior using non-shrink nonmetallic grout in accordance
with Section 10-55. All internal surfaces shall be constructed with a smooth and
uniform finish.
4. Cast-in-place Bases
Cast in place concrete bases shall be Class “B” concrete as set forth in
Section 10-5 of these Specifications. Portland Cement shall be Type II, as set
forth in Section 10-1 of these Specifications. Installation of cast in place bases
shall require written approval of the Engineer.
5. Manhole Flowlines
Manhole flowlines for main pipe and intersecting mains thirty-six inches
(36”) or less in diameter shall be constructed of vitrified clay pipe liners. If the
25-3
main is “laid through”, flowline material shall be same as the host pipe. PVC
flowlines are not allowed.
Where multiple pipes are joined, the host pipe for purposes of this specification
is defined as the downstream pipe. If inlet and outlet pipes are of different sizes,
new flowline pipe size shall match larger pipe size. If host pipe is not utilized as
the flowline, new flowline shall match inlet and outlet pipe elevations and shall
extend to inside face of manhole. For host pipes up to 36-inches in diameter, all
inlet pipes shall be channelized through the manhole base using clay pipe bends,
grouted smooth to prevent the accumulation of debris.
Manholes not constructed in streets shall have three (3), six inch (6”)
adjusting rings placed between the top of the cone and the bottom of the
manhole head. Top of head to be six inches (6”) above the ground surface.
Manholes constructed in streets shall have the top of the cone within
twelve inches (12”) to eighteen inches (18”) of final street grade.
6. Precast Bases
Precast concrete bases and their details shall have the prior approval of
the Engineer and shall conform to ASTM C 478 and the Standard Drawings.
Openings in the base that are not connected to a pipe shall be sealed with
a watertight plug such as a “Gripper” mechanical wing nut plug by Cherne, or
equal, and grouted smooth.
7. Joining Precast Manhole Sections
Preformed plastic sealing compound, in conformance with Section 10-37
of these Specifications, shall be used for joining all precast manhole sections.
Prior to application of preformed plastic sealing compound, all joint surfaces
shall be thoroughly cleaned. The sealing compound shall be protected from dirt
during placing. Ends of the compound shall be joined end-to-end and not joined
by overlapping. Squeeze-out on the inside of the manhole shall be neatly
trimmed flush with the inside surface.
All surface irregularities and joints in the interior of the manhole shall be
grouted smooth with non-shrink metallic grout in conformance with Section 10-
55. In areas of high groundwater, the external joint of each barrel section and
of the barrel/cone connection shall be sealed with an external rubber sealing
wrap as manufactured by Infi-Shield Inc. or equal. The seal shall be made of
neoprene and EPDM rubber and have a minimum total thickness of 60 mils.
Material shall conform to specifications of ASTM C 923, ASTM C 443, and ASTM F
477.
Material shall extend beyond each side of the joint a minimum of 3-inches,
be continuous around the perimeter of the barrel section, and overlapped a
25-4
minimum of 6-inches. “High groundwater” will be considered a location where
the groundwater reaches the level of the manhole barrel during a typical rainy
season.
8. Manhole Chimneys
For manholes constructed in streets, the height of the manhole chimney
shall be between six and three-quarters inches (6-¾”) and eighteen inches (18”)
and in accordance with these guidelines. In general, manhole precast
components shall be selected to produce the minimum practical chimney height.
In newly constructed streets, chimney height shall be between six and three-
quarters inches (6-¾”) and thirteen inches (13”). On streets with average cross
slopes greater than 3% or streets receiving overlays, chimney height shall be
between twelve and eighteen inches.
9. Chimney Collars
There shall be a minimum of eight inches (8”) of concrete placed around
the head after it is set to the final street grade. The concrete shall extend from
two inches (2”) below the top of the manhole cone to a point two inches (2”)
below the pavement grade. After the concrete has hardened, the remaining
two-inch (2”) space will be filled with asphaltic concrete carefully raked and
compacted by approved powered tampers.
10. Concrete Collars (unimproved areas)
For manholes not constructed in streets, three (3), six inch (6”) adjusting
rings shall be placed between the top of the cone and the bottom of the manhole
head. Top of head shall be a minimum of six inches (6”) above the ground
surface. A concrete collar shall be constructed around head a minimum of six
inches (6”) wide, from top of cone to top of head.
11. Manhole Location Signs
For manholes not constructed in streets a manhole location sign shall be
installed in accordance with these specifications and as directed by the Engineer.
The use of concrete for mount stabilization will not be allowed. Sign posts shall
be driven a minimum of three feet into the undisturbed or compacted soil. If a
stable mount cannot be achieved at minimum sign post mounting heights, greater
driven depths must be used in conjunction with longer channel posts. All signs
shall be mounted on the wide, or open, side of the channel post. Bolts shall
protrude beyond the lock nut by at least a full thread after assembly, and care
shall be exercised when tightening the bolts so as not to create a “Dimple” in
the aluminum sign.
25-5
12. Manhole Connections
Connections to an existing manhole shall be made using a “Core-Bore”
technique or other method approved by the Engineer. All connections to sanitary
sewer manholes shall be made using a resilient connector conforming to ASTM C
923, as made by Kor-N-Seal, A-LOK, or approved equal, and shall be watertight.
For connections not part of the base, the annular space between the resilient
connector and the manhole wall shall be filled with a flexible material approved
by the pipe manufacturer.
13. Manhole Testing
In areas where ground water is expected, including but not limited to
Pocket Area, Willow Creek, North Natomas and areas close to the rivers, all
manholes shall be tested and shall meet the requirements of ASTM C 1244 prior
to acceptance. For installations not affected by groundwater a minimum of 25%
of manholes shall be tested. At the discretion of the Engineer, a failed test may
result in an increased number of manholes to be tested. Manholes shall be tested
prior to backfill. If the manhole fails the test at this time, the manhole shall be
repaired by Contractor and retested. This procedure shall be repeated until the
manhole passes the required test. The Engineer may also require the manholes
to be tested using this method after backfilling if he has reason to suspect that
the manhole has been disturbed during the backfilling operation, or at other
times during construction of the improvements being installed as part of the
development.
In order to prepare the manhole for this test, all lift holes shall be plugged
and all pipes entering the manhole shall be temporarily plugged, taking care to
securely brace the pipes and plugs to prevent them from being drawn in to the
manhole.
The test procedure shall be as follows:
a. The test head shall be placed at the top of the manhole in
accordance with the manufacturer's recommendations.
b. A vacuum of 10 inches of mercury shall be drawn on the manhole,
the valve on the vacuum line of the test head closed, and the
vacuum pump shut off. The time shall be measured for the vacuum
to drop to 9 inches of mercury.
c. The manhole shall pass if the time for the vacuum to drop from 10
inches of mercury meets or exceeds the values indicated in Table
1 of ASTM C 1244.
The vacuum gauge used for this test shall be supplied by Contractor, and
25-6
shall have maximum scale division of 0.1 psi, and shall have an accuracy of 0.04
psi. Accuracy and calibration of the gauge shall be certified by a reliable testing
firm at six month intervals, or when requested by the Engineer. In addition, the
Engineer may compare Contractor's gauge with a City owned gauge at any time.
During testing, the vacuum gauge shall be located such that it is readily visible.
Surface restoration shall be in accordance with the section of the General
Requirements entitled “Pavement Cutting and Surface Restoration” and shall be
paid for under this item of the contract. Pavement cutting shall be perpendicular
and parallel to the centerline of the road.
25-4 ADJUSTING MANHOLE HEADS
Existing manholes in streets shall be adjusted to grade when shown on the
Plans or called for in the Special Provisions.
Manhole heads shall be raised by wiring the frame to two 2" X 4"’s of
sufficient length to span the excavation. The space between the old manhole
and the bottom of the head will then be filled with a cement mortar, conforming
to Section 10-37 of these Specifications, poured against a suitable form on the
inside of the structure. Concrete will then be poured around the head to a point
two inches (2") below the top of the head. Concrete shall be Class “A” concrete,
conforming to Section 10-5 of these Specifications. After the concrete has
hardened, the remaining two-inch (2") space will be filled with asphaltic
concrete carefully raked and compacted by approved powered tampers.
When adjusting a manhole head will result in less than six and three-
quarters inches (6¾"), or more than eighteen inches (18") between the top of the
cone and final street grade, the cone shall be removed and forty-eight inch or
sixty inch (48" or 60") diameter manhole barrels shall be added or removed so
that the top of the cone is within six and three-quarters to eighteen inches (6¾"
to 18") of final street grade.
Manhole heads that need to be lowered shall be removed as directed by
the Engineer to a depth that will allow the manhole to be reconstructed with the
proper cone and to the lines and elevation shown on the Plans. Manholes that
require lowering shall be indicated on the Plans or Special Provisions as manholes
to reconstruct. Manholes that require raising shall be indicated on the Plans or
Special Provisions as manholes to raise.
When manholes are required to be adjusted in a street that is open to
traffic, all work involved in adjusting shall be fully completed during the work
day so as to permit full use by traffic at 4 p.m. of the same day. Should
Contractor be unable to fully complete a manhole by the above time, a
temporary asphaltic cutback surface shall be placed in any depression so as to
provide a smooth traveling surface until the manhole can be fully completed.
25-7
The use of barricades around incomplete manholes during night hours in not
permitted.
25-5 FLUSHER BRANCHES
Flusher branches are not permitted for new construction.
25-6 PAYMENT FOR MANHOLES
On unit price Proposals, payment for manholes shall be at the unit price
bid per manhole. This price shall include full compensation for all necessary
excavation, form work, pre-cast and cast-in-place concrete, furnishing all other
material and doing all work necessary to construct the manholes complete in
place to the dimensions shown on the Plans or in these Specifications. If shown
in the list of bid quantities, the Proposal may require separate unit prices on
standard manholes of various depths but if only a single item is shown for
standard manholes, then manholes of all depths will be included and shall be
paid for at the price bid.
Special manholes, that is, those which may be shown on the Plans which
are separately detailed and do not conform to standard manhole details shall be
paid for under a separate item or items of the Proposal. The price bid per special
manhole shall include full compensation for doing all work and furnishing all
material necessary to construct the special manhole as shown on the Plans.
Payment for raising or reconstructing manholes shall be at a unit price
bid, which shall include full compensation for doing all work and furnishing all
material necessary to raise or reconstruct the manholes as shown on Plans or
Special Provisions. On overlay projects, raising of cones will be considered as
Extra Work and shall be paid for according to the terms and conditions of Section
4-6 of these Specifications.
26-1
Section 26
LAYING SEWER AND DRAIN PIPE
26-1 EXCAVATION
Trench excavation for all sewer and drain pipe shall conform to standard
drawing T- 80 and the following requirements
Table 26-1.1 Minimum and Maximum Trench Width (TW) @ Top
of Drainage Pipe
Pipe Inside
Diameter
(inches)
(Min. Trench Width)
Pipe Outside
Diameter Plus
(inches)
(Max. Trench Width)
Pipe Outside Diameter
Plus
(inches)
33 or less
12
16
36 or greater
12
24
Table 26-1.2 Minimum and Maximum Trench Width (TW) @ Top
of Sewer Pipe
Pipe Inside
Diameter
(inches)
(Min. Trench Width)
Pipe Outside
Diameter Plus
(inches)
(Max. Trench Width)
Pipe Outside Diameter
Plus
(inches)
Flexible Pipes
15 or less
12
24
18 or greater
12
36
Vitrified Clay Pipe
All Pipe Sizes
24
No Limit
26-2
Contractor shall substitute stronger pipe or increased bedding and backfill
requirements, subject to approval of the Engineer, at no extra cost, if the
specified trench width is exceeded by the fault of Contractor. If field conditions
do not allow for a trench within the above limitations, at no fault of Contractor,
as determined by the Engineer, alternative bedding and backfill requirements
shall be incorporated as directed by the Engineer and added cost will be
reimbursed as extra work.
At a minimum, the depth of excavation shall be three inches (3”) below
the outside diameter of the barrel or one inch (1”) below the outside diameter
of the bell, whichever is deeper.
No tunnels shall be allowed, except when, in the opinion of the Engineer,
it is impossible or impracticable to prevent tunneling.
Contractor shall comply with the requirements set forth in paragraph 6-8
“TRENCH SAFETY PLANS”, Section 6.
Trenches shall be excavated only as far in advance of pipe laying as can
be backfilled in the same day. The maximum total length of open trench shall
be five hundred feet (500’). Under no condition shall more than fifty feet (50’)
of trench remain open overnight. A trench in an existing roadway which is not
to be regraded is defined as open until backfilled and paved with temporary
surfacing, ready for traffic. Other trenches are defined as being open until
backfilled to subgrade or the original ground line. Temporary surfacing is defined
in 26-11, “Repaving Trenches”.
Contractor, at his/her option, may elect to cut existing sewer services
that are encountered or tunnel under them. All sewer services cut by trench
excavation shall be replaced before nightfall of the same day in accordance with
Standard Drawing S-230, Section 38 of the Standard Specifications. No additional
compensation will be paid Contractor for any sewer services purposely or
accidentally cut and repaired
26-2 DEWATERING
Contractor shall be responsible for the control, removal, and disposal of
any groundwater that may be encountered in the course of excavating and
backfilling trenches or placing pipe. Whenever water or over-saturated soil
conditions exist which may interfere with proper installation, trenches shall be
dewatered to a level twelve inches (12”) below the trench bottom before
placement of any pipe or material. Unless approved in writing by the Engineer,
groundwater and/or water from trench dewatering shall be free of sediment and
other construction materials before entering the City storm drain system. A
dewatering plan, including a water de-sedimentation plan, shall be submitted to
26-3
the Engineer for approval prior to any pumping or discharge of water to the City
storm drain system.
For projects located within the combined system the procedures outlined
in paragraph 16-1, “Ground Water Discharges” shall be followed.
26-3 HEALTH AND SAFETY
Contractor is warned that existing sanitary sewers and appurtenances
have been exposed to sewage and industrial wastes. These facilities shall
therefore be considered contaminated with disease-causing organisms.
Personnel in contact with contaminated facilities, debris, wastewater, or similar
items shall be advised by Contractor of the necessary precautions that must be
taken to prevent infection. It is Contractor's responsibility to urge his personnel
to observe a strict regime of proper hygienic precautions, including any
inoculations recommended by the local public health officer.
Because of the danger of solvents, gasoline, and other hazardous material
in the existing sewers or drains, these areas shall be considered hazardous to
open flame, sparks, or unventilated occupancy. Contractor shall be aware of
these dangers and shall take the necessary measures to assure his personnel
observe proper safety precautions when working in these facilities.
Contractor shall not allow any wastewater to discharge from sanitary
sewage collection systems onto adjacent lands or waters. In case of accidental
discharge, Contractor at his/her expense shall be responsible for containment,
immediate cleanup, and disposal to the full satisfaction of the Engineer. Where
containment is not possible, Contractor at his/her expense shall provide
adequate disinfection as directed by the Engineer or jurisdictional agency. If, in
the opinion of the Engineer, Contractor fails to adequately follow the above
guidelines, the City will make arrangements to have the work done by others,
and have the cost deducted from amounts owing to Contractor.
26-4 PIPE MATERIALS/TYPES
Sewer and drain pipe shall conform to Sections 10, 26, and 38. The type,
class and size of pipe are generally shown on the Plans and/or in the list of
quantities contained within the Proposal.
1. Continuous types
Only one type of pipe shall be used between manholes with the exception
of changing from Class III to Class IV RCP as long as the pipes are completely
compatible with no modifications and both classes of pipe come from the same
manufacturer and are of the same manufacturing process.
26-4
Prior to the start of work, Contractor shall submit a plan showing types of
pipe and locations to the Engineer. Any deviation in the plan thereafter shall
not be allowed unless approved in advance by the Engineer.
2. Acceptable Sewer and Combined Sewer Pipe Types
Sewer pipe types shall be as shown on the Plans or as noted in the Special
Provisions and shall be of one of the following types unless otherwise noted:
Vitreous Clay (VCP); Closed Profile Polyvinyl Chloride (CPPVC); Polyvinyl Chloride
(PVC); Glass Fiber-Reinforced Thermosetting-Resin; calcareous aggregate
reinforced concrete (RCP) Class ; or HDPE Solid Wall Fusion Jointed.
3. Acceptable Drainage Pipe Types
Drainage pipe types shall be as shown on the Plans or as noted in the
Special Provisions and shall be of one of the following types unless otherwise
noted : Reinforced Concrete (RCP) Class III or Class IV; Closed Profile Polyvinyl
Chloride (CPPVC); Polyvinyl Chloride (PVC); Glass Fiber-Reinforced
Thermosetting-Resin; or HDPE Solid Wall Fusion Jointed.
26-5 LAYING PIPE
Laying sewer and drain pipe shall conform to Sections 10, 14, 26, and 38.
Pipe shall be placed in accordance with the Plans, Special Provisions,
manufacturer’s recommendations, and as directed by the Engineer.
1. Saw-cutting over existing pipelines
Prior to saw-cutting, Contractor shall mark the exact location of the
existing pipeline on the pavement using a ferreting device or equivalent.
2. Manhole connections
All connections to the manholes not cast as part of the manhole base shall
be made by use of a coring machine. The annular space between the outside of
the pipe and the manhole shall be sealed by using a flexible annular space filler
such as "Kor n' Seal Cavity O-Ring" by NPC Inc. or approved equal.
3. Bedding
Bedding shall be Type A clean crushed rock and shall be placed in
accordance with these Standard Specifications and the pipe manufacturer’s
recommendations. The bedding material shall provide uniform support of the full
length of the pipe to a width of at least fifty percent (50%) of the pipe internal
diameter. Initial backfill shall be brought to uniformity on each side of the pipe
26-5
to prevent distortion or displacement. Consolidation under pipe haunches shall
be accomplished by shovel slicing or rodding to assure all voids are filled.
Remaining initial backfill shall be placed in lifts and then consolidated with
vibratory equipment to insure proper compaction. Ponding and jetting methods
of achieving compaction will not be allowed.
4. Special foundation treatment
Whenever the bottom of the trench is soft or rocky, or, in the opinion of
the Engineer, otherwise unsuitable as a foundation for pipe bedding, the
unsuitable material shall be removed to a minimum depth of six inches (6”) and
replaced with Type D clean crushed rock, “pit run” or cobbles or any combination
thereof. Pit run shall have a minimum sand content of 25 and shall be compacted
to 90% relative compaction. Cobbles shall be a maximum of 12” and a minimum
of 4”.
As an alternate to, or in addition to, the bedding materials specified
above, the Engineer may direct Contractor to furnish and place geotextile fabric
below the bedding materials. The geotextile material shall be a high modulus
woven fabric, and shall be inert to commonly encountered chemicals, rot-proof,
and resistant to ultraviolet light, insects, and rodents. The geotextile fabric
shall have a minimum grab tensile strength of two hundred pounds (200 lbs.) in
any direction as measured in accordance with ASTM D 4632, a Mullen burst
strength of at least four hundred pounds per square inch (400 psi) per square
inch per ASTM D 3786, and an Equivalent Opening Size no larger than the U.S.
Standard Sieve Number 50 as determined by ASTM D 4751. Geotextile fabric
shall be Mirafi 600X or equal. Each roll of fabric shall be handled and placed in
accordance with the manufacturer’s recommendations. Furnishing and placing
of geotextile fabric will be paid for as extra work as defined in 4-6, “Extra Work,
Force Account”.
If material more than twelve inches (12”) below the typical trench bottom
is ordered removed by the Engineer, the excavation below that point and the
imported material required to backfill the trench to that elevation will be paid
as extra work as provided in Section 4 unless otherwise specified in the Special
Provisions. Before excavation of the pipe trench in fill areas of roadway
embankments, the fill area or embankment shall be completed to a height above
the pipe invert grade line of not less than twice the internal pipe diameter or to
final fill or embankment subgrade, whichever is lower, but in no case less than
twelve inches (12”) above the top of the pipe. Such embankment shall be
compacted to a minimum relative compaction of ninety percent (90%) for a
distance on each side of the pipe equal to a least two (2) pipe diameters. The
remainder of the embankment shall be compacted to the minimum relative
compaction specified elsewhere in these Specifications for the type of
construction being done, or as specified in the Special Provisions or on the Plans.
26-6
5. Trench backfill
a. Initial backfill
Initial Backfill shall be provided by Contractor and shall be placed
in accordance with these Standard Specifications and the pipe
manufacturer’s recommendations. Initial backfill shall be the material
between the top of the bedding material and six inches (6”) above the top
of the bell or barrel if the pipe does not have a bell. Unless otherwise
indicated in the Special Provisions, initial backfill shall be granular
material consisting of imported Type A, or Type B clean crushed rock,
conforming to the requirements of 10-17, “Clean Crushed Rock” of these
Standard Specifications.
Initial backfill shall be placed immediately after pipe joints have
been completed, inspected, and passed by the Engineer. The material
shall be carefully placed so as not to disturb or damage the pipe and shall
be brought up evenly on both sides. Initial backfill material shall be
placed in layers not exceeding eight inches (8”) in depth before
compaction at or near optimum moisture content. Contractor shall place
initial backfill by shovel slicing, tamping, and/or vibratory compaction in
order to produce firmly compacted material under the haunches of the
pipe. Compaction shall be by mechanical pneumatic or vibratory
compaction equipment approved by the Engineer. Care shall be used to
avoid dislodging the pipe. No wedging or blocking of the pipe will be
permitted. Ponding and jetting methods of achieving compaction shall not
be allowed.
When the bedding material for the pipe consists of crushed rock,
sand shall not be used as initial backfill material.
b. Trench backfill
Unless otherwise approved by Engineer, trench backfill shall be
provided, and placed to grade by Contractor, in accordance with these
Standard Specifications and the pipe manufacturer’s recommendations.
Trench backfill shall be the material between the initial backfill and the
top of trench or subgrade. The material for trench backfill may be of job
excavated, native material provided that such material is free of organic
materials or other unsuitable materials as determined by the Engineer
that may cause voids or depressions to develop during or after placement
of the backfill. Rocks, stones and solid earth chunks exceeding three
inches (3”) in greatest dimension shall be removed from the trench
backfill material.
Trench backfill material shall be placed in layers not exceeding
26-7
eight inches (8”) in depth before compaction at or near optimum moisture
content. Until the total backfill above the top of the pipe exceeds three
feet (3’), machine-placed backfill material shall not be allowed to
“freefall” more than two feet (2’).
Unless otherwise shown on the Plans or specified in the Special
Provisions, compaction of all backfill material shall be by mechanical
pneumatic or vibratory compaction equipment. Minimum relative
compaction of the trench backfill material shall be ninety percent (90%)
when tested according to ASTM D 1557, except that the top six inches
(6”) below the subgrade shall be compacted to a relative compaction of
ninety-five percent (95%). Trenches in easements outside the street
rights-of-way may be compacted to ninety percent (90%) relative
compaction throughout the depth. Compaction testing will be performed
by the Engineer and the cost thereof will be borne by the City, except
that retests of areas which fail to meet the required compaction shall be
charged to Contractor and deducted from any payment due Contractor for
work performed under the terms of the Proposal.
Ponding and jetting methods of achieving compaction shall not be
allowed.
Upon written request by Contractor, and upon approval of the
Engineer, the trench may completely backfilled to the bottom of the AC
pavement with slurry cement or Control Density Fill backfill provided in
conformance with 10-16, “Controlled Density Fill”. For pipes and conduits
two inches (2”) and smaller, bedding, initial backfill, and trench backfill
shall be slurry cement backfilled, placed to within one and one-half inches
(1½”) of finished grade.
c. Unsuitable material/import
If the portion of existing, native material removed in the
excavation of trenches to be used for backfill is determined by the
Engineer to be unsuitable for backfill not due to any action or negligence
of Contractor nor because native material is inadequately protected from
inclement weather, Contractor shall remove unsuitable material and
import and place suitable backfill material.
The cost for this item shall be paid separately and it includes all
associated costs including hauling away unsuitable material, disposal, and
transportation and material cost for import material, except that the cost
of placing and compacting import material is not included in this item but
is included in the item for placing pipe. The quantity of "Unsuitable
Material/Import" and the cost thereof shall not include that native
26-8
material which is removed from the trench in the area wherein the pipe
bedding, initial backfill, aggregate base course, asphalt concrete or the
pipe itself is placed. Such material, whether unsuitable or not, and its
replacement material of whatever kind shall be included in the cost of the
pipe.
The quantity of unsuitable material/import shown on the Proposal
is for bidding purposes only. The unit price indicated will not be adjusted
because the actual quantity varies from the quantity shown on the
Proposal. The cost for replacing unsuitable material rendered unsuitable
due to any act or omission of Contractor or due to inclement weather shall
be borne by Contractor and there will be no compensation therefore.
Trench import material shall be placed in accordance with “Trench
Backfill” herein.
d. Unstable trench
Contractor may assume that trench side walls may be maintained,
without shoring, at a slope of three-quarter vertical to one horizontal
(3/4:1). When trench side slopes are not able to be maintained at this
slope due to unstable materials or excessively high ground water or both,
as determined by the Engineer, and not based on improper or insufficient
dewatering nor because of inadequate shoring and not due to any action
or negligence of Contractor, the trench shall be considered an unstable
trench. When such unstable trenches are encountered, as defined herein,
additional effort and materials will be paid for as extra work, as described
in Section 4, unless otherwise directed in the Special Provisions.
In areas of trench determined to be unstable, flexible pipe may be
used in sizes up to nominal 24-inch diameter. Larger sizes up to and
including 42-inch diameter may only be used if submitted with an
engineered design for trench details for normal installation and for
unstable trench conditions, stamped and signed by an engineer registered
in the State of California and with prior written approval by the Engineer.
Additional trench width shall also be provided in accordance with
manufacturer’s recommendations for installation in unstable conditions.
When placing flexible pipes in unstable trench locations,
Contractor shall perform that work necessary to create a stable trench.
All work shall conform to pipe manufacturer’s recommendations, to ASTM
D 2321, and the special provisions. At a minimum, vertical, stable trench
walls shall be maintained to 12 inches above the top of the pipe and
additional trench width shall be excavated, in accordance with pipe
manufacturer’s recommendations, to a point 12 inches above the top of
26-9
the pipe, and replaced with Type A clean crushed rock. Initial backfill
shall be brought to uniformity on each side of the pipe to prevent
distortion or displacement. Consolidation under pipe haunches shall be
accomplished by shovel slicing or rodding to assure all voids are filled.
Remaining initial backfill shall be placed in lifts and then consolidated
with vibratory equipment to insure proper compaction.
e. Precast manhole bases
Where pre-cast manhole bases are used, Contractor shall install a
flexible bell and spigot) joint a horizontal distance of 18-inches to 24-
inches from the wall of the manhole.
f. Existing pipe
Existing pipe shall be removed at such places as shown on the Plans
or as designated by the Engineer in accordance with Section 13 and the
Special Provisions. All removed pipes or portions thereof shall be disposed
of by Contractor.
g. Pipe laying, grade and alignment:
After the trench for pipe has been brought to the proper line and
grade, the pipe shall be laid in the following manner:
Pipe laying shall proceed upgrade with the bell or groove end of
the pipe placed upstream. Each section of pipe shall be laid true to line
and grade and in such a manner as to form a watertight, concentric joint
with the adjoining pipe. The interior of the pipe shall be cleared of all
dirt and debris as the work progresses. Pipe shall not be laid when the
condition of the trench or the weather is unsuitable, in the opinion of the
Engineer, because of water or mud which may interfere with proper
jointing. All open ends of pipe and fittings shall be adequately and
securely closed whenever the work is discontinued.
Circular reinforced concrete pipe with elliptical reinforcement
shall be placed with the minor axis of the reinforcement in a vertical
position.
The pipe shall be laid in strict conformity to the prescribed line and
grade and each pipe length checked to the top grade line. Three (3)
consecutive points on the same grade of slope shall be used at all times
to detect any variation from a straight grade. In case any discrepancy
exists, the work shall be stopped and the discrepancy immediately
reported to the Engineer. In addition, when requested by the Engineer, a
26-10
string line shall be used in the bottom of the trench to insure a straight
grade and alignment of the pipe.
At the option of Contractor, grade and alignment controlled by a
laser beam system which complies with OSHA requirements may be used.
The laser system shall have good visibility when used with suitable target
material. The laser system must be of the self-leveling type so that the
laser beam is automatically compensated for minute grade disturbances.
The laser system must also have an early warning system that
instantly warns the pipe layer when the laser is off grade. The laser system
is to be provided by Contractor and shall have a minimum accuracy of
±0.01 foot per one hundred feet (100’) on line; and a minimum visible
range of one thousand feet (1000’).
Grade tolerance of the flow line of pipe shall not exceed plus or
minus 0.05 feet. In addition, the total variation plus and minus from flow
line grade shall not exceed 0.05 feet in any twenty-five foot (25’) length.
Both joint surfaces shall be cleaned before the joints are made. Care shall
be used to prevent chipping or cracking of either end of the pipe during
installation.
h. Moveable trench support:
When using movable trench support, care should be exercised not
to disturb the pipe location, jointing or its embedment. Removal of any
trench protection below the top of the pipe and within two and one-half
(2½) pipe diameters of each side of the pipe shall be prohibited after the
pipe embedment has been placed and compacted. Movable trench
supports shall only be used in either wide trench construction where
supports extend below the top of the pipe or on a shelf above the pipe
with the pipe installed in a narrow, vertical wall subditch. Any voids left
in the trench wall or embedment material by support removal shall be
carefully filled with bedding material which shall be adequately
compacted. Removal of bracing between sheeting shall only be done
where backfilling proceeds and bracing is removed in a manner that does
not relax trench support. When advancing trench boxes or shield, there
shall be no longitudinal pipe movement or disjointing.
i. Protecting existing sewers and drains:
Mortar or brick plugs shall be installed and maintained in existing
manholes as directed by the Engineer in order to prevent surface water,
ground water, and debris from entering existing sewer or drain systems
during construction. Inflatable plugs will not be permitted. Care shall be
26-11
exercised in installing plugs to avoid interrupting service. Plugs shall be
removed upon completion of testing as described in 26-10.
j. Installation procedures for HDPE solid wall pipe:
i. Handling:
Pipe, fittings, and accessories shall be carefully inspected
before and after installation and those found defective shall be
rejected. Pipe and fittings shall be free from fins and burrs. Before
being placed in position, pipe, fittings, and accessories shall be
cleaned, and shall be maintained in a clean condition. Proper
facilities shall be provided for lowering sections of pipe into
trenches. Under no circumstances shall pipe, fittings or any other
material be dropped or dumped into trenches.
ii. Joint welding:
Sections of polyethylene pipe shall be joined into continuous
lengths on the job site above ground. The joining method shall be
the thermal butt fusion method and shall be performed in strict
accordance with the pipe manufacturer’s recommendations. Fusion
equipment used in the joining procedure shall be capable of
meeting all conditions recommended by the pipe manufacturer,
including, but not limited to, fusion temperature, alignment, and
fusion pressure.
Butt fusion shall conform to ASTM D 2657 and pipe
manufacturer’s criteria for the type of joining. Butt fusion joining
shall be 100% efficient and shall provide a joint strength equal to
or better than the tensile strength of the adjacent pipe.
Fusion equipment shall be operated only by technicians who
have been certified by the pipe manufacturer, and who have a
minimum of two (2) years of experience fusion welding pipelines of
the diameters used in this project. The technician’s experience
shall be documented in the HDPE pipeline submittal.
iii. Installation of pipe:
All pipe shall be carefully placed and supported at the proper
lines and grades and all pipe flanges shall be set level, plumb, and
aligned. All flanged fittings shall be true and perpendicular to the
axis of the pipe. All bolt holes in flanges shall straddle vertical
centerline of pipes. Piping shall be installed without springing or
26-12
forcing the pipe in a manner which would set up stresses in the
pipe, valves, or connected equipment.
26-6 SEWER AND DRAIN SERVICES
Sewer services shall be installed at the points shown on the Plans. All
sewer services shall be installed perpendicular to the main unless otherwise
shown on the plans or approved by the Engineer. All services, where not
connected shall be closed with a stopper or plug of proper size. Where services
are carried from the main line to the property line, stoppers shall be placed in
the ends of the pipe. Before backfilling, a 2” X 2” redwood post shall be placed
with its lower end at the end of the pipe, and its upper end extended vertically
twelve inches (12”) above the street grade. Where grade of sewer permits, the
flow line of a sewer service at the property line shall be four feet (4’) below the
street grade.
In addition, where curb and gutter exists, or is to be constructed
concurrently with sewer facilities, the location of each sewer service shall be
permanently indicated by inscribing the letter “S” two inches (2”) in height in
the curb directly above the line when the service is perpendicular to the street
centerline. Otherwise, the “S” mark for skewed or angling services shall be
placed at a right angle to the end of the service. When sewer services are
installed in an existing street, the curb mark shall be placed at the time the
service is installed to assure proper location.
In new subdivisions when the sewer services are installed before the curb
is constructed, it shall be Contractor’s responsibility to establish the exact
location of each sewer service and to furnish this information to the Engineer. In
all alley improvements where a main is being replaced, all services to that main
will be replaced and a clean-out installed as indicated on the Plans or specified
in the Special Provisions.
26-7 DRAIN AND DITCH BOX LEADS
RCP or PVC ditch box leads and fittings shall be constructed to the details
on the Plans, the Special Provisions and shall conform to Sections 10 and 14.
Where noted on the plans, C900 class 100 PVC pipe shall be used.
All connections of drain leads to the maintenance holes not cast as part
of the maintenance hole base shall be made by use of a coring machine. The
annular space between the outside of the pipe and the maintenance hole shall
be sealed by using a flexible annular space filler such as "Kor n' Seal Cavity O-
Ring" by NPC Inc. or approved equal.
26-13
26-8 PIPE JOINTS
All pipes shall have elastomeric gasket joints providing a water tight seal.
Joints in pipe shall conform to section 10-19of these Specifications.
26-9 PROTECTIVE COVERING
Whenever sewer or drain pipe is laid in trenches at such an elevation that
the top of the pipe bell is less than eighteen inches (18”) below sub-grade of the
street, the pipe must be covered with a protective covering as shown in Section
38, Drawing S-250, of these Specifications. The concrete used in making the
covering shall conform to Portland Cement concrete Class “A”, as denoted in
these Specifications. As an alternate, C900, C905, or ductile iron pipe with
controlled density fill placed as shown in Section 38, Drawing S-250 may be used,
as approved by the Engineer.
26-10 TESTING OF PIPE
After laying pipes, backfilling, trench compaction, and before placing any
road base or asphalt, sewer and drainage pipelines shall be inspected and tested
for obstructions and leakage, unless otherwise specified, as follows.
1. Test for obstructions
All lines or mains shall be cleaned by balling, and any obstructions or
irregularities shall be removed or repaired by Contractor. All testing, cleaning
and repairing shall be done to the satisfaction of the Engineer. Water used in
cleaning shall not be permitted to enter existing sewer or drainage systems.
Contractor shall provide all necessary labor, materials, tools and equipment for
the tests and shall dispose of all waste, including water at their own expense.
2. Test for leakage
As directed by the Engineer, individual pipeline joints or any section of
constructed pipeline shall be tested by the Contractor using the methods listed
or described in (3) and (4) of this Section, or the pipe manufacturers
recommendations An exception to this requirement is HDPE solid wall pipe
where only a hydrostatic test for leakage is required as recommended by the
manufacturer. For sections of pipe between manholes, no leakage is acceptable
for solid wall HDPE. Leakage testing must take place in the presence of the
Engineer.
3. Air test for leakage
Air testing of joints for RCP pipelines 27 inches and larger in diameter
26-14
shall follow ASTM C-1103.Pipeline sections tested at any one time shall be limited
to the length between adjacent manholes. The test section shall be pressurized
to 3.5 psi and shall be held above 3.0 psi for not less than five (5) minutes. Air
shall be added if necessary to keep the pressure above 3.0 psi. At the end of
this five (5) minute saturation period, note the pressure (must be 3.0 psi
minimum) and begin the timed period. If the pressure drops 0.5 psi in less than
the time given in the following table, the section of pipe shall not have passed
the test.
Table 2610.1 - Minimum Time for Prescribed
Pressure Drop
Pipe Diameter (inches)
Time Span
(seconds)
4
122
6
184
8
245
10
306
12
367
15
460
For larger diameter pipe use the following formula: Minimum time in
seconds = 370 X pipe diameter in feet. If the time for the pressure to drop 0.5
psi is less than the time given in the table, the leakage shall be repaired and the
line retested until found satisfactory to the Engineer.
When the prevailing ground water is above the pipe being tested, air
pressure shall be increased 0.43 psi for each foot the water table is above the
invert of the pipe.
House sewer services shall be considered part of the lateral to which they
are connected and no adjustment of test time shall be allowed to compensate
for the smaller diameter of the house services.
The pressure gauge used shall be supplied by Contractor, shall have
minimum divisions of 0.10 psi, and shall have an accuracy of 0.04 psi. Accuracy
and calibration of the gauge shall be certified by a reliable testing firm at six-
month intervals, or when requested by the Engineer.
4. Hydrostatic test for leakage
Hydrostatic testing of RCP pipelines 27 inches and larger in diameter shall
26-15
follow ASTM C-1103. Hydrostatic testing of pipeline sections shall be prepared
for testing by plugging the upper side of the downstream manhole and all
openings in the upstream manhole except the downstream opening. Where
grades are steep and excessive heads would result by testing from one manhole
to another, test tees, the same size as the main, shall be installed at
intermediate points so the maximum head on any section under test shall not
exceed twelve feet (12’).
A section of line prepared as above shall be tested by filling with water to
an elevation five feet (5’) above the top of pipe at the upstream end of the test
section, or five feet (5’) above the existing ground water elevation, whichever
is greater. The water shall be introduced into the test section at least four (4)
hours in advance of the official test period to allow the pipe and joint material
to become saturated with water. The water level shall then again be brought to
the five foot (5’) mark. At the beginning of the test, the elevation of the water
in the upper manhole shall be carefully measured from a point on the manhole
rim or test tee. After a period of four (4) hours, or less, with the approval of the
Engineer, the water elevation shall be measured from the same point on the
manhole rim and the loss of water during the test period calculated. If this
calculation is difficult, enough water shall be measured into the upper manhole
to restore the water to the level existing at the beginning of the test, and the
amount added taken as the total leakage.
The allowable leakage in the test section shall not exceed five hundred
(500) gallons per mile per day per inch diameter of pipe tested at the five foot
(5’) test head, unless otherwise specified. If it is necessary or desirable to
increase the test head above five feet (5’), the allowable leakage will be
increased at the daily rate of eighty (80) gallons for each foot of increase in
head.
Test sections showing leakage in excess of that allowed shall be repaired
or reconstructed as necessary to reduce the leakage to that specified above.
Water used in testing will not be permitted to enter existing sewer systems.
5. Testing for deflection
For all flexible sewer and drain pipes and fittings, the minimum pipe
stiffness (F/y) at 5% deflection shall be 46 PSI in accordance with ASTM D 2412,
“External Loading Properties of Plastic Pipe by Parallel-Plate Loading.” A
deflection test shall be made by Contractor upon completion and acceptance by
the Engineer of all backfill operations and prior to the placement of the finished
surface, if any. Deflection testing shall be conducted no sooner than 96 hours
following completion and acceptance of all backfill operations, unless otherwise
approved by the Engineer.
26-16
The deflection testing shall be witnessed by the Engineer and shall be
conducted by Contractor’s forces and performed at the expense of Contractor.
One-hundred percent (100%) of all flexible sewer and drain pipe mainline
installed shall be deflection tested for excessive deflection using a pre-sized,
rigid mandrel or “Go-No-Go” device 5% smaller than the average inside diameter
of the pipe as approved by the Engineer. Mandrel tests may be performed by
the City after a 6 month period of time at which time a maximum deflection of
7½% from the base internal diameter, as specified in ASTM D 3034 and ASTM D
2680 for PVC or ABS gravity sewer pipe, respectively will be allowed. The
mandrel used shall be the PHOS PVC Sewer Pipe Deflection Gauge or other
deflection gauge approved by the Engineer.
The mandrel shall be drawn through the pipe using only the force that can
be exerted by one individual on the end of a rope, using no mechanical
advantage. Under no conditions shall the mandrel device be attached to the
cleaning ball.
Pipe which does not pass all specified mandrel tests shall be replaced at
Contractor’s expense. Re-rounding or other attempts to reduce deflection
beyond the allowable shall not be acceptable. All re-tests for deflection shall
be made at the expense of Contractor.
6. Closed Circuit T.V. inspection
Unless otherwise directed by the Engineer, Contractor shall perform
Closed Circuit TV (CCTV) camera inspections of all new installations of sewer,
combined sewer, storm drain pipes, junction boxes, and manholes. Comply with
Section 26-12 requirements.
26-11 REPAVING TRENCHES
Certain construction projects may require the cutting of existing
pavements, the laying of pipe, backfilling and then repaving of the cut
pavement. When the trench is in an existing paved area, the pavement shall be
sawed or scored and broken ahead of the trenching operations. Before saw
cutting the pavement, Contractor shall use a ferreting device or equivalent to
determine the exact location of the existing pipes and mark them on the
pavement. The proper tools and equipment shall be used in marking and breaking
so that the pavement will be cut accurately to a neat and parallel line six inches
(6”) wider on each side than the trench width required. All cuts in Portland
Cement concrete pavements shall be sawcut with approved equipment.
Where the edge of the trench is within two (2) feet of existing curb and
gutter or pavement edge, the asphalt concrete pavement between the trench
and the curb or pavement edge shall be removed and replaced.
26-17
Contractor shall restore all surfaces which have been removed or damaged
by Contractor in kind, using the same material as existing, unless otherwise
noted on the Plans or in the Special Provisions. The repaving is to be done in such
a manner to, as closely as possible, replace the cut pavement with a similar type
and an equal or greater structural section. In any case, where a trench is cut in
existing pavement, or as directed by the Engineer, a temporary asphaltic plant
mix cut back surface not less than two inches (2”) in thickness shall be placed
immediately after the top backfill has been completed and compacted and
maintained at a level surface until removal. Temporary surfacing material shall
be removed just prior to placing the permanent surfacing material. Payment for
temporary paving shall be included in the price bid per foot of pipe placed, unless
otherwise set forth in the Special Provisions.
1. Asphalt concrete replacement
The structural section shall be no less than four inches (4”) of asphaltic
concrete over twelve inches (12”) of Class 2 aggregate base. Asphalt concrete
shall be Type B, medium, and its placement shall conform to the requirements
of Section 22 of these Standard Specifications. Class 2 aggregate base and its
placement shall conform to the requirements of Sections 10-7 and 17.
2. Portland cement concrete replacement
Restoration of existing Portland cement concrete pavement shall consist
of at least six (6) inches of Portland cement concrete and shall conform to the
requirements of Sections 10 and 19. Concrete surfaces to be replaced shall be
colorized, as necessary, to match existing adjacent concrete color by the
addition of Lamp Black coloring agent. Contractor shall submit concrete mix
design for approval including a proposed proportion of coloring agent appropriate
to the shade of adjacent concrete. Where entire alley requires replacement,
concrete shall not include coloring agent, unless directed by the Engineer.
3. Unpaved surfaces
Unless otherwise provided on the Plans or in the Special Provisions,
pipeline trenches in unpaved portions of street rights-of-way shall have the top
twelve inches (12”) filled with aggregate base Class 2, conforming to Section 10-
7 of these Specifications and compacted to ninety-five percent (95%) relative
compaction as determined by ASTM D 1557.
26-18
26-12 PROCEDURES FOR CLOSED-CIRCUIT TELEVISON (CCTV) INSPECTIONS OF
PIPING SYSTEMS
1. Standards
Unless otherwise directed or approved by the Engineer, CCTV
recording performed for acceptance of new pipelines shall conform to the
requirements herein. Submit, in accordance with Section 5-7 of these
Standard Specifications, one (1) electronic copy of the CCTV video,
database, and report on a portable electronic data storage device for
approval.
2. Equipment
a. Camera
The camera shall record in color. The footage read-out shall
appear on screen away from the central focus of the main. A target shall
precede the camera for measuring sags and offsets (size of target shall be
noted within the video and on the video label). Target sizes shall be as
follows, unless otherwise specified or directed by the City:
TARGET SIZE
PIPE SIZE
¾ inch
≤ 12 inches
1 inch
>12 inches and ≤ 36 inches
2 inches
>36 inches
The focal distance shall be adjustable through a range from 6 inches
to infinity. The camera shall be tractor driven with a rotating camera
head suitably sized for each pipe diameter to be inspected.
b. Recorder
The recorder shall record in digital video format using MPEG-2
technology or shall be capable of being converted to an MPEG-2 (*.mpg
file format) or the latest digital video format compatible with the City’s
applications without the loss of video quality.
c. Video Quality
The digital video recording shall be a high-resolution video of DVD
quality with a minimum of 720 columns of pixels by 480 rows of lines
(720x480) with a minimum refresh rate of 60 interlaced fields per second
(60Hz or 30 frames per second) as established by the National Television
System Committee (NTSC).
26-19
d. Lighting
There shall be sufficient lighting to produce a clear and sharp image
of the entire inside periphery of the pipe for all conditions encountered
during the work. Lighting is to be adjusted according to the size of pipe.
In an eight-inch diameter pipe with joints at five-foot intervals, the
lighting shall allow the camera to reveal not less than three consecutive
joints, or up to ten feet of unobstructed pipe shall be visible in the
monitor picture.
e. Locator
A locating device or other acceptable locating method shall be used
to locate points of deficiencies on the ground, in green paint, or green
flag.
3. Procedure
a. Timing
The Contractor shall notify the Construction Inspector two (2)
working days prior to televising the mains to allow the Inspector the option
of being on-site at time of televising.
The job is ready for CCTV inspection, only after compaction of
street sub-grade and prior to placement of road base. The following must
be completed before CCTV inspection:
i. All underground facilities, utility piping, conduits, and
access structures are installed, backfilled, and trench
backfill compacted.
ii. Final joint testing.
b. Schematic
The manholes shall be uniquely identified (e.g., location stationing,
letter identifier, consecutive numbering, etc.) on a plan to be provided
to the Inspector and the televised segments tied to the assigned manhole
reference. Use existing City Mapbook manhole identifiers unless otherwise
approved by City. The length of televised run shall be measured from
pipe end to pipe end in one contiguous pipeline segment from manhole to
manhole. Maximum allowable tolerance for the TV counter shall not
exceed 1 foot in 1,000 feet for location accuracy.
26-20
c. Camera Run
The main shall be flushed cleaned prior to running the TV camera.
TV runs shall not be performed during cleaning operations and shall
provide a clear view of the interior of the pipe and manholes. The
camera is to be placed in the main with the footage counter at zero (0) at
the pipe end within the manhole. The camera is to travel at a speed not
to exceed 30 feet per minute with slowdowns at joints and services.
Inspect service connections with a rotating camera head. The picture
shall be clear and bright enough to allow a photograph of a section to be
made. The footage counter, date, and time shall appear on screen at all
times, and show the upstream and downstream manhole line segments
being televised. All service laterals shall be televised and recorded from
point of service cleanout or manhole to City connection on City main or
manhole tap.
d. Water Introduction
Prior to performing the TV on new construction, the Contractor
must introduce enough water in the pipe segment(s) to fill all low sections
and flow through the final downstream structure included within the pipe
segment to be inspected. If any section of the pipe segment appears to
be dry, additional water must be introduced as described above. The City
Inspector will verify the adequacy of water and target size before the TV
is performed. The TV must begin within 30 minutes of introducing water
into the pipe segment.
e. Recording
The following items are to be recorded on the first 15 seconds of
the recording:
i. Location, subdivision name and/or project name and number
ii. Date and time
iii. Upstream and downstream manhole identifier or stationing
reference number associated with the project construction
plans
iv. Company name, Operator’s name and NASSCO’s PACP
Certification Number
v. Direction of travel (e.g.; against flow, with flow)
vi. Pipe size
vii. Pipe shape
26-21
viii. Pipe material
ix. Significant comments
A label shall be affixed to the portable electronic data storage
device and jacket or envelope with the above information, start-end
footage, and size of target.
Each televised segment shall be preceded by the following:
i. Location (MH to MH identifier or station reference number
associated with the project construction plans)
ii. main size, type of pipe, pipe shape
iii. main slope and flow direction
iv. length of run (measured per asbuilt plans)
v. number of pipes entering MH and sizes
vi. number of service connections
The portable electronic data storage device shall be given to the
City’s Engineer or Construction Inspector and shall become the property of
the City of Sacramento upon completion of the televised inspection. The
City reserves the right to reject any televised inspection not conforming to
the requirements herein. Any televised inspection that is rejected shall be
re-inspected at the Contractor’s expense.
4. Acceptance Criteria
Maximum acceptable sag for sewer pipes is ¾ inch, unless otherwise specified
in the Special Provisions and the Project Plans. All other criteria as set by the City
Standard Specifications and the Contract Documents shall apply for both sewer and
drain pipes. Within ten full working days from receipt of the digital video, database,
and report, the Inspector shall review and either approve the main(s) or call for
repairs. The Contractor is to be notified in writing of any deficiencies revealed by
the television inspection that will require repair. If the Contractor is to make repairs
and wishes to review the television inspection with the Inspector, the Contractor
shall contact the Inspector to set a time for viewing. Upon completion of any
repairs, the main is to be re-inspected.
5. Report
Perform and record all CCTV inspections in accordance with the National
Association of Sewer Service Companies’ (NASSCO’s) Pipeline Assessment
26-22
Certification Program (PACP). CCTV inspections shall be conducted entirely in
digital video format compatible with Granite XP software (version 7, Granite Net
or City’s most current version), recorded in accordance with section 26-12, 2.b.,
and stored on a portable electronic data storage device.
CCTV inspection reports shall be accurate to within +/- 2 (two) feet or
less of the total measured footage along the pipe from upstream end of the pipe
to the downstream end of the pipe or vice versa.
Every section of the pipe (access point to access point) shall be identified
on the video display in accordance with section 26-12, 3.d. In addition to
inspecting the pipe, all manholes shall be panned with the CCTV camera.
Documentation of the work shall consist of digital video recordings, the
PACP CCTV Report(s), and the unmodified PACP database. The database shall
contain PACP scoring for each inspection observation or defect. The
documentation shall note important features and any defects encountered. One
copy of the digital video recording, inspection observation database, and report
(one printed copy & one digital copy) shall be submitted to the City on a portable
electronic data storage device for approval. With the submission, it shall also
include the CCTV Inspection video form (attached to the end of this Section 26)
filled with required information.
26-13 PAYMENT FOR SEWER AND DRAIN PIPE
Payment for sewer and drain pipe will be at a price bid per lineal foot
which will include full compensation for pavement cutting and removal,
excavation, trenching, shoring, dewatering, removal and disposal of existing
pipe, bedding, furnishing and laying of pipe, initial backfill, trench backfill,
manhole connections, temporary paving, final paving and all other work
necessary to construct the sewer or drain pipe complete in place as shown on
the Plans.
Measurement of such lineal footage shall be the total distance along the
centerline of the pipe from the centerline of manhole to centerline of manhole
and shall include the straight run of all tees where used.
Payment for clean crushed rock or bedding material provided for use shall
be considered as included in the price paid for laying pipe, unless otherwise
indicated in the Special Provisions.
Payment for concrete or control density fill used as protective covering
shall be paid for at a separate price per lineal foot for protective covering in
place, unless otherwise set forth in the Special Provisions.
Where tee fittings are placed in a main sewer or drain line in connection
26-23
with sewer or drain services, payment for the fittings shall be considered as
included in the price per lineal foot for the main sewer or drain pipe and no
deduction or addition will be made to the length of main line laid.
Placing of sewer and drain services will be paid for at the contract unit
price bid per service, which price shall include full compensation for furnishing
and placing all service pipe from the tee or the fitting in the main sewer or drain
line to the property line, and furnishing and placing other necessary bends and
stoppers to construct the service complete in place.
The cost for testing and inspecting the pipe shall be included in the price
bid for the pipe in place.
The cost of removing and replacing pavement over trenches shall be
included in the price bid for installation of the pipe in place, unless otherwise
set forth in the Special Provisions.
26-24
CCTV Inspections of Pipe Systems ( Submission for Sewer/Combine or Storm Drain) Insp Form 020
****** ManHole Inspection is not Included ******
This submission is submitted by, Name: _____________________; Tel: ______________ Dept: ____________; Date: __________
This submission is received by, Name: _____________________; Tel: ______________ Dept: ____________; Date:
_________
Project ID: ______________, CPC or RPC; Project Name: __________________________________(Phase ___)
Developer, Name: ___
_________
____________________________________________________________________
TV Operator: Name: ________________________, Tel: __________________________
NASSCO Cert #: ____
___________ or Not Certified
Remarks: _____________________________________________________________________
*************************************************************************************************
The submitted items: 1) DVD video; Flash drive; Others: __________________________
2) NASSCO, PACP Report
*************************************************************************************************
-- Inspection Section ---
Type of Tests/Inspections required to be done Before CCTV Inspections Submission
*************************************************************************************************
CCTV Examiner, Name: ____________________________; Tel: ___________________; Date: ____________________
Approved, Sign: _________________________; Date: ___________________________________
Approved with Comments: ______________________________________________________________
______________________________________________________________
Reject this submission, By: _____________________ Date: ___________________________________
Rejection because of: 1) The said inspection section has not been completed;
2)
NSAACO, PACP: Main Inspection with Pipe-Run Graph
Report is incomplete;
3) NSAACO, PACP: Observation Report is incomplete;
4) TV the pipe line partial, not from MH to MH;
5) The plug for stub is not wing nut or equivalent device
6) Exceed the maximum acceptable sag for: Sewer, ¾”; Storm Drain, ___
Additional Comments: __________________________________; __________________________________________
: ________________
___________________; __________________________________________
----- After the approval of this TV inspection, please call for the project final walkthrough! -----
Sewer and/or Combined Collection System
( those have been tested & passed)
Mains, test type: ___________________
MH, test type: _____________________
The above information has been
verified
and
Approved by, Name : ____________________
Signed: ___________________ Date: __________
Tel: __________________________
Result, attached; No attachment
Remarks: ___________________________
_____________________________________
Storm Drain Collection
System
( those have been tested & passed)
Mains, test type: ________
___________
MH, test type: _______________
______
The above information has been verified and
Approved by, Name : ____________________
Signed: ____________________ Date: __________
Tel: ___________________________
Result, attached; No attachment
Remarks: ___________________________
________________________________________
Compaction Tested & passed, Approved by, Name: _______________________, Tel: ____________
Result, attached; Signed: _______________________, Date: ___________
Remarks: __________________________________________________________________________
__________________________________________________________________________
27-1
Section 27
WATER DISTRIBUTION SYSTEMS
27-1 GENERAL
All water pipe, fittings, valves, fire hydrants, blow-offs, air release valves
and other appurtenances shall be installed in accordance with the requirements
of the project Plans and Special Provisions, these Standard Specifications, the
American Water Works Association (AWWA), ANSI-61, the City’s Cross Connection
Control Policy, and the manufacturer’s recommendations. Materials shall be as
specified in Section 10 “Construction Materials” of these Standard Specifications.
During construction, Contractor shall not operate any valves in the
City’s distribution system and must request that City Utilities Department
Personnel operate them. Contractor shall request the Engineer to notify the City
Utility Department Personnel as specified in Section 27-11 of these Standard
Specifications.
If shown on the Plans or specified in the Special Provisions, Contractor
shall pay all fees for taps, tie-in connections, and meters in advance at the
Department of Utilities Customer Service Office, 1395 35
th
Avenue. Fees shall be
paid after the “Notice to Proceed” has been issued, and prior to the work being
performed by the Department of Utilities. For current fee information, contact
Customer Service at 264-5371.
27-2 WATER PIPE
1. General - All water pipes shall be designed to withstand the external earth
load and the AASHTO H-20 vehicle live load. The pipe shall also be designed to
withstand an internal working pressure of one hundred and fifty pounds per
square inch (150 psi).
2. Water Services - Pipe used for water services two inches (2”) in
diameter or less shall be copper or polyethylene tubing as specified in Section
10 of these Standard Specifications. Pipe used for water services four inches
(4”) in diameter or large shall be the same as specified for distribution mains.
Polyethylene services shall be a single piece of tubing (no joints allowed
including butt welds) and shall have a locating wire attached with ten (10) mil
tape at three foot (3’) spacing. The minimum allowable radius shall be thirty
(30) times the tubing diameter.
3. Distribution Mains (4" to 12") Unless otherwise specified on the Plans or
Special Provisions, water mains four inches (4") through twelve inches (12")
diameter in water distribution systems shall be made of ductile iron pipe (DIP),
27-2
or polyvinyl chloride pipe (PVC) meeting the applicable requirements of Section
10 of these Standard Specifications.
4. Transmission Mains (greater than 12") - Water mains greater than twelve
inches (12") in diameter shall be ductile iron pipe (DIP), concrete cylinder pipe
(CCP) or welded steel pipe (WSP) meeting the applicable requirements of Section
10 of these Standard Specifications.
27-3 TRENCHING FOR WATER PIPE
Trenches for water pipe including water transmission mains, water
distribution mains, fire hydrants branch leads, and water services shall be as
specified herein unless otherwise indicated on the Plans or in the Special
Provisions.
Prior to cutting pavement Contractor shall notify Underground Service
Alert (USA) per Section 6-19 of these Standard Specifications and shall bring to
the Engineer’s attention any possible conflicts.
Existing pavement to be removed shall be saw cut the full depth to provide
a neat straight pavement break along both sides of the pipe trench as shown on
Standard Drawing W-701. Contractor shall perform the pavement cutting
operation by saw cutting.
Trenches for water main pipe shall be excavated to the lines and grades
indicated on the Plans and as detailed by Standard Drawing W-701 in Section 38
of these Standard Specifications. Contractor shall furnish, install, and maintain
a trench shoring system in compliance with Section 6-8 of these Standard
Specifications.
Water distribution mains constructed in fully improved streets with curb,
gutter, and sidewalk shall be installed with a minimum of thirty-six inches (36")
of cover and a maximum of fifty-four inches (54") of cover measured from the
top of the pipe to pavement surface.
Water distribution mains in unimproved areas or in existing streets
lacking curb, gutter, and sidewalk shall be installed with a minimum cover of
fifty-four inches (54") and a maximum cover of sixty inches (60") measured from
the top of the pipe to the existing ground or pavement surface.
In order to avoid conflicts with other utilities, particularly at street
intersections, it may be necessary to deviate from the above-specified minimum
and maximum cover requirements. At locations where the crossing of water
mains with other underground utilities results in grade conflicts, adjustment to
the vertical alignment of the water main may be required. Adjustments over or
27-3
under the conflicting utility line shall be made as detailed in Standard Drawing
W-106 in Section 38 of these Standard Specifications. The cost to make these
adjustments shall be included in the bid price to install the pipe when the
conflicts are shown on the Plans.
In designing the distribution system, it was intended that ten feet (10') be
the minimum horizontal distance between parallel water and sanitary sewer lines
and services, and that the water main be at least twelve inches (12") higher. No
field changes shall be made that conflict with the requirement without prior
approval of the Engineer. When crossing a sanitary sewer force main, the water
main shall be a minimum of three feet (3’) above the sewer line and no fittings
within ten feet (10') of the crossing.
The bottom of the excavated trench shall be cleared of rocks and clay
lumps larger than two inches (2") in size. All grade stakes, wood, cut and
abandoned pipe, or other material shall be removed from the trench. The bottom
of the trench shall be smoothed and compacted to provide uniform support of
the pipe between the joints. The bottom of the trench shall be compacted to a
minimum of ninety percent (90%) of maximum dry density as determined by ASTM
Test Designation D698.
Whenever the bottom of the trench is soft or rocky, or, in the opinion of
the Engineer, otherwise unsuitable as a foundation for pipe bedding, the
unsuitable material shall be removed per Section 14-8 of these Standard
Specifications.
Unsuitable material encountered during excavation of the trench shall be
excavated and disposed of as directed by the Engineer. Contractor shall excavate
unsuitable material and the resulting space shall be filled per Section 14-8 of
these Standard Specifications.
At the end of each working day, the maximum amount of trench open on
any portion of the project shall not exceed the length of open trench necessary
for placing pipe the next working day. This open trench shall be bridged. Open
trench exceeding the length necessary for placing the pipe the next day shall be
backfilled, compacted, and temporarily paved. Within the traveled way in a
direction crossing traffic flow, the open trench shall either be bridged or shall
be backfilled, compacted, and temporarily repaved. Temporary paving shall be
installed in accordance with the requirements of Section 14-4 of these Standard
Specifications.
Temporary bridges placed over excavated trenches at street
intersections, pedestrian crosswalks, driveways, and private roadways shall be
provided by Contractor for the safe passage of pedestrian and vehicular traffic
in accordance with Section 6-10 of these Standard Specifications.
27-4
Footbridges adequate for pedestrians shall have a minimum width of five
feet (5'). The footbridges shall be designed and constructed to withstand a
minimum uniform load of one hundred and fifty pounds per square foot (150 psf).
Handrails and support posts shall be made with dressed lumber.
Bridges for vehicle traffic shall be a minimum of twelve feet (12') in width,
skid resistant and structurally able to withstand an AASHTO H-20 vehicle load.
Temporary bridges shall be installed over the trenches at all intersections
whenever excavation is in excess of one-half the street width. Bridges shall also
be provided at residential and commercial driveways for the safe access of
vehicle traffic onto public streets.
All temporary bridges over excavated trenches shall remain in place for
public safety and convenience during the duration of the work. At Contractor’s
risk, the bridges may be temporarily removed or relocated to accommodate the
work as approved by the Engineer.
Unless directed or indicated otherwise, plug or seal the ends of existing
pipes cut to install new pipe. As a minimum, provide temporary end covers to
prevent dirt from entering pipes that are to be reconnected. The cut ends of
abandoned pipes made of plastic, clay, Transite, concrete, or similar materials
shall be permanently sealed with a concrete plug extending at least two feet (2’)
into the cut pipe. Use Class “C” or Class “D” concrete per Standard Specifications
Section 10-5. Cut ends of abandoned steel pipes may either be plugged with
concrete as above, or sealed by welding quarter inch (¼”) thick steel plates onto
each end. Cut ends of abandoned pipe that will be removed do not require
permanent seals.
When active water mains must be cut, Contractor shall anticipate that
existing water system valves do not seal drip tight, and thus pipes downstream
of existing valves may become pressurized. Seal the cut ends of active water
mains with watertight 150 psi pressure rated end caps suitable for potable
water use. Pressure rated end caps shall be left in-place until the cut pipe is
restored, or the Engineer determines that the cut pipe is fully isolated and thus
is no longer an active main. If end caps are removed from water mains to be
abandoned, plug the exposed ends as described above.
Contractor shall be responsible for the control, removal, and disposal of
any groundwater that may be encountered in the course of excavating and
backfilling trenches or placing pipe. Whenever water or over-saturated soil
conditions exist which may interfere with proper installation, trenches shall be
dewatered before placement of any pipe or material. Unless approved in writing
by the Engineer, groundwater and/or water from trench dewatering shall be free
of sediment and other construction materials before entering the City storm
27-5
drain system. A dewatering plan, including a water de-sedimentation plan, shall
comply with Section 16-1 of these Standard Specifications and be approved by
the Engineer prior to any discharge of water to the City’s storm drain system.
27-4 LAYING WATER PIPES
1. General
Contractor shall take all appropriate measures to prevent any type of
foreign material or animals from entering the pipe while the water pipe is being
placed. Contractor shall clean the inside of the pipe as directed by the Engineer.
Pipe for water mains shall not be placed during inclement weather or
when the conditions in the trench will interfere with proper jointing of the pipe
as determined by the Engineer. Whenever the work of placing the water main is
discontinued and at the end of each workday, all open ends of water main pipe,
fittings and valves at the pipe end shall be sealed. The seal shall be water tight
and shall be easily installed and removed. The trench shall be temporarily
backfilled to completely cover the seal.
All metallic pipe and fittings shall be wrapped with eight (8) mil
polyethylene material in accordance with AWWA Standard C105/A21.5.
Polyethylene shall be installed in accordance with the requirements of Section
27-17 “Corrosion Monitoring” in these Standard Specifications.
Pipe for the project shall not be stockpiled within public street right-of-
way along the alignment of the water transmission main in excess of an amount
representing a five (5) day supply at current rates of pipe laying, and shall never
exceed a maximum length of five hundred feet (500') unless otherwise indicated
in the Special Provisions. Stockpiling of pipe on the opposite side of the street
from construction shall not be allowed without the approval of the Engineer.
Each section of pipe and each fitting shall be thoroughly cleaned before
it is installed. All pipes, valves, fittings, and appurtenances shall be lowered into
the trench in such a manner as to prevent any damage, particularly to the pipe
lining and coating. Under no circumstance shall pipe or appurtenances be
dropped into the trench.
The pipe shall be laid true and uniform to line and grade, with no visible
change in alignment at any joint unless a curved alignment is shown on the Plans,
in which case the maximum deflection at any joint shall not exceed two-thirds
() the manufacturer’s recommendation for the type of pipe and joint being
used.
27-6
All pipe jointing, including the deflection at joints in curved alignments,
shall be in accord with accepted best practice and as detailed herein and in the
manufacturer’s installation manual. Both joint surfaces shall be clean before
joints are made. Materials used to join the pipe shall only be that furnished with
the pipe or recommended by the manufacturer.
When field cutting pipe, the cut ends shall be cut square and all burrs
removed from the pipe interior. The beveling of the pipe ends shall be as
specified by the manufacturer. Guide marks for jointing the pipe, after cutting,
shall be made on the pipe in accordance with the manufacturer’s
recommendations.
Contractor shall prevent undue pipe deflection and/or unit loading during
pipe handling. Damage to the pipe lining or coating shall be repaired by
Contractor in accordance with the manufacture’s recommendations as directed
by the Engineer
2. Rubber Gasket Joints
The joining of lengths of pipe with rubber gasket joints shall be performed
in the following sequence and in accordance with the pipe manufacturer’s
recommendations:
a. The spigot groove, inside bell sealing surface and rubber O-ring
gasket shall be thoroughly cleaned.
b. The above-cleaned surfaces shall be thoroughly lubricated with a
soft, vegetable soap compound.
c. The gasket shall be uniformly stretched while placing it in the
spigot groove to assure a consistent volume of rubber distributed
uniformly around the circumference.
d. The pipe shall be joined by a firm horizontal push without binding.
e. A feeler gauge shall be inserted between the bell and spigot to
check the position of the rubber gasket around its periphery. If the
gasket is in an improper position, it shall be removed, inspected,
reassembled, and rechecked.
3. Field Welding of Pipe Joints
Field welding of pipe joints for welded steel pipe and concrete cylinder
pipe shall be performed in accordance with the requirements of AWWA C206,
27-7
AWSD 7.0 “Field Welding of Steel Water Pipe Joints” and Standard Drawings W-
904 and W-903 in Section 38 of these Standard Specifications.
All welding, whether done in the shop or in the field, shall be performed
by experienced and skilled operators familiar with the methods and materials to
be used. Welding operators and welding procedures for all manual welding of
joints and fittings shall be qualified in accordance with the standard
qualifications procedure of Section IX of the ASME Boiler and Pressure Vessel
Code. Welder operators shall be certified for three position welding in
accordance with AWWA, ASME or other similar three position root bend test
method of qualification.
All shop and field welding shall be performed by the submerged or
shielded electric arc method unless specified in the Special Provisions. The
minimum number of passes for welded joints shall be as follows:
Steel Cylinder
Thickness (inches)
Minimum Number of
Passes for Welds
Less than 0.25 2
Equal to or greater
than 0.25
3
Welds shall be full circumferential and shall be done in passes no more
than one-quarter inch (¼") in thickness. Welding electrodes shall comply with
the requirements of American Welding Society A5.1 or A5.5. Size and type of
electrodes and the magnitude of the voltages and currents used shall be
consistent with methods, materials, and loads to be resisted.
Artificial cooling of the weld area during welding or quenching the
completed weld is not permitted. The Engineer will have the option of
requesting welding sample coupons for testing. The tests shall show the weld
strength to be at least equal to the strength of the plates being welded to be
acceptable.
Particular attention shall be given to the alignment of edges to be joined
to allow complete penetration and fusion throughout the full depth of the weld.
Welds shall contain no undercuts or valleys in the center or at the edges of the
weld. Each weld pass shall be thoroughly cleaned of dirt, slag, and flux before
each succeeding weld bead is applied.
Completed field welds of pipe joints shall be cleaned of dirt, slag and flux,
and then visually inspected. Subject to the approval of the Engineer, all porosity
and cracks, trapped flux, or other defects in the welds, discovered during
inspection, shall be completely chipped out in a manner that shall allow proper
27-8
and complete repair by re-welding. Under no circumstances shall caulking of
defective welds be permitted.
4. Cement Mortar Joint Finish
Following satisfactory testing of the welds, the interior of all joints shall
be cement mortar lined and the exterior of the joints shall be cement mortar
coated in accordance with AWWA C205 for welded steel pipe and AWWA C303
for concrete cylinder pipe.
The application of cement mortar to the joints on the exterior of the pipe
shall be made after the pipe is adequately bedded. Interior joints shall be
mortared after initial backfill is in place or after pipe is secured in or on a
structure.
To minimize annular shrinkage cracks due to temperature change,
exterior joints shall be poured when the pipe is cool. Water jetting to cool the
pipe shall be done when the joint mortar is still in a plastic state and is protected
from washing by canvas or impervious joint wrapping.
Cracks occurring in interior or exterior joint mortar shall not exceed four
hundredths of an inch (0.04”). Where cracks exceed this limit, they shall be
removed to the metal to a width of at least three eights inch (⅜”) and new
mortar set in.
a. Exterior Joints
After cleaning, a sail cloth band with three eighths inch (⅜”) wide
steel box strapping attached to the two long ends shall be placed around
the pipe outside and centered over the joint with the band, opening for
grout on the pipe top. The strapping band shall fit snugly around the pipe.
The cement mortar shall consist of one (1) part Portland Cement to
two (2) parts sand mixed to a consistency of thick fluid cream. After the
joint is moistened, the cement mortar shall be poured into the joint recess
on one side, rodded, if necessary, until it appears on the opposite side,
then the remainder shall be poured. Portland Cement shall meet the
requirements of Section 10 of these Standard Specifications.
The cement mortar shall completely fill the outside joint exposed
metal annular space. Upon completion, the joint cover shall be placed
over the opening and the mortar allowed to set.
27-9
b. Interior Joints
The cement mortar shall consist of one (1) part Portland Cement
and one and one-half (1½) parts sand, dry mixed and wetted with
sufficient water to permit caulking and troweling without crumbling or
sloughing. Sufficient time shall be allowed for curing prior to use.
Portland Cement shall meet the requirements of Section 10 of these
Standard Specifications.
For pipe less than twenty-two inches (22”) in diameter cement
mortar shall be placed in the inside recess prior to joining the pipe. After
each new length of pipe has been placed in final position, a ball shall be
pulled through the joint in order to smooth the mortar at the joint. This
procedure is not necessary if a hand hole is used to mortar the joint.
For pipes greater than or equal to twenty-two inches (22”) in
diameter, cement mortar shall be placed in the inside of recess while
working inside the pipe. Foreign substances which adhere to the steel
joint rings shall be removed, the surface cleaned, and stiff cement mortar
packed into each joint. The mortar shall be finished with a steel trowel
to match the lining in the adjoining pipes. Excess mortar and other
construction debris shall be removed from the pipe interior.
Closure assemblies shall be cement-mortar lines to a mortar
thickness at least equal to the adjoining standard pipe sections. The steel
shall be cleaned with wire brushes and a cement and water wash coat
applied prior to applying the cement mortar. Where more than a 4-inch
joint strip of mortar is required, welded wire mesh reinforcement having
a 2-inch by 4-inch pattern of No. 13 gage shall be placed over the exposed
steel. The mesh shall be installed so that the wires on the 2-inch spacing
run circumferentially around the pipe. The wires on the 4-inch spacing
shall be crimped to support the mesh 3/8 inch from the metal surface.
The interior mortar shall have a steel-troweled finish to match adjoining
mortar lined pipe sections.
5. Cleanup-Up Behind Pipe Laying Operations
Contractor shall maintain cleanup operations in pace with pipe laying.
Concurrently with or immediately after placing a temporary bituminous surface
within paved areas, or the placing of backfill in unpaved locations, all areas
affected by Contractor’s operations shall be restored to their original conditions
(except for final repaved surfacing) and left in a neat and orderly condition.
Paved areas shall be swept with a power broom and then flushed with
water.
27-10
Excavations at locations of valves, blow-offs, air relief valves, and tie-in
connections shall not be left open without the Engineer’s written permission.
Replacement of removed improvements or repairs to damaged or
disturbed real property or improvements shall be performed concurrently with
the cleanup work.
Failure to perform the above work in pace with the forward trenching
progress shall be sufficient cause for the Engineer to order Contractor to stop
trenching until the Engineer has determined that the work has been caught up.
27-5 PLACING LOCATING WIRE WITH DISTRIBUTION MAINS
All runs of distribution mains (4" to 12") including metal and plastic shall
have a locating wire taped to the top of the pipe to facilitate location after
installation, as shown on Standard Drawing W-102 in Section 38 of these Standard
Specifications. The locating wire shall be a No. 10 gauge copper wire insulated
with high molecular weight polyethylene (HMWPE), blue in color, and suitable
for direct burial.
27-6 THRUST BLOCKING AND RESTRAINED JOINTS
1. Distribution Main (4"-12")
All plugs, caps, tees, or bends with a deflection greater than eleven and
a quarter degrees (11¼°) shall be provided with concrete thrust blocks installed
as detailed on Standard Drawing W-103. Nuts or bolt heads of bolted connections
shall not be covered by concrete or form materials. The thrust block shall extend
from the fitting to undisturbed soil.
Deadman thrust assemblies shall not be allowed without prior approval
from the Engineer.
Mechanically restrained joints may be used in lieu of concrete thrust
blocks when approved by the Engineer and shall be the type recommended by
the manufacturer of the pipe.
2. Transmission Mains (Greater than 12")
Contractor shall submit to the Engineer for approval, calculations for
minimum lengths of restrained pipe where there is unbalanced hydraulic thrust,
such as at abrupt changes in horizontal and/or vertical alignment, at tees, valves
and caps. Thrust restraint calculations shall be based on an internal test pressure
of two hundred and twenty-five pounds per square inch (225 psi). Any
27-11
demarcations of restrained joint requirements on the Plans indicate only possible
segments for restrained pipe joints. Contractor is responsible for verifying the
necessity of and minimum lengths for restrained joints. Concrete thrust blocking
is not allowed.
Joints shall be restrained when deflection of the pipe at the joint exceeds
two-thirds () manufacturer’s recommendation. Transmission mains constructed
of welded steel pipe or concrete cylinder pipe shall be restrained by field welding
the joints. Ductile iron pipe shall be restrained with Field Lok Gaskets, TR Flex,
or an approved equal.
Thrust restraints for fittings, elbows, reducers, in-line valves,
appurtenances, etc., shall be provided by means of restrained pipe joints,
utilizing pipe skin friction for horizontal restraint, and dead load for vertical
restraint (uplift). In-line valves shall be considered as a dead end main for thrust
restraint calculations. Thrust forces shall be calculated using the internal
diameter of the pipeline. Skin friction shall be calculated with allowance for
pipe dead and live load. Earth load above the pipe when backfilling prior to
testing, and a friction coefficient incorporating the properties of the actual
backfill materials shall be used.
The friction coefficient shall not exceed 0.25 for C200 and C303 unless a
geotechnical evaluation is submitted. In no case shall the friction coefficient
exceed 0.30. For polyethylene encased ductile iron pipe, only skin friction
between the encasement and the pipe shall be considered with no allowance for
soil cohesion or the internal friction angle of the soil. The skin friction for
polyethylene wrapped ductile iron pipe shall be reduced thirty percent (30%) to
a maximum of 0.17 unless Contractor submits a geotechnical evaluation.
27-7 APPURTENANCES
1. General
Appurtenances shall comply with the material requirements of Section 10
of these Standard Specifications and shall be installed per the manufacture’s
recommendations. All new valves and hydrants to open counter-clockwise.
Appurtenances shall be installed at elevations and locations as shown on
the Plans. The joints between the main pipe and side fittings shall be restrained
in compliance with the Plans, Special Provisions, and these Standard
Specifications. The trench bottom shall be graded uniformly to provide a level
base for the fittings and minimize torsional strain when the backfill is placed.
On transmission mains, insulated flanged joints shall be provided at every
butterfly valve, gate valve, flanged outlet, at each tie-in connection, at fire
hydrant connections, at air release valves, at blow-off connections, at intervals
of two thousand five hundred feet (2,500') along the water main pipe, and/or as
27-12
otherwise indicated on the Plans. Insulated joints shall be installed in accordance
with the requirements of Section 27-17, “Corrosion Monitoring”, and Standard
Drawings W-902 and W-905 in Section 38 of these Standard Specifications.
Polyethylene material with a minimum thickness of eight (8) mil shall be
placed around the exterior of the appurtenances in accordance with AWWA
Standard C105/A21.5. Polyethylene shall be installed in accordance with the
requirements of Section 27-17, “Corrosion Monitoring”.
2. Fire Hydrants
In no case shall a fire hydrant be installed within three feet (3') of a
building or any other structure that would limit access. All hydrants shall be set
plumb and installed and located in accordance with Standard Drawing W-201 in
Section 38 of these Standard Specifications.
Only ductile iron or polyvinyl chloride pipe shall be used as branch leads
that connect fire hydrants to water mains.
Where the Plans indicate that existing fire hydrants are to be removed
and salvaged, the salvaged hydrants shall be removed intact and delivered
undamaged to the Corporation Yard as directed by the Engineer.
Fire hydrants placed at street intersections shall be installed at the
beginning or end of round corners (curb returns) and not be positioned along the
arc of the round corner.
Only one six inch (6') or twelve inch (12') fire hydrant extension kit per
hydrant shall be allowed. Contractor shall meet the bury depth requirements by
use of forty five degree (45
o
)
fittings.
3. Gate Valves
All gate valves shall be restrained in both directions.
Value operating nut extensions are required in accordance with Standard
Drawing W-308 in Section 38 of these Standard Specifications when valve nut is
in excess of thirty inches (30") below finished grade.
Contractor shall carefully place valve into position, avoiding contact or
impact with other equipment, or trench walls. The pipe ends shall be prepared
in accordance with the manufacturer’s instructions. The water main shall be
properly supported to avoid line stress on valve. The pipe/valve joint shall not
be deflected nor shall the valve be used as a jack to pull the pipe into alignment.
27-13
4. Backflow Prevention Assemblies and Swing Check Valves
The City maintains a backflow prevention and cross-connection control
program in accordance with the requirements of Title 17 of the California
Administrative Code. Backflow prevention assemblies shall be installed in
accordance with the appropriate Standard Drawings in Section 38 of these
Standard Specifications (Drawing Numbers W-501 thru W-511 and W-601 thru W-
607). The backflow prevention assembly must be installed such that the device
is readily accessible for testing and maintenance, and shall be located as close
as practical to the point of service delivery (meter).
The City of Sacramento Department of Utilities maintains a list of
approved assemblies. Only assemblies that appear on this list are acceptable for
installation. Assemblies shall be shipped from the manufacturers in the fully
assembled configuration. This includes bypass arrangements and shutoff valves.
Assemblies received for installation not completely assembled are not approved.
Field conversions of double check assemblies to a detector assembly, or vice
versa, are not permitted.
The City of Sacramento’s requirements for designing, constructing,
installing, and maintaining backflow prevention assemblies is found in the Cross
Connection Control Policy of Department of Utilities. Copies of the “Cross
Connection Control Policy” are available from the Department of Utilities
Customer Service at 1395 35th Avenue. Following acceptance of the installation,
the device must be performance tested at the owner’s expense by a certified
tester selected from the City approved list.
All assemblies shall be installed to provide protection from vandalism and
freezing. Cages must be installed so that adequate clearance is available for
maintenance and testing or it should be completely removable and allow for any
discharge from the relief valve to fully drain from the protective cage or cover.
As a minimum, backflow prevention assemblies shall be sized equivalent
to the diameter of the service connection. The installation of backflow
prevention assemblies shall be aboveground.
5. Blow-Offs
a. Distribution Mains
Standard two inch (2") and four inch (4") blow-offs shall conform to
and be installed in accordance with Standard Drawing W-301 in Section 38
of these Standard Specifications.
b. Transmission Mains
27-14
Blow-offs shall be six inches (6") in size and shall conform to and be
installed in accordance with Standard Drawings W-804 or W-805 in Section
38 of these Standard Specifications.
6. Butterfly Valves
Butterfly valves shall conform to and be installed in accordance with
Standard Drawing W-801 in Section 38 of these Standard Specifications.
Value operating nut extensions are required in accordance with Standard
Drawing W-308 in Section 38 of these Standard Specifications when valve nut is
in excess of thirty inches (30") below finished grade.
Contractor shall carefully place valve into position, avoiding contact or
impact with other equipment, or trench walls. The pipe ends shall be prepared
in accordance with the manufacturers instructions. The water main shall be
properly supported to avoid line stress on valve. The pipe/valve joint shall not
be deflected nor shall the valve be used as a jack to pull the pipe into alignment.
7. Combination Air Vacuum and Release Valves
Combination air vacuum and release valves shall be two inches (2") or four
inches (4") in size, as indicated on the Plans. Installation of air vacuum and
release valves shall conform to and be installed in accordance with Standard
Drawings W-802 and W-803 in Section 38 of these Standard Specifications.
8. Flexible Couplings and Flanged Coupling Adaptors
a. Transmission Mains
The flexible couplings shall be installed with provision for thrust
restraint ties attached to the water main pipe. The thrust restraint ties
on the pipe shall be welded lugs, lugs cast integrally with the pipe, or
friction collars. Anchor studs placed perpendicular to the long axis of the
pipe are unacceptable. Resistance to hydraulic thrust shall be adequate
to sustain a force developed by a test pressure of two hundred and twenty-
five pounds per square inch (225 psi).
Flanged coupling adapters shall be provided with thrust ties
attached to the pipe with welding lugs, cast-in-place lugs, or friction
collars. Lugs shall have a minimum thickness equal to that of adjacent
flange and shall have holes the same size as those on the flange. Anchor
studs placed perpendicular to the longitudinal axis of the pipe are
unacceptable.
27-15
Contractor shall ensure that the pipe is in proper alignment.
Contractor shall clean all dirt, rust, oil or loose scale from pipe ends for a
distance of two inch (2") greater than the length of the flanged coupling.
Contractor shall check area where gaskets will seat on pipe and flange
faces to make sure there are no dents, projections, gouges, etc. that will
interfere with the gasket seals. Welds must be ground flush. Bolt
tightening should be done evenly, alternating to diametrically opposite
positions to bring bolts to recommended tightness.
b. Distribution Mains:
Flexible couplings shall be installed with provisions for thrust
restraint.
9. Mechanical Joints
Contractor shall thoroughly clean socket and plain end of all rust
or foreign material. The socket, gasket and plain end shall be lubricated
with soapy water or an approved pipe lubricant meeting requirements of
AWWA C111. The bolts shall be tightened to draw gland toward the pipe
flange evenly, maintaining approximately the same distance between the
gland and the face of the flange at all points around the joint using torque-
measuring wrenches.
10. Valve Boxes
Valve boxes shall be furnished and installed in accordance with
Standard Drawings W-303, W-304, and W-306 in Section 38 of these
Standard Specifications.
11. Access Manholes
Installation of access manholes shall conform to and be installed in
accordance with Section 25 and Standard Drawing W-702 in Section 38 of
these Standard Specifications
27-8 PIPE BEDDING AND BACKFILLING OF TRENCHES
Pipe bedding and initial backfill for water mains, fire hydrant branch
leads, and water services shall be furnished and placed according to the
requirements contained herein and as detailed on Standard Drawing W-701 in
Section 38 of these Standard Specifications. The pipe bedding and initial backfill
material shall consist of sand meeting the requirements as given in Section 10-
27-16
13 of these Standard Specifications unless otherwise specified in the Special
Provisions.
Bedding material shall be placed and compacted along the bottom of the
trench to provide uniform support for the water main pipe at every point
between the joints. Support of the pipe by wedging or blocking shall not be
permitted. At the location of each joint, holes of adequate size shall be provided
in the bottom and sides of the trench to permit easy joint preparation, pipe
assembly, and visual inspection of the entire joint.
Initial backfill shall be placed immediately after pipe joints have been
completed, inspected, and passed by the Engineer. Trench backfill shall be earth
material, unless otherwise specified in the Special Provisions, placed and
compacted above the granular bedding and initial backfill material to the level
of the subgrade in paved areas or to the top of the trench in unpaved areas.
Backfill shall be provided by Contractor and shall be placed in accordance with
Section 14-3 of these Standard Specifications and the pipe manufacturer’s
recommendations.
Imported granular material may be used to backfill pipe trenches in place
of job excavated native material. The imported granular material placed above
the initial backfill shall be uniformly graded Class 2 aggregate base, meeting the
requirements of Section 10-7 of these Standard Specifications. Compaction and
placement requirements for imported granular material shall be the same as
required for compaction of job excavated native material.
Full depth select or imported backfill will be required under the
following circumstances:
1. At locations where over excavation is required, i.e., butterfly
valves, blow-offs, system tie-in connections, insulated joints, etc.
2. At locations where pipes for sewage or drainage cross above the
water transmission main pipe.
3. In areas where the trench section is of unusual configuration.
4. Jacking and receiving pits for the boring and jacking of pipe
casings.
Full depth select backfill shall be placed in layers not exceeding eight
inches (8”) in depth and shall extend to the level of subgrade road subbase and
to undisturbed earth on the sides. Compaction and placement requirements for
full depth select backfill shall be the same as required for compaction of job
excavated native material. Unless otherwise specified on the Plans or Special
27-17
Provisions, full depth select backfill material shall consist of sand, Class 2
aggregate base or controlled density fill (CDF) meeting the requirements of
Section 10 of these Standard Specifications.
27-9 REPAVING WATER PIPE TRENCHES
Repaving of trenches for water mains, fire hydrant branch leads, and
water services shall be as specified in this Section of these Standard
Specifications unless otherwise indicated on the Plans or in the Special Provisions
Contractor shall restore all surfaces, which have been removed or
damaged by Contractor in kind, using the same material as existing, unless
otherwise noted on the Plans or in the Special Provisions. The repaving is to be
done in such a manner to, as closely as possible, replace the cut pavement with
a similar type and an equal or greater structural section.
Upon completion of trench backfill, existing pavement as well as any
curbs, gutters and sidewalks that have been cut or damaged as a result of the
construction activities shall be replaced. The replacement of pavement, curb,
gutter or other improvements shall match that of the original as close as practical
unless otherwise indicated on the Plans. Segments of pavement that were
damaged during construction shall be cut to a neat straight line. To form the
required “T” trench, the existing pavement shall be ground or saw cut an
additional six inches (6”) outside the excavated area prior to paving. The
minimum pavement section within public street right-of-way shall be four inches
(4") of asphaltic concrete over twelve inches (12") of Class 2 aggregate base
unless otherwise noted on the Plans or in the Special Provisions.
Aggregate base for repair and/or replacement of existing pavement shall
meet the requirements for Class 2 aggregate base as contained in Section 10 of
these Standard Specifications. Aggregate base shall be placed and compacted in
accordance with Section 14 of these Standard Specifications, except that it shall
be compacted to a relative compaction of not less than ninety-five percent (95%)
as measured by tests specified in Section 14 of these Standard Specifications.
Asphaltic concrete pavement and its placement shall conform to the
requirements of Section 22 of these Standard Specifications.
Restoration of existing concrete pavement shall consist of at least six
inches (6") of concrete and shall conform to the requirements of Section 19.
Concrete surfaces to be replaced shall be colorized, as necessary, to match
existing adjacent concrete color by the addition of Lamp Black coloring agent.
Contractor shall submit concrete mix design for approval including a proposed
proportion of coloring agent appropriate to the shade of adjacent concrete.
27-18
Where entire alley requires replacement, concrete shall not include coloring
agent, unless directed by the Engineer.
Concrete used in the repair and/or replacement of curb, gutter, or
sidewalk shall conform to Section 24-1 of these Standard Specifications.
Concrete used in the replacement of existing concrete “V” gutter or pavement
shall be Class “A” concrete in accordance with Section 10 of these Standard
Specifications. Placement of concrete shall conform to the requirements of
Section 24 of these Standard Specifications.
Where less than two feet (2') of existing pavement is left between the
edge of the trench and the lip of concrete gutter or pavement edge, the narrow
strip of existing pavement shall be removed and the area repaved along with the
area overlying the trench. All existing asphaltic concrete or concrete pavement
adjacent to the pipe trench that has been loosened, cracked, or damaged as a
result of Contractor's operations shall be removed and replaced.
Unless otherwise provided on the Plans or in the Special Provisions,
pipeline trenches in unpaved portions of street rights-of-way shall have the top
twelve inches (12") filled with aggregate base Class 2, conforming to Section 10
of these Specifications and compacted to ninety-five percent (95%) relative
compaction as determined by ASTM Designation D1557.
All pavement debris and other excavated material not destined to be used
for backfill shall be removed and disposed of outside the limits of the project at
Contractor's expense.
27-10 WATER SERVICES
Materials for services shall meet the requirements specified in Section 10
and shall be installed in accordance with the Standard Drawings. All new and
reconnected services shall be metered.
The location of water services extending beneath curbs, gutters and
sidewalks shall be denoted by imprinting a two inch (2") size Gothic letter “W”
on the upper face of the curb, unless otherwise directed by the Engineer.
Service saddles for one inch (1"), one and a half inch (1½") and two inch
(2") services shall be installed in accordance with Standard Drawing W-403 in
Section 38 of these Standard Specifications. Three inch (3") services are not
allowed. A three inch (3") meter shall be installed on a four inch (4") tap. Tapping
sleeves for services four inch (4") and larger shall have a stainless steel sleeve
and stainless steel flange.
27-19
Gate valves for water services four inches (4") and larger in diameter shall
be installed at the main with a flanged connection and shall include a valve box
and riser. Boxes and risers shall be as specified in and installed in accordance
with Standard Drawing W-303 in Section 38 of these Standard Specifications.
No hydrant branch lead, services or fitting (tee, ell, etc.) shall be tapped
to accommodate any service.
27-11 WATER TAPS TO NEW AND EXISTING MAINS
Prior to scheduling taps on new or existing water mains, Contractor shall
provide the Engineer a copy of a bacteriological report showing that all piping
including on-site fire services, private fire hydrants, and domestic services meet
the requirements of these Standard Specifications.
Water taps on new mains prior to being accepted by the City shall be made
by Contractor. Water taps on existing City mains shall only be made by City crews
at Contractor’s expense.
For any given project, a maximum of two (2) water main shutdowns, water
main tie-in connections (tap or “cut-in”), or combination thereof directly
involving work by the City crews, shall be scheduled per day. Such work
performed by City crews will be between 9:00 am and 3:00 pm. Modification to
this procedure may be requested by Contractor and will be considered on a case-
by-case basis with the final determination to be made by the Engineer.
Contractor shall notify the Engineer that a shutdown is required and the
City will schedule the shutdown within five (5) working days of notification. The
Engineer will notify Contractor of the time of shutdown at least two (2) working
days prior to the shutdown. Contractor shall excavate around the water main,
per Standard Drawing W-404, twenty-four (24) hours prior to the City tapping the
water main.
Any change made to the vertical and horizontal alignment of water
services shall be made behind the sidewalk and outside the City right-of-way.
Within the City right-of-way the water services shall be installed perpendicular
to the main.
27-12 DISINFECTION OF WATER MAINS
1. General
The intent of this section is to present procedures essential for the
disinfection of newly constructed water mains and appurtenances. No new mains
shall be connected to existing mains until they have been disinfected in
27-20
accordance with this section, and pressure tested in accordance with Section 27-
13 in these Standard Specifications. All disinfection and testing shall be made in
the presence of the Engineer. The basic procedure consists of the following:
a. Preventing contaminating materials from entering the water mains
during construction.
b. Disinfecting any residual contamination that may remain.
c. Determining the bacteriological quality by laboratory testing after
disinfection.
Contractor shall furnish all hoses, pumps, gauges, connections, valves,
other necessary apparatus, and personnel required for disinfecting, flushing, and
disposal of chlorinated water.
Precautions shall be taken to protect pipe interiors, fittings, and valves
against contamination during the construction of the water system.
Chlorination and testing of the pipeline shall be in accordance with AWWA
C 651 with the following exception: the first bacteria sample after flushing the
main is not required. Water distribution mains up to and including twelve inches
(12") in diameter shall be disinfected using the Tablet Method or Continuous-
feed Method described in AWWA C 651. Water transmission mains eighteen inches
(18”) in diameter and greater shall be disinfected using the Continuous-feed
Method described in AWWA C 651.
Disinfecting the pipeline may be performed concurrently with the
hydrostatic testing in accordance with Section 27-13. In the event repairs are
necessary, as indicated by the hydrostatic test, additional disinfecting may be
required as directed by the Engineer.
2. Tablet Method
The Tablet Method shall employ the use of a sufficient number of calcium
hypochlorite tablets as a disinfectant to yield an average chlorine dose of
approximately twenty-five milligrams per liter (25 mg/l). The five-gram (5g)
calcium hypochlorite tablets shall contain at least sixty-five percent (65%)
available chlorine by weight. These tablets shall meet the requirements of AWWA
B 300, standard for hypochlorites.
Because preliminary flushing cannot be performed when tablets are used,
cleanliness must be exercised during construction of the water main.
27-21
The calcium hypochlorite tablets shall be placed in each section of pipe
and also in hydrants, hydrant branches and other appurtenances. They shall be
attached by an adhesive at the top of the pipe to prevent washing to the pipe
end. If the tablets are fastened before the pipe section is placed in the trench,
their position shall be marked on the section to assist in keeping the tablet’s
position at the top of the pipe.
Number of 5 Gram Calcium Hypochlorite Tablets*
Pipe Diameter
(Inches)
Length of pipe section (feet)
13 or
less
18 20 30 40
4
1
1
1
1
1
6
1
1
1
2
2
8
1
2
2
3
4
10
2
3
3
4
5
12
3
4
4
6
7
*Based on 3.25 grams of available grams of chlorine
per tablet. Any portion of tablet rounded to next
highest number.
The adhesive shall be Permatex No. 1, or approved equal. There shall be
no adhesive on the tablet except on the broad side next to the surface to which
the tablet is attached. The number of calcium hypochlorite tablets required for
main disinfections shown by the table above.
3. Continuous Feed Method
The continuous feed method consists of completely filling the main to
remove all air pockets, flushing the completed main to remove particulates, and
filling the main with chlorinated potable water so that after a twenty four (24)
hour holding period in the main there will be a free chlorine residual of not less
than ten milligrams per liter (10mg/l) at all locations in the main.
Prior to being chlorinated the main shall be filled to eliminate air pockets
and shall be flushed to remove particulates. The Flushing velocity in the main
shall be not less than two and a half feet per second (2.5fps) unless otherwise
directed by the Engineer.
A chlorine-water solution shall be applied by means of a solution feed
chlorinating device. Care shall be taken to prevent the highly chlorinated water
in the pipeline being treated from flowing back into the pipeline supplying the
water. At a point not more than ten feet (10’) downstream from the beginning
of a new main, the concentrated chlorine solution shall be pumped into the main
27-22
at a uniform feed rate until the desired chlorine residual (at least 25mg/l) is
measured in the flushed water at the terminal outlet. Chlorine application shall
not cease until the entire main is filled with chlorinated water. If at any time
the application of chlorine is interrupted, the flow of water shall be stopped
until chlorine application is resumed.
4. Pipeline Filling
Before filling the pipeline, Contractor shall:
a. Remove any and all residual water from the entire pipeline to be
tested.
b. Open all air vents.
c. Furnish a double check valve assembly to make a single supply
connection for testing. Installation of the double check valve
assembly shall be in accordance with Standard Drawing W-107 in
Section 38 of these Standard Specifications. A double check valve
assembly hook-up to the City water system must be approved by
the Engineer prior to water use. The double check valve assembly
shall be approved by a certified tester. The certification tags shall
be displayed on the double check valve assembly after approval.
Each section of the pipe to be disinfected shall be slowly filled with water
at a velocity of less than one foot per second (1fps), and all air shall be expelled
from the pipe. The release of the air can be accomplished by opening fire
hydrants and service line cocks at the high points of the system and blow-offs at
all dead ends. If required, Contractor shall provide a corporation stop at high
points to provide air vents and insure that all air is released. The valve controlling
the admission of water into the section of pipe to be disinfected should be
opened wide before shutting the hydrants or blow-offs. After the system has
been filled with water and all the air expelled, all the valves controlling the
section to be tested shall be closed.
5. Disinfection, Flushing and Testing
The disinfection, flushing and testing sequence shall be as follows:
a. Chlorination and testing of the pipeline shall be in accordance with
AWWA Standard C651 with the following exception: the first
bacteria sample after flushing the main is not required.
b. The heavily chlorinated water shall be retained in the main for at
least twenty-four (24) hours, during which time all valves and
27-23
hydrants shall be operated to ensure disinfection of the
appurtenances. At the end of the twenty-four (24) hour period,
the main shall have a residual of not less than ten milligrams per
liter (10 mg/L) of free chlorine or the disinfection procedure shall
be repeated using the continuous-feed or other method described
in AWWA C651 as directed by the Engineer.
c. Contractor shall flush the main until the chlorine residual is less
than one part per million (1.0 ppm) or matches distribution system
chlorine residual level and turbidity is less than one nephelometric
turbidity unit (1.0 NTU). The chlorinated water shall be flushed
from the system at its extremities and at each appurtenance, using
potable water from a source designated by the Engineer. The
minimum water velocity during flushing shall be two and a half feet
per second (2.5 fps) or as directed by the Engineer. Temporary
inlets/outlets shall be sized to provide adequate velocity to flush
the main. The minimum inlet/outlet size shall be two inches (2”)
in diameter.
d. Samples will be collected at locations along the pipeline identified
by the Engineer. Contractor shall notify the Engineer at least
twenty-four (24) hours in advance of the time that the
bacteriological samples are to be drawn for testing. Contractor
shall furnish and install temporary sampling devices in accordance
with Standard Drawing W-302 in Section 38 of these Standard
Specifications at the locations indicated by the Engineer spaced no
greater than twelve hundred feet (1200') apart.
e. Twenty-four (24) hours after flushing the chlorinated water from
the main the Engineer will collect samples for testing.
f. Bacteriological examination of the samples shall meet the following
criteria:
i. Total Coliform absent
ii. Total Plate Count less than five hundred (500) colony
forming units per milliliter
Re-disinfection, if required due to test failure, shall be performed by
Contractor at Contractor’s expense. Cost to retest the water will be at
Contractor’s expense.
27-24
The water shall meet State and Federal drinking water standards; Title
22, California Administrative Code and the Safe Drinking Water Act of 1974, as
amended.
6. Disposal of Chlorinated Water
After disinfection of the system and prior to coliform bacteria and
turbidity testing, chlorinated water shall be disposed of such that water does not
flood, inundate or damage property. Contractor shall dechlorinate the water by
use of apparatus that injects or mixes EPA approved chemicals with the water to
neutralize the chlorine before it is hard piped to a manhole on the nearest storm
or sanitary sewer system. Residual chlorine levels shall be reduced and
maintained to a maximum of one hundredth of a milligram per liter (0.01 mg/l).
Contractor shall test the discharge at fifteen minute (15) intervals to insure that
acceptable levels of neutralization are maintained. Discharge shall be stopped if
chlorine levels exceed one hundredth of a milligram per liter (0.01 mg/l).
Dechlorinating apparatus shall be the de-chlorinator by Romac Industries
or approved equal. All procedures shall be in accordance with manufacturer’s
recommendations and as approved by the Engineer.
27-13 PRESSURE TESTING WATER MAIN INSTALLATIONS
Following disinfection, Contractor may use the chlorinated water to
perform a hydrostatic pressure test of the system. Prior to making final tie-in
connections, the entire system shall be pressure tested by Contractor
independent of the existing system or systems to be connected.
Contractor shall furnish all hoses, pumps, pressure gauges, leakage
measuring devices, connections, relief valves, temporary pressure heads, other
necessary apparatus, and personnel required for hydrostatic pressure and
leakage testing. Pressure gauges shall register pressure in pounds per square
inch gauge (psig). The range of the gauge shall be from zero to two hundred and
seventy-five pounds per square inch gauge (0-275 psig). The gauge readings shall
have a five (5) psig incremental tick marks. The gauge shall be calibrated within
forty-five (45) days of the hydrostatic test and the calibration tag affixed to the
gauge.
In no case shall there be placement of permanent pavement prior to
successful completion of the test. Joints and fittings must be backfilled to the
springline of the pipe and the pipe between joints backfilled to a depth necessary
to hold the line securely during the test, but in no case less than eighteen inches
(18”) above pipe. Thrust blocks shall have been in place for at least thirty-six
(36) hours if high-early-strength concrete was used or at least seven (7) days if
standard concrete was utilized.
27-25
A hydrostatic test pressure of one hundred fifty pounds per square inch
gauge (150 psig) shall be maintained for 60 minutes. The allowable leakage
criterion is “zero”. No leakage, as represented by a measurable drop in pressure
below the starting test pressure, is allowed.
Contractor shall determine the cause of unacceptable leakage results,
take corrective measures, and conduct subsequent tests until the pipeline meets
the allowable leakage criteria. Contractor shall perform any excavation required
to locate and repair leaks or other defects that may develop during the test,
including removing backfill that has been already placed. The Engineer shall
witness the test and Contractor shall provide the Engineer a forty-eight (48) hour
notice prior to the test.
Contractor at his expense shall repair any leaks detected by visual
inspection regardless whether test results are acceptable.
Contractor shall take all necessary precautions to prevent joints from
drawing while the pipelines and their appurtenances are being tested. Any
damage to the pipes and their appurtenances, or any other structures, resulting
from or caused by these tests, shall be repaired by Contractor at Contractor’s
expense.
27-14 “CUT-IN” CONNECTION TO EXISTING WATER MAINS
Connection of new water mains to existing mains shall be made only after
the newly constructed water mains have been successfully disinfected and
pressure tested including onsite fire systems and domestic services.
Contractor shall furnish and install all pipe, fittings, and valve boxes
necessary to complete the “cut-in” as shown on Standard Drawing W-105 in
Section 38 of these Standard Specifications.
City crews shall perform all shutdowns of existing water mains. See
Section 27-11 for water main shut down procedure.
Contractor shall expose the existing water main at the “cut-in” locations
per Standard Drawing W-404 and shall have all material necessary to complete
work onsite at least one day prior to the scheduled “cut-in” to the satisfaction
of the Engineer. Contractor shall have all necessary manpower and equipment
ready at the time of the scheduled “cut-in” necessary to be able to complete
the “cut-in” within four (4) hours of the shutdown to the satisfaction of the
Engineer. Failure to comply with above-specified requirements shall result in the
cancellation of the scheduled shutdown.
27-26
New pipe, fittings and valves required for connection but not included in
the hydrostatic pressure testing and disinfection procedures shall be disinfected
prior to connection in accordance with AWWA Standard C651 relating to
“Connections Equal To or Less Than One Pipe Length”.
In the connection of new water mains to existing mains, any offset in
horizontal or vertical alignment between the exposed ends of new and existing
water main pipes that is six inches (6”) or greater shall be taken up by the use
of elbow fittings. Ninety degree (90°) elbows shall be used only with the
Engineer’s approval. Deflection of the pipe joints or the use of flexible couplings
shall not be permitted.
27-15 SETTING, ADJUSTING AND LOCATING VALVE BOXES
For all new water valves installed, Contractor shall furnish and install
valve boxes, covers, drop caps, and steel risers in accordance with Standard
Drawings W-303 and W-304 in Section 38 of these Standard Specifications. Unless
otherwise shown on the Plans, or specified in the Special Provisions, in
construction areas involving elevation changes or where existing valve boxes or
risers are disturbed, or as indicated on the Plans, Contractor shall furnish and
adjust to final grade all existing valve boxes in accordance with Standard
Drawings W-303, W-304 and W-306 in Section 38 of these Standard Specifications.
All non-steel risers shall be replaced with steel risers in accordance with
Standard Drawings W-303 and W-306 in Section 38 of these Standard
Specifications. When approved by the Engineer, Contractor may reuse existing
valve boxes that meet these Standards Specifications and are in an undamaged
condition.
All water valve boxes removed for subsequent reinstallation to allow
reconstruction of existing streets shall be temporarily replaced with a protective
metal container. The temporary container shall cover the riser over the valve
and will assist in keeping the location of the valve visible during street
reconstruction activities, the risers at each valve shall be kept free of debris and
the valve operating nut left exposed.
Prior to construction Contractor shall furnish locations or swing ties to all
existing valves within the streets to be resurfaced. A copy of the valve location
measurements shall be provided for the Engineer prior to any street construction
or resurfacing.
27-16 ADJUSTING AIR RELEASE VALVES
Contractor shall install new or adjust existing air valve box or manhole
head and cover in accordance with Standard Drawing W-802 in Section 38 of
these Standard Specifications.
27-27
All precast concrete sections used to construct the vaults or manholes for
air release valves shall be set in Portland Cement mortar or preformed plastic
sealing compound. The preformed plastic sealing compound and the mixing of
the mortar shall meet the requirements specified in Section 10-37 of these
Standard Specifications.
The interior and exterior surfaces of the joints of the precast concrete
sections shall be coated with Portland Cement mortar. The precast sections shall
be cleaned and moistened immediately prior to setting the sections in the
mortar. A moistened brush shall be used to apply and smooth the mortar to the
interior and exterior joint surfaces of the precast concrete sections.
27-17 CORROSION MONITORING
1. General
All metallic pipe and appurtenances larger than 12” in diameter shall be
bonded such that all joints and fittings are electrically continuous, except across
insulated joints. Contractor shall furnish and install the corrosion monitoring
system components as indicated on the Plans and these Standard Specifications.
Material shall be as specified in Section 10 and this section of these Standard
Specifications. All corrosion monitoring equipment shall be supplied by a
manufacturer regularly engaged in the production of such equipment. Equipment
shall not be installed without prior review and approval by the Engineer.
Contractor shall install each system component in a workmanlike manner
and in strict conformance with the latest edition of the following standards.
NEC - NATIONAL ELECTRICAL CODE
NEMA - NATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION
ASTM - AMERICAN SOCIETY FOR TESTING AND MATERIALS
IEEE - INSTITUTE OF ELECTRICAL AND ELECTRONIC ENGINEERS
ANSI - AMERICAN NATIONAL STANDARD INSTITUTE
IPCEA - INSULATED POWER CABLE ENGINEERS ASSOCIATION
OSHA - OCCUPATIONAL SAFETY AND HEALTH ADMINISTRATION
NACE - NATIONAL ASSOCIATION OF CORROSION ENGINEERS
UL - UNDERWRITERS LABORATORIES
All electrical equipment and materials and the design, construction and
installation thereof shall comply with all applicable provisions of the National
Electric Code (NEC) and applicable local codes and regulations.
Corrosion Specialist shall refer to a California registered Corrosion
Engineer or NACE certified Corrosion Protection Specialist.
27-28
The system shall be complete and in a satisfactory operating condition at
the time of acceptance of the work.
2. Equipment Locations
The locations of corrosion monitoring equipment, devices, outlets, and
appurtenances as indicated on the Plans are approximate only. Exact locations
shall be per these Specifications, unless otherwise determined by the Engineer.
Contractor shall verify in the field, all data and final locations of work
done under other sections of these Standard Specifications required for placing
of the electrical work.
3. Test Stations/Traffic Valve Boxes
Test stations shall be provided where shown on the Plans, and shall
conform to the Standard Drawing W-1002 in Section 38 of these Standard
Specifications. Test stations for insulated joints shall conform to the Standard
Drawing W-1001 in Section 38 of these Standard Specifications. Test stations for
anodes shall conform to the Standard Drawing W-1013 in Section 38 of these
Standard Specifications. Test station junction boxes shall conform to the
Standard Drawing W-1004 in Section 38 of these Standard Specifications.
Attachment of wire identification tags, split bolts and shunts shall be
made as stated in these Standard Specifications.
At a minimum, test stations shall be installed as follows:
Insulated Joint Test Stations (IJTS) Shall be installed at all isolation points
(such as isolation gaskets) on pipelines larger than 12” in diameter.
Corrosion Monitoring Test Stations (CMTS) Shall be installed on transmission
mains every 1000-ft at readily identifiable locations (such as hydrants, air-vacs,
or tie-in points). Corrosion Test Stations are not required if another test station
is connected to the pipe addressing the 1000-ft spacing.
Foreign Pipe Test Stations (FPTS) - Shall be required where high voltage power,
or high pressure metallic gas pipelines, cross within 2-feet from a new
transmission main, unless otherwise directed by Engineer.
Anode Test Station (ATS) Shall be installed where foreign pipe test stations
are not permitted by the foreign pipeline owner to be installed (in order to
negate possible stray current impacts).
Casing Test Stations (CTS) Shall be installed where transmission mains are
encased within a metallic casing. Casing Test Stations shall be installed on both
the entry and exit points of the casing, unless the casing is less than 30-feet in
length at which time only one Casing Test Station is required.
27-29
Anodes and grounding beds shall be installed at test stations as required
by the Engineer.
Junction boxes for test stations shall be B9X Utility Boxes, as
manufactured by Christy Products Inc., or 36 Box as manufactured by Brooks
Products or equal. Junction boxes covers shall be steel checker plates with
welded bead legend “Test Station” and shall be installed out of traffic lanes.
4. Test Boards
Panel boards for test stations shall be made of phenolic plastic one-
quarter inch (¼”) thick and sized as shown on Standard Drawings W-1005, W-
1006, and W-1014 in Section 38 of these Standard Specifications. Solderless
copper lugs and capacitors shall be installed on the panel boards as shown on the
Details. Shunts for the anode junction boxes shall be one-hundredth (0.01) ohm,
eight (8) ampere, manganin wire type, as indicated. Shunts shall be as
manufactured by Holloway or equal.
5. Wire
Conductors shall consist of solid or stranded copper of the gage as shown
on the Standard Drawings in Section 38 of these Standard Specifications. Wire
sizes shall be based on American Wire Gage (AWG). Copper wire shall be in
conformance with ASTM Designations B3 and B8.
Wires buried in the ground shall be laid straight, without kinks and shall
have a minimum cover of twenty-four inches (24”). The bottom of the finished
trench shall be free from stones, roots or other materials that may damage the
wire during or after installation.
Each wire run shall be continuous in length and free of joints or splices.
Care shall be taken during installation to avoid punctures, cuts, or other damage
to the wire insulation. Damage to insulation will require replacement of the
entire length of wire.
At least eighteen inches (18”) of slack shall be left for each conductor at
each test station housing. Slack in the wire shall be sufficient to allow removal
of wire extension for testing. Wire shall not be bent into a radius of less than
eight (8) times the diameter of the wire.
The wire attached to the anodes shall be (AWG) stranded, single
conductor, copper and insulated for six hundred (600) volts. Wire size shall be
minimum No. 10 AWG THWN and conform to the requirements of ASTM D 2220
and NEMA WC-5. Connection of wire to the anode shall have a pulling strength,
27-30
which shall exceed the tensile strength of the wire. Any damage to the wire
insulation or anode shall require complete replacement of the wire and anode.
The anode manufacturer shall conduct and report resistance tests
performed on each anode wire connection to assure the finished connection does
not exceed four-thousandths (0.004) ohms. These resistance tests shall be
performed with a Kelvin bridge circuit or equal. All anode wire connections that
have a resistance value of greater than four-thousandths (0.004) ohms shall
require replacement by the anode supplier prior to shipment. An accurate record
of tests shall be submitted by the anode supplier to the Engineer.
Anode wires shall be of one continuous length without splices from the
anode connection to the respective Junction Box. Anode wires with the attached
anode shall be shipped to the job site with the wire wound on a reel. The
minimum core diameter of the reel shall be five and a half inches (5½”).
Wire identifiers shall be installed in conformance with Standard Drawing
W-1015 in Section 38 of these Standard Specifications. Wire identifiers for anodes
shall be the wrap around type with a high resistance to oils, solvents, and mild
acids. Marker shall fully encircle wire with imprinted alphanumeric characters
for pipe identification. Wire identifiers shall be placed on the wires prior to
backfill, using nylon straps.
Red caution tape three inches (3”) in width shall be installed above buried
wire and conduits at a maximum depth of eighteen inches (18”) below grade over
the wire and conduit location.
Unless otherwise permitted by the Engineer, wire colors shall be as
follows:
White new pipe or valve
Red existing pipe or insulated pipe
Yellow permanent reference electrode
Black anode
Green casing or foreign pipe
6. Exothermic Welds
Exothermic welds shall be provided for cable to structure connections in
strict accordance with the manufacturers recommendations. Connections shall
be made in accordance with Standard Drawing W-1011 in Section 38 of these
Standard Specifications.
The shape and charge of the exothermic weld shall be chosen based on
the following parameters:
27-31
Pipe material
Pipe size
Wire material
Number of strands to be welded
Orientation of weld (vertical or horizontal)
Type of exothermic weld to be used shall be submitted to the Engineer
for approval. Exothermic weld connections shall be installed in the manner and
at the locations shown on the plans. Coating materials shall be removed from
the surface over an area of sufficient size to make the connection. The steel
surface shall be cleaned to white metal by grinding or filing prior to welding the
conductor. The use of resin impregnated grinding wheels will not be allowed.
The conductor shall be welded to the pipe by the exothermic welding process
with a copper sleeve fitted over the conductor. Only enough insulation shall be
removed such that the copper conductor can be placed in the welding mold.
After the weld has cooled, all slag shall be removed and the metallurgical bond
shall be tested for adherence to the pipe or casing. All defective welds shall be
removed and replaced. Connections to the piping shall not be buried prior to
inspection and approval by the Engineer.
Exothermic welds shall be tested by Contractor for adherence to the pipe
or casing and for electrical continuity between the pipe or casing and wires. A
twenty-two ounce (22oz.) hammer shall be used for adherence testing by striking
a blow to the weld. Care shall be taken to avoid hitting the wires.
7. Field Repair of Coatings
After installation of coated items, contractor shall repair damaged shop-
applied coatings and coat field welds with the coating manufacturers
recommended repair material. Contractor shall furnish all materials, clean
surfaces, and repair any damage to protective coatings and linings damaged as a
result of the welding. This shall be done in accordance with these specifications.
For ductile iron or dielectrically coated steel, the coating shall be a
bitumastic coating as listed in these specifications. All surfaces must be clean
and dry and free of oil, dirt, loose particles, and all other foreign materials prior
to application of the coating. Exothermic welds shall be coated and then covered
with a plastic weld cap.
For cement mortar lined and coated pipe or concrete cylinder pipe, the
coating shall match the exterior mortar.
For epoxy-coated appurtenances, Contractor shall use an epoxy-coating
touch-up kit. Prior to coating, surfaces shall be cleaned and ground to bare
metal. Apply one or two coats as required to obtain a dry film thickness of eight
(8) mils minimum using brush or spray. Brush shall be used for touch-up work of
27-32
less than three square feet (3 sf). Field repairs shall comply with the
recommendations of the coating manufacturer.
8. Bitumastic Coating
Bitumastic coating shall be TC Mastic, as manufactured by Tapecoat
Company, Bitumastic 505 as manufactured by Koppers Company, Inc. or
approved equal.
Contractor shall furnish all materials, clean surfaces, and repair any
damage to protective coatings and linings damaged as a result of the welding.
This shall be done in accordance with these specifications.
9. Weld Caps
Weld caps shall be Royston Handy Cap, as manufactured by Royston
Laboratories, Incorporated, Thermite Weld Cap, as manufactured by Phillips
Petroleum Company, or an approved equal.
10. Insulating Flange Kits
Insulating flange kits shall be installed to effectively isolate metallic piping
from foreign metallic structures. Flange insulators shall be installed as shown on
Standard Drawings W-902 and W-905 in Section 38 of these Standard
Specifications.
Insulating flange gaskets shall include full-faced gaskets, insulating
washers and sleeves, and steel washers. The complete assembly shall have a
pressure rating equal to that of the flanges between which it is installed. Gaskets
shall be neoprene faced phenolic, 1/8-inch thick having a high dielectric
constant. Insulating sleeves shall be fabric reinforced resin, 1/32-inch thick.
Insulating washers shall consist of two sets of 1/8-inch thick neoprene faced
phenolic, having a high dielectric constant.
The central gasket shall have a minimum electrical resistance of eighteen
thousand megohms (18,000mΩ) for flanged joints larger than twelve inches (12”)
in diameter and sixteen thousand megohms (16,000mΩ) for flanged joints twelve
inches (12”) in diameter and smaller, be temperature rated to one hundred and
fifty degrees Fahrenheit (150°F), and possess a water absorbency of no more
than five (5) percent when tested in accordance with ASTM D 229.
Steel washers shall be stainless steel (Type 316) and fit well within the bolt
facing on the flange. Insulating washers shall fit within the bolt facing the flange
over the outside diameter of the sleeve.
27-33
Bolts and nuts used for insulated flanged joints shall be stainless steel
(Type 304) and shall conform to ASTM F593, Group 1, and ASTM F594, Group 1,
respectively.
Insulating flange kits shall be installed to effectively isolate metallic piping
from foreign metallic structures. Contractor shall test the performance of these
insulating flange kits prior to backfill. An electric resistance test of at least fifty
thousand ohms (50,000Ω) shall be performed on all insulated joints after each
joint installation has been completed. If the results of the test for electrical
resistance are less than fifty thousand ohms (50,000Ω), the joint shall be
inspected for damage, repaired, as needed, and retested.
11. Joint Bonds
Bond cables or clips shall be provided across flexible couplings on steel
pipe, cement mortar coated steel cylinder pipe joints, and ductile iron pipe
joints as necessary to ensure electrical continuity. Joint bonds shall be installed
as shown on Standard Drawings W-1008, W-1009, W-1011, and W-1012 in Section
38 of these Standard Specifications. Bond wires shall have minimal slack in the
wire at each weld but otherwise be as short as possible.
After installation, all joint bonds shall be tested for effectiveness. The
testing shall be performed prior to backfill of the pipe and shall be verified upon
completion of backfilling operations. Prior to backfilling, current shall be
circulated through the pipe and the measured resistance shall be compared to
the theoretical resistance of the pipe and bond cables. The resistance measured
shall not exceed one hundred and twenty percent (120%) of the theoretical
resistance.
12. Polyethylene Encasement
Polyethylene encasement shall completely encase and cover all metal
surfaces to form a continuous and all-encompassing layer of polyethylene
between the iron and the surrounding earth or backfill material. Polyethylene
encasement material shall conform to AWWA C 105.
Pipe: All ductile-iron pipe shall be encased with polyethylene sleeves in
accordance with Method A described in AWWA C 105, or with polyethylene wrap
in accordance with Method C described in AWWA C 105.
Fittings: Fittings such as tees, bends, reducers, and flanged outlets shall
be encased with polyethylene wrap in accordance with AWWA C 105.
Valves: Valves shall have only the stem and operating nut exposed and the
wrap shall be attached so that valve operation will not disturb the wrapping or
break the seal.
27-34
Polyethylene sleeves shall be secured with polyethylene or vinyl adhesive
tape or plastic tie straps at the ends and quarter points along the sleeve in a
manner that will hold the sleeve securely in place during backfill. Polyethylene
wrap shall be secured with polyethylene or vinyl adhesive tape in a manner that
will hold the wrap securely in place during backfill.
13. Magnesium Anodes
Magnesium anodes shall be “High Potential” magnesium anodes of the
following composition, percent by weight:
Aluminum 0.01% max
Manganese 0.50 - 1.30%
Copper 0.02% max
Nickel 0.001%max
Iron 0.03% max
Other 0.05% each or 0.30% max total
Magnesium Remainder
The anodes shall be prepackaged in a cloth bag containing backfill of the
following composition; seventy-five percent (75%) gypsum, twenty percent (20%)
bentonite and five percent (5%) sodium sulfate. The magnesium anodes shall be
of the size indicated and placed where indicated. Cable for the anodes shall be
black, No. 10 AWG THWN, stranded, and of sufficient length to extend to the
junction box without splicing.
Anodes shall be cast with a galvanized steel core strap. One end of the
anode shall be recessed to provide access to the rod for connection of the lead
wire. The lead wire shall be silver brazed to the rod, making a mechanically
secure connection. The connection shall be insulated to a six hundred volt (600v)
rating by filling the recess with asphaltic concrete. The asphaltic concrete
material shall be extended over the lead wire insulation by not less than one half
inch (½”). Contractor shall repair all damaged lead wire insulation as directed
by the Engineer and at no additional cost to the City.
Prepackaged anodes shall be installed at the locations indicated. Plastic
or paper wrap shall be removed from the anode prior to lowering the anode into
the hole. Anodes shall not be suspended by the lead wires. When compacted soil
is required and has been placed to the top of the anode and prior to the filling
of the hole with soil, a minimum of 10 gallons of water shall be poured into the
hole to saturate the anode backfill and surrounding soil.
Backfilling with native soil shall proceed in six inch (6”) lifts, compacting
the soil around the anode during each lift until the backfill has reached grade.
27-35
Damage to the canvas bag, anode to wire connection, copper wire or wire
insulation will require replacement of entire assembly.
Anodes shall not be backfilled prior to inspection and approval of the
Engineer.
14. Zinc Grounding Mats
Zinc grounding mats shall be installed when pipelines are exposed to high
voltage and stray current impacts are possible.
Where installed, zinc anodes shall be 99.99 % zinc bars, conforming to
ASTM B-418, zinc grounding mat shall be 5/8 inch x 7/8 inch and 180 feet long
zinc ribbon anode. Cable for the grounding mat shall be Black, No. 8 AWG
HMWPE, stranded, and of sufficient length to extend to the test station without
splicing.
The wire attached to the grounding mat shall be (AWG) stranded, single
conductor, copper and insulated for 600 volts. Wire size shall be minimum #8
AWG HMWPE and conform with the requirements of ASTM D-1248, Type 1, Class
C, Grade 5, and IPCEA-NEMA S-61-402. Connection of wire to the grounding mat
shall have a pulling strength which shall exceed the tensile strength of the wire.
Any damage to the wire insulation or grounding mat will require complete
replacement of the wire and grounding mat.
The grounding mat supplier shall conduct and report resistance tests
performed on each wire connection to assure the finished connection does not
exceed 0.004 ohms. These resistance tests shall be performed with a Kelvin
bridge circuit or equal. All wire connections that have a resistance value of
greater than 0.004 ohms shall require replacement by the supplier prior to
shipment. An accurate record of tests shall be submitted by the grounding mat
supplier to the Engineer. The records shall include, as a minimum, six (6) copies
of the following information:
Grounding mat numbering system to identify anode under test
Grounding mat wire length
Resistance value as indicated by test
Test equipment
Test method
The supplier shall mark the reel holding the wire for shipment to the job
site with the same numbering system used on the test records and the total
length of attached grounding mat wire.
27-36
Grounding mat wires shall be of one continuous length without splices
from the connection to the respective test station as shown on the Plans.
Grounding mat wires with the attached mat shall be shipped to the job site with
the wire wound on a reel. The minimum core diameter of the reel shall be 5-
1/2 inches. The anode wire insulation shall be free of surface damage such as
nicks, abrasions, scratches, etc. in all respects throughout the entire length of
the wire. Precaution shall be taken during fabrication, transportation and
installation of the anodes to see that the wire is not kinked or sharply bent.
Bends sharper than 2-1/2 inches in radius are not permissible.
15. System Check-Out
Upon completion of the installation, Contractor shall provide testing of
the system by a qualified Corrosion Specialist, approved by the Engineer, to
ensure compliance with the Plans and these Standard Specifications. The testing
by the Corrosion Specialist shall be in addition to, and not a substitution for, any
required testing of individual items at the manufacturers plant or in the field
by Contractor.
a. Testing
The following test results shall be submitted to the Engineer:
i. Continuity test report
ii. Insulator test results
iii. Initial pipe-to-soil potential survey
iv. On-off potential survey (when sacrificial or impress current
cathodic protection systems are in place)
The assembled flange shall be tested with a Gas Electronics Model
601 Insulator Checker or equivalent instrument that is specifically
designed for the testing of insulating flanges. The testing shall be done in
accordance with NACE RP0286-97. If a short is indicated, each bolt shall
be tested to verify the integrity of each insulating sleeve before the flange
is disassembled. Contractor shall provide assistance in finding any and all
shorts or shorted bolts.
Contractor shall locate and repair any defects that may become
apparent during testing. All efforts by Contractor to test and repair
defects, including excavation and replacement of backfill that has been
already placed, will be at Contractors expense. The system will not be
considered free from defects until the Corrosion Specialist retests and
confirms that all defects have been eliminated.
27-37
b. Written Report:
The Corrosion Specialist retained by Contractor shall prepare a final
report that contains the following:
i. Verification that all test stations have been installed properly.
ii. Verification that all insulating flanges have been tested with
an approved test instrument and that all have passed. If the
pipe-to-soil potential on each side of the insulating flange has
less than 10-mV difference between them, additional testing
with a temporary impressed current system shall be conducted
to confirm insulation.
iii. Field continuity test data, calculations of actual (measured)
pipe resistance from the data and calculations of the
theoretical resistance for each section of pipe tested. The
report shall include a statement that each section of pipe that
contains a bonded or mechanical joint was tested and that the
resistance of each section tested was less than or equal to one
hundred and twenty percent (120%) of the theoretical
resistance.
iv. Verification that all casings are isolated from the pipe.
v. Tabulation of all pipe-to-soil potential survey data.
vi. Verification that all anodes are “high potential” anodes.
vii. Other information that the Corrosion Engineer believes is
pertinent with respect to the corrosion status or long-term
performance of the pipeline or structure installed.
27-18 PAYMENT FOR FURNISHING AND INSTALLING WATER DISTRIBUTION SYSTEMS
Unless unit bid prices are required by the Special Provisions, payment for
the item “Water Distribution System to construct” shall be made at the lump
sum price. Such payment shall be full compensation for furnishing all labor,
material, tools, and equipment and doing all work involved in cutting, trenching,
laying, blocking, making connections, disinfecting, testing, backfilling, and
paving or repaving, as required herein, on the Plans or in the Special Provisions.
28-1
Section 28
DRIVEWAY CULVERT AND SIDEWALK FRENCH DRAINS
28-1 DRIVEWAY CULVERT
Driveway culvert shall be reinforced concrete pipe (RCP), high density
polyethylene (HDPE) with smooth bore, corrugated metal pipe (CMP), or field
assembled metal plate as called for on the plans. Material shall conform to
Section 10 and the following:
1. Pipe Materials
RCP shall be ASTM C 76, Class III. CMP and field assembled plate shall be
minimum of 12 gage, galvanized or aluminized pipe. HDPE shall be smooth
interior, shall conform to ASTM F 894 and referenced standards contained therein
or AASHTO M 294 with HDPE belled ends; resin utilized in manufacture of M294
polyethylene pipe shall conform to ASTM D 1248 and ASTM D 3350. HDPE pipe
shall have a minimum Ring Stiffness Constant (RSC) of 63 and/or a minimum SDR
rating of 26. Joints shall be rubber gasket material conforming to ASTM F 477, or
shall be fused, and shall be capable of the same water tightness as PVC (ASTM
3212).
2. Installation
Installation of RCP shall be in accordance with Section 26. Installation of
HDPE shall conform to ASTM D 2321 and additional requirements contained
therein or ASTM F 714, ASTM D 3261, ASTM D 3350, and ASTM 1248. CMP shall
be placed in accordance with Section 66 of the State Specifications. Field
assembled plate culvert shall be placed in accordance with Section 67 of the
State Specifications.
28-2 SIDEWALK FRENCH DRAINS
Sidewalk French drains shall be placed in new construction when directed
by the Engineer or when shown on the plans and shall conform to applicable
portions of Section 26 and the following:
1. Pavement Cutting
Pavement cutting shall conform to Sections13-3, and 38 (STD DWG T-8).
The thickness of existing AC to be cut and AB is variable. There shall be no
additional payment due to the varying thickness of AC and AB. Existing street
surface to be removed shall be saw cut in a neat line and shall be disposed of
away from the project site in a location and manner satisfactory to the Engineer.
28-2
Pavement removal shall not precede trenching by more than seven (7) calendar
days unless approved by the Engineer.
2. Placement of French Drains
In new construction, French drains are normally placed underneath, and
in alignment with the gutter in accordance Standard Drawing T-40.
3. Trench Excavation
Trenches shall be graded to the lines and sections as shown on the Plans
or where directed by the Engineer and shall be in accordance with the provisions
of Section 14.
Care shall be exercised to prevent excavation below the grade for the
bottom of the trench, and areas excavated below grade shall be filled with
suitable material and thoroughly compacted by Contractor at his/her expense.
Excavated material shall become the property of Contractor and shall be
disposed of away from the site.
4. Crushed Rock
Contractor shall place Type C Crushed Rock conforming to Section 10 and
in accordance with Standard Drawing T-40.
5. Perforated Pipe
All French drains shall be four inches (4") in diameter unless otherwise
indicated. Perforated pipe shall be polyvinyl chloride (PVC) pipe with
perforations throughout the length of the pipe and conforming to the applicable
portions of AASHTO M 252. Alternatively, pipe may be perforated corrugated
polyethylene tubing conforming to the applicable portions of AASHTO M 252 or
M 294.
6. Filter Fabric
Filter fabric shall conform to Sections 68 and 96 of the State
Specifications.
7. Drain Inlet Penetrations
Cast in place drain inlets shall be core bored and french drain lead pipes
connected to manholes using "Kor n' Seal Cavity O-Ring" by NPC Inc., or approved
28-3
equal. Connecting French drains to pre-cast drain inlets shall be per Section 30,
“Drain Inlets.
28-3 PAYMENT
Payment for pipe culvert will be at the price bid per lineal foot and will
include full compensation for furnishing and laying the pipe, excavation, backfill,
compaction, special foundation treatment, dewatering, incidentals and all other
work necessary to place pipe culvert.
Payment for sidewalk French drains will be at the price bid per lineal foot
and will be considered full compensation for constructing the French drains,
connections to drain inlets or manholes, clean crushed rock, filter fabric, all
labor, materials, tools, equipment and all incidentals and work necessary to
complete this item in place. Steel under sidewalk drains and replacement of
existing asphalt pavement shall be paid for separately.
29-1
Section 29
MOVING OR CHANGING UTILITIES AND WATER SERVICES
29-1 UTILITIES AND FRANCHISES
If it is required to move a public utility or franchise, the owner will be
notified by the Engineer to move such, and Contractor shall protect the facility
from damage and not interfere with such facilities until after it is moved.
The City and owners of public utilities and franchises reserve the right to
enter upon the street for the purpose of making necessary repairs or making
changes in their facilities made necessary by the work.
29-2 PROVISION FOR UTILITY CONNECTION
The City reserves the right to construct or reconstruct any sewer, water,
drain, electric or any other facility, to grant permits to lay gas, electric, or
communication lines, conduits, and other facilities, and to make connections
thereto, at any time during the work.
29-3 COOPERATION OF CONTRACTOR DURING RELOCATIONS AND UTILITY
CONNECTIONS
Contractor shall not interfere with or place any impediment in the way of
any person or persons authorized by the City to perform such relocations and
utility connections.
The City of Sacramento reserves the right to suspend the work on any part
of an improvement at any time during the construction of the same, for the
purposes stated above.
30-1
Section 30
DRAIN INLETS, GUTTER DRAINS AND DITCH BOXES
30-1 DRAIN INLETS
Drain inlets shall conform to Sections 10 and Standard Drawings S-10, S-
20, S-21, S30, S-40, and S-65 of Section 38 of these Standard Specifications.
Drain inlets shall be pre-cast or cast in place or a combination of the two. Hand
forming of concrete will not be allowed. For cast in place drain inlets, maximum
wall thickness shall be 8 inches. Concrete shall be Type A or B in Accordance
with Section 10 of these Specification.
30-2 DRAIN INLET GRATE AND HOOD
The grate shall conform to drawings included in Section 38 of these
Specifications. Joints and connections between grate frame, hood and vertical
walls of drain inlet shall be smooth and continuous, with a slight broom finish or
equivalent. If steel, surfaces shall be covered with an asphaltic paint.
30-3 GUTTER DRAINS
Gutter drains shall conform to Standard Drawings S-42, S-45, S-50, S-55,
and S-60 of Section 38 of these Standard Specifications.
30-4 WATER QUALITY MARKING
All drain inlet and gutter drain installations shall include a permanent
storm water quality marking conforming to Section 38 of these Specifications.
30-5 PAYMENT
Payment for drain inlets, gutter drains or ditch boxes will be at the price
bid per each and will be considered full compensation for excavation, material,
and labor necessary to construct this item in place.
31-1
Section 31
CONSTRUCTION OF FENCING
31-1 MATERIAL IN FENCE
Fence shall conform to Section 10-38 of these Specifications.
31-2 CONSTRUCTING CHAIN LINK FENCE
Chain link fence shall be constructed in accordance with Standard Drawing
T-90 of Section 38 of the Standard Specifications, with fencing and fabric height
specified on the plans. Top of fence fabric shall be knuckled, unless otherwise
specified or shown on the Plans.
The line of the fence shall be cleared of all obstructions and surface
irregularities and the bottom of the fence shall be to uniform grade as may be
established by the Engineer. The posts shall be spaced not more than ten feet
(10’) apart and at points specifically shown on the Plans.
Terminal posts, gate posts, and line posts shall be set thirty-six inches
(36”) in concrete footings. Concrete shall be Class “C” as set forth in these
Specifications. Concrete footings for terminal, gate and line posts shall be
allowed to cure for not less than seven (7) days before wire fabric is placed. Set
posts to within six (6) inches from the bottom of the concrete footing. Set top of
footing at post two (2) inches above finish grade. Slope top of footing for water
runoff.
Stretcher bar and truss bands shall be spread and slipped on end, corner,
pull, brace, and gate posts before installation of top rails. Extension joints shall
be provided for rails at intervals of one hundred feet (100’). Bottom tension
wire shall be seven (7) gauge galvanized coil spring steel.
The placing of the rails, braces, and the wire fabric shall be accomplished
in such a manner that the finished fence shall be taut, true, and of precise
workmanship throughout. The fabric shall be stretched so that no slack sections
remain at any point. The fabric shall be securely tied to posts and rails in a
manner so that the fabric will remain tight and immovable. Position fabric two
(2) inches above finish grade. Attach fabric to end, corner, and gate posts with
tension bars and tension bar clips.
Install gates using fabric to match fence. Install two (2) hinges per leaf.
Install latch, catches, foot bolts and sockets, retainer and locking clamp.
Provide concrete center rest and drop bolt retainers at center of double gate
openings. Install center brace rail on all gate leaves. Gates shall be so set that
31-2
they are true and will swing freely with a maximum force of 5 pounds in the
direction indicated on the Plans. The bottom surface of the gate on the push side
must be smooth and shall be located at the bottom 10” of the gate
Provide standard commercial grade locking latches for use with padlocks
on all gates, and provide 3/8”diameter U-bolts welded (1/4” fillet weld) to gate
posts and gate frame for backup chain and lock.
31-3 CHAIN LINK FENCING VINYL SLATS
When shown on the Plans or specified in the Special Provisions, chain link
fence shall be constructed with vinyl slats. The slats shall be inserted vertically
into each mesh of the wire fabric. The slats shall be fastened in position by the
weaving machine which shall produce a bow knuckle at both ends of the slats.
No staples in the slats are permitted. The slats shall be of redwood color, unless
otherwise directed.
31-4 POST AND CABLE FENCE
The line of the fence shall be cleared of all obstructions and surface
irregularities and the bottom of the cable shall not be less than 2-6” blow the
surfacing of the finish grade. The posts shall be spaced not more than fifteen
feet (15’) apart and at points specifically shown on the Plans.
Terminal posts, and post at bends shall be set fourth-two inches (42”) in
concrete footings. Concrete shall be Class “C” as set forth in these
Specifications. Concrete footings for terminal and line posts at bends shall be
allowed to cure for not less than seven (7) days before the cable is installed. Set
posts to within six (6) inches from the bottom of the concrete footing. Set top of
footing at post two (2) inches above finish grade. Slope top of footing for water
runoff.
31-5 PAYMENT FOR FENCING
Payment for chain link fencing and chain link fencing with vinyl slats shall
be at the price bid per lineal foot, unless otherwise stated in the Special
Provisions. Gates shall be paid for separately at the price bid per each gate of
a specified size, unless otherwise stated in the Special Provisions. Payment shall
include full compensation for furnishing all fencing material, labor, equipment,
concrete, or other materials and constructing the fence or gates at the location
shown on the Plans or as otherwise directed.
31-3
31-3 VINYL SLATS
When shown on the Plans or specified in the Special Provisions, chain link
fence shall be constructed with vinyl slats. The slats shall be inserted vertically
into each mesh of the wire fabric. The slats shall be fastened in position by the
weaving machine which shall produce a bow knuckle at both ends of the slats.
No staples in the slats are permitted. The slats shall be of redwood color, unless
otherwise directed.
31-4 PAYMENT FOR FENCING
Payment for chain link fencing and chain link fencing with vinyl slats
shall be at the price bid per lineal foot, unless otherwise stated in the Special
Provisions. Gates shall be paid for separately at the price bid per each gate of
a specified size, unless otherwise stated in the Special Provisions. Payment
shall include full compensation for furnishing all fencing material, labor,
equipment, concrete, or other materials and constructing the fence or gates at
the location shown on the Plans or as otherwise directed.
32-1
Section 32
TRAFFIC SIGNS, MARKINGS, AND BARRICADES
32-1 TRAFFIC SIGNS
1. General
Signs shall conform to Section 82, “Signs and Markers”, of the State
Specifications, and these Specifications.
2. Overhead Sign Structures
Overhead sign structures shall conform to Section 56, “Overhead Sign
Structures, Standards and Poles”, of the State Specifications and these
Specifications.
3. Roadside Signs
Roadside signs shall conform to Section 82, “Signs and Markers”, of the State
Specification, and these Specifications. Unless otherwise shown or specified in
the Contract, all signs and pipe posts shall be furnished and installed by
Contractor.
City Specialty Signs shall conform to Standard Drawings of Section 38 of
these Standard Specifications.
City Specialty Signs may be purchased from the Signs and Markings operation
of the Streets Division.
Construction signs shall conform to the provisions of the U.S. Department
of Transportation, Federal Highway Administration, “Manual on Uniform Traffic
Control Devices” and the California Supplement.
4. Material
Sign panel fastening hardware shall conform to Section 82, “Signs and
Markers”, of the State Specifications, and these Specifications. Lag screws,
bolts, metal washers, and nuts may be cadmium-plated steel instead of
commercial quality galvanized steel. All street name signs shall be fastened with
stainless steel hardware and strapping.
Wood posts and laminated wood box posts as referenced in Section 82,
“Signs and Markers, of the State Specifications shall not be allowed.
32-2
5. Construction
Construction shall conform to Section 82, “Signs and Markers”, of the State
Specifications and these Specifications. Wood Posts and Laminated Wood Box
Posts shall not be allowed.
6. Installation
Installation shall conform to Section 82 “Signs and Markers,” of the State
Specifications and these Specifications. Socket-Mounted Stanchions: Socket-
mountings shall conform to Standard Drawing T-260. Socket mounting is used on
median signs and on signs installed in asphalt, or as specified on plans.
32-2 THERMOPLASTIC PAVEMENT MARKINGS
Thermoplastic traffic stripes and markings, both white and yellow, shall
be placed as shown on the Plans, and in conformance with Sections 84 of the
State Standard Specifications. All striping details shall be in conformance with
the State Standard Plans (latest edition).
1. Material
Thermoplastic shall be Alkyd type for extrusion application and shall
produce an adherent reflectorized strip capable of resisting deformation by
traffic.
The thermoplastic material shall be 100 percent solids. The binder shall
consist of synthetic alkyd resins and shall be homogeneously incorporated with
all the necessary prime pigments, fillers, and glass beads to produce a traffic
coating to meet the requirements as specified herein. The characteristics of
finished thermoplastic are shown on Table 32-2.01
Table 32-2.01
White
Yellow
Glass Beads, AASHTO M-247, Type I, percent by weight, min.
(Cal. Test Method 423)
30 30
Titanium Dioxode (TiO2), percent by weight, min.
(AASHTO T250-77)
10
Lead Chromate, Medium Heat Stability, percent by weight, min.
2.5
Specific Gravity, max.
(Cal. Test Method 423)
2.15 2.15
32-3
White
Yellow
Binder, percent by weight, min.
(Cal. Test Method 423)
18 18
Ring & Ball Softening Point, F (ASTM E28)
200
240
200
240
Tests on Material after 4 hours heat with stirring at 425 + 2
F,
which includes 1 hour for meltdown and temperature
stabilization:
Bond Strength to Concrete, 0.125-
inch thick film drawdown at
425F test at 75F + 2F, psi, min. (Cal. Test Method 423)
180 180
Brookfield Thermosel Viscosity, Spindle SC4-27, 20 RPM at 425
F,
Poise
(Cal. Test Method 423)
30 45 30 45
Impact Resistance, Falling Ball Method, 0.125-
inch thick film
drawdown at 425 F on concrete. Test at 75F + 2F inch-
lbs.,
(ASTM D 2794)
10 10
Daylight Luminous Reflectance, min. (ASTM E97)
75 40
Yellowness Index, max., (ASTM E313)
15
Hardness, Shore A-2 Durometer with 2 kilogram weight at 115F
(Cal. Test 423)
60 80 60 80
Low Temperature Stress Cracking, Resistance at 25F (AASHTO)
No
Crack
No
Crack
Color Match, Federal Std. No. 595a, Color No. 33538
Passes
2. Removal
Traffic stripes and pavement markings shall be removed by any method
that does not materially damage the existing pavement. Pavement marking
images shall be removed in such a manner that the old message cannot be
identified. Where grinding is used, the pavement marking image shall be
removed by grinding a rectangular area. The minimum dimensions of the
rectangle shall be the height and width of the pavement marking. Residue
resulting from removal operations shall be removed from pavement surfaces by
sweeping or vacuuming before the residue is blown by the action of traffic or
32-4
wind, migrates across lanes or shoulders, or enters into drainage facilities. The
Contractor shall be responsible for disposal of all removed striping material.
Traffic stripes shall be removed before any change is made in the traffic
pattern.
3. Application
The thermoplastic material shall be applied by extrusion methods in a
single uniform layer. Stencils shall be used when applying thermoplastic material
for pavement markings. Stencils may be new or used, if in good condition. If
stencils are bent or damaged, they shall be replaced at the request of the
Engineer.
The pavement surface to which thermoplastic material is applied shall be
completely coated by the material and the voids of the pavement surface shall
be filled. Surface must be dry before application. Contractor may use artificial
method to dry the pavement surface.
Unless otherwise specified in the Special Provisions, the thermoplastic
material for traffic stripes shall be applied at a minimum thickness of 0.075-inch.
Thermoplastic Material for pavement markings shall be applied at a minimum
thickness of 0.125-inch. Glass beads shall be applied immediately to the surface
of the molten thermoplastic material, at a rate of not less than 8 lbs. per 100
sq. ft. The amount of glass beads applied shall be measured by stabbing the glass
beads tank with a calibrated rod.
Contractor shall apply all traffic stripes and markings on new asphalt
surface in accordance with the manufacturer’s recommendations.
3. Tolerances and Appearance
The completed traffic stripes and markings shall have clean and well-
defined edges without deformations, and shall be free of tears or other
disfigurements. Improperly placed, defective, or disfigured traffic stripes and
markings shall be immediately removed from the pavement surface by methods
approved by the Engineer. All such removal work shall be at Contractor's
expense.
Completed traffic stripes shall be uniform, shall be straight on tangent
alignment, and shall be on a true arc on curved alignment. On tangent alignment,
when a 100' string line is stretched taught and placed directly on the outer edge
of the completed traffic stripe, the distance between the string and the edge of
the traffic stripe shall not exceed three-fourths of one inch (3/4") when
measured anywhere along any 100' interval of the tangent alignment. On curved
alignment, the outer edge of the traffic stripe shall not deviate more than three-
32-5
fourths of one inch (3/4") from the true arc. The lengths of the gaps and
individual stripes that form broken traffic stripes shall not deviate more than 2"
from the lengths required to produce a uniformly repeating, broken-stripe
pattern.
4. Time Limitations
All permanent marking must be placed no earlier than three (3), and no
less than seven (7), days from the placement of slurry seal. Partial removal of
roadway markings shall be replaced within two (2) weeks. Contractor may
contact City Signs and Markings to replace markings at cost.
32-3 PAINTED PAVEMENT MARKINGS
1. General Requirements
Painted pavement markings shall not be used unless directed by the
Engineer. If directed, painted pavement markings shall be placed in conformance
with the State Standard Plans (latest edition) and Sections 84 of the State
Specifications except as modified herein.
2. Materials
Section 84 of the State Standard Specifications shall be amended to read
as follows:
The paint thickness shall be 12 to 14 mils wet. Thinning of paint will not
be allowed, except when placed for temporary markings that will be replaced
within two (2) weeks.
3. Certificate of Compliance
When requested, Contractor shall provide the Engineer with a
manufacturer's certificate of compliance which certifies that the paint comply
with the specifications contained herein. Contractor shall also provide the
Material Safety Data Sheet (MSDS) on all material.
4. Time Limitations
All permanent marking must be placed within three (3) days of final
paving. Partial removal of roadway markings shall be replaced within two (2)
weeks. Contractor may contact City Signs and Markings to replace markings at
cost.
5. Quality
32-6
The completed markings shall have clean and well-defined edges without
deformations, and shall be free of tears or other disfigurements. Improperly
placed, defective, or disfigured markings shall be immediately removed from the
pavement surface by methods approved by the Engineer. All such removal work
shall be at Contractor's expense.
32-4 COLORED BIKE LANES
Colored pavement, traffic stripes, and markings for bike lanes shall be
placed where shown on the plans or as directed by the Engineer and shall
conform to the applicable requirements of Section 32 of the City Standard
Specifications, Sections 84 of the State Standard Specifications and these Special
Provisions. All striping details shall be in conformance with the State Standard
Plans (latest edition).
Material Properties
The colored pavement material shall be a methyl methacrylate (MMA)
acrylic based resin system used for color pavement marking and anti-skid
surfacing. The resin, catalyst, and aggregate compounds shall be capable of full
cure in a wide range of temperatures without requiring external heat sources.
Properties
Unit of Measure
Test
Neat Resin
Tensile Strength
2000 psi (14MPa) min
ASTM D638
Elongation
70% min
ASTM D638
Tensile Modulus
of Elasticity
1370 psi (9.5 MPa) min
ASTM D638
Hardness
15 20 Shore D
ASTM D2240
Water
Absorption
0.25% max
ASTM D570
Density
13.42 lb/gal (1.6 gm/ml)
ASTM D2849
Pot Life
15 minutes @ 72˚F
(22˚C)
AASHTO T237
Flash Point
50˚F (10˚C)
ASTM D1310
Solids Content
99%
ASTM D1644
Skid Resistant
45 minimum
ASTM E274
Aggregate
Specific Gravity
2.65
ASTM C128
Hardness
7.0
Mohs Scale
32-7
Material Color
The daytime chromaticity coordinates for the color used for green colored
pavement shall be as follows:
1
2
3
4
x
y
x
y
x
y
x
y
0.230
0.754
0.266
0.500
0.367
0.500
0.444
0.555
The daytime luminance factor (Y) shall be at least 7, but no more than 35.
The nighttime chromaticity coordinates for the color used for green colored
pavement shall be as follows:
1
2
3
4
x
y
x
y
x
y
x
y
0.230
0.754
0.336
0.540
0.450
0.500
0.479
0.520
Surface Preparation
Before applying colored pavement material, cover manholes, valve and monument
covers, grates, or other exposed facilities located within the area of application, using
a plastic or oil resistant construction paper secured by tape of adhesive to the facility
being covered.
All surfaces that are to receive colored pavement material shall be thoroughly clean,
dry, and free of all dirt, grease, and other contaminates that might interfere with
proper adhesion
Clean the pavement surface using high pressure water, compressed air, sandblasting,
shot-blasting, or mechanical abrasion. The surface should be visibly dry, and the
moisture content should be tested according to ASTM D4263 (modified to 2 hours). New
asphalt shall have been placed for a minimum of 15 days prior to installation of the
colored pavement material and surface oils shall not be present. The temperature of
the pavement and air shall be between 40˚F - 104˚F (5˚C - 40˚C).
All areas to be coated shall be masked prior to application of primer and masked again
prior to application of the colored pavement material.
Mixing and Application
Mixing and applying colored pavement material and primer shall be in
accordance with the manufacturer's instructions.
32-8
32-5 RAISED REFLECTIVE PAVEMENT MARKERS
1. General Requirements
Raised reflective pavement markers shall conform to Section 81 of the
State Specifications except as noted herein.
2. Materials
Raised reflective pavement markers shall be #290 manufactured by 3M
Company or approved equivalent and shall be placed in conformance with
Section 81 of the State Standard Specifications.
3. Placement
Blue raised reflective pavement markers shall be placed in the street, 6”
- 12” off of centerline and perpendicular to the fire hydrant. Markers shall be
blue with two reflective faces.
Green raised reflective pavement markers shall be placed in the street,
6- 12” off of centerline and perpendicular to the “backyard” manhole. Markers
shall be green with two reflective faces. Contractor shall be responsible for
locating, inventorying, and replacing all green raised reflective markers.
Contractor shall provide to the Engineer an inventory list of all green raised
reflective markers before starting construction.
32-6 TEMPORARY PAVEMENT MARKINGS
1. General Requirements
Temporary pavement markers shall be furnished, placed, maintained, and
later removed as specified in the Special Provisions, and as directed by the
Engineer.
2. Materials
The following markers are approved for use on City of Sacramento street
resurfacing projects:
Temporary Overlay marker (Types Y and W) manufactured by Davidson
Plastics Company, 18726 East Valley Highway, Kent, Washington 98032,
telephone (206) 251-8140.
32-9
Safe-Hit Temporary Pavement Marker, manufactured by Safe-Hit
Corporation, 1930 West Winton Avenue, Building #11, Hayward, CA 95545,
telephone (415) 783-6550.
Swareflex Pavement Marker (Models 3553, 3554, Cat Eyes Nos. 3002 and
3004), manufactured by Swareco and distributed by Servtech Plastics Inc., 1711
South California Street, Monrovia, CA 91016, telephone (818) 359-9248.
Stimsonite Construction Zone Marker (Model 66), manufactured by
Amerace Corporation, Signal Products Division, 7542 North Natchez Avenue,
Niles, IL 60648, telephone (312) 647-7717.
Flex-O-Lite Raised Construction Marker (RCM), manufactured by Flex-O-
Lite, Lukens Company, P.O. Box 4366, St. Louis, MO 63123-0166, telephone (800)
325-9525.
3M Scotch-Lane A200 Pavement Marking System (reflective raised
pavement marker on reflective traffic line tape), manufactured by 3M Company,
Highway Safety Products, 1010 Hurley Way, Suite 300, Sacramento, CA 95825,
telephone (916) 924-9605.
MV Plastics Chip Seal Marker (1280/1281 Series with Reflexite
Polycarbonate, PC 1000, reflector unit), manufactured by MV Plastics, Inc., 533
W. Collines Avenue, Orange, CA 92667, telephone (714) 532-1522.
3. Placement
Temporary reflective raised pavement markers shall be placed in
accordance with the manufacturer's instructions. Temporary reflective raised
pavement markers shall be cemented to the surfacing with the adhesive
recommended by the manufacturer, except epoxy adhesive shall not be used.
At the direction of the Engineer, Temporary pavement striping may be
required.
After paving and or planing, temporary pavement markers shall be placed
on all existing striped streets that are opened to public traffic prior to final
striping in accordance with the striping diagrams. Temporary pavement markers
that are damaged from any cause during the progress of the work shall be
repaired or replaced by Contractor at his expense.
When no longer required for the work as determined by the Engineer,
temporary pavement markers shall be removed in accordance with the provisions
in Section 15-2, "Miscellaneous Highway Facilities," of the State Standard
Specifications, except as otherwise provided herein. If the temporary pavement
32-10
markers to be removed are on surfacing that is to be removed, the temporary
pavement markers may be removed and disposed of in conjunction with the
removal of the surfacing, providing such pavement markers do not interfere with
the required traffic lane delineation, as determined by the Engineer.
The 14-day waiting period for placing pavement markers on new asphalt
concrete surfacing shall not apply to temporary pavement markers.
32-7 TEMPORARY STREET SIGNS
Temporary street signs shall conform to this Section 32-1 and Section 38
of these Specifications. The signs shall be placed as shown on the Plans. Their
exact location and orientation shall be designated by the Engineer.
The dimensions of the materials shall be as shown in Section 38. The post
shall be either redwood or Douglas Fir. Douglas Fir shall be treated with a wood
preservative in conformance with Section 58 of the State Specifications. The
signboard shall be exterior plywood. Paint shall be a quality latex base for
exterior wood.
The sign shall have black letters on a white background. Gothic letters
similar to those in Section 38 shall be used. The lettering shall be four inches
(4”) in height with a stroke width of no less than one-half inch (½”) or more than
three-fourths inch (¾”). Numeral suffixes, i.e., st, nd, rd, and th, shall be two
inches (2”) in height with a stroke width of no less than one-fourth inch (¼”) or
more than three-eighths inch (⅜”). The back of the sign-board and the post shall
also be painted white.
Each sign-board shall be fastened to the post by bolts. The bottom of the
sign shall be no less than seven feet (7’) above the ground. Payment for
temporary street signs shall be the Contract price bid per each complete in
place.
32-8 STREET BARRICADES
Street barricades shall conform to this Section and Section 38 of these
Standard Specifications. The barricades shall be placed where shown on the Plans
or designated by the Engineer.
Wood members shall be either redwood or Douglas Fir. Douglas Fir shall
be treated with a wood preservative in conformance with Section 58 of the State
Specifications.
A fully reflectorized sign 18 inches by 18 inches (18” X 18”) (2.25 square
feet) shall be placed on the barricade with bolts, nuts, and washers, and shall
32-11
face on-coming traffic to designate dead end streets. All barricades shall be
painted white in color, with two (2) applications of a quality latex base paint for
exterior wood.
32-9 PAYMENT
Payment for traffic signs, including overhead sign structures and roadside
signs shall be at the price bid per each and shall conform to Section 56-1.06,
“Payment” of the State Specifications, and these Specifications. The price bid
for each sign of the type or types designated in the Contract will include full
compensation for furnishing all labor, materials, (except City furnished
material), tools, equipment, and incidentals, and for doing all the work involved
in furnishing and installing roadside signs, complete in place, including the
installation of sign panels, shown or specified in the Contract, specified in these
Specifications, and as directed by the Engineer.
Measurement for overhead and roadside sign structures shall conform to
Section 56-1.10, “Measurement” of the State Specifications, and these
Specifications. Signs will be measured by the unit from actual count, complete
in place, of the type or types of signs designated in the Contract.
Payment for thermoplastic pavement markings will be at the unit price
bid per lineal foot for striping as measured by the lineal foot of thermoplastic
material placed. No payment will be made for gaps in broken traffic stripes.
Double center stripes will be paid as two (2) four-inch (4") stripes. Regular cross
walks, parking Tees and L’s will be measured by the lineal foot. Payment for all
other thermoplastic marking will be at the price bid per square foot of
thermoplastic material placed. Payment for all thermoplastic markings will be
considered full compensation for furnishing all labor, material, tools, equipment
and incidentals, and for doing all work involved in removing existing striping and
placing stripes and markings, as specified in the Special Provisions and as
directed by the Engineer. Existing striping shall be removed by grinding.
The quantities of thermoplastic traffic stripes or thermoplastic pavement
markings may be adjusted, deleted, or omitted as directed by the Engineer to
meet the existing requirements. No adjustment to the unit price bid will be made
because of a change in quantity from the Engineer's estimate.
Payment for bike legends will be at the unit price bid per square foot and
will include full compensation for furnishing all labor, material, tools, equipment
and incidentals, and for doing all work involved in removing existing and painting
new pavement markings, as specified in the Special Provisions and as directed
by the Engineer.
Payment for painted pavement markings will be at the price bid per square
32-12
foot bid for the actual area painted.
Payment for painted pavement markings will be at the price bid per square
foot bid for the actual area painted.
Payment for raised reflective pavement markers shall be at the unit price
bid per each and shall include full compensation for furnishing all labor,
material, tools, equipment, incidentals required to perform all work involved
with placing pavement markers, including removal of existing pavement
markers, as shown on the layout diagrams, as specified in these Special
Provisions and as directed by the Engineer.
Payment for street barricades shall be at a unit price for each barricade
constructed. This price will include full compensation for constructing street
barricades complete in place as shown on the Plans.
33-1
Section 33
PNEUMATICALLY APPLIED MORTAR
33-1 GENERAL
Also known as air-blown mortar, gunite, or shotcrete, this section refers
to premixed sand and cement, pneumatically applied by suitable mechanism and
competent operators, and to which mixture water is added immediately previous
to its expulsion from the nozzle. The pneumatically applied mortar shall be
placed at the thickness shown on the Plans or called for in the Special Provisions.
The resulting surface shall be uniform and free from humps or depressions.
33-2 MATERIALS
Portland Cement shall conform to the requirements of Section 10-1 and
shall be Type II, unless otherwise specified in the Special Provisions.
Sand shall be clean, sharp, and free from clay, silt, and loam. It shall be
well graded and suitable for the purpose intended with no particles larger than
three-eighths inch (⅜”) in diameter.
The sand shall contain not less than three percent (3%) nor more than six
percent (6%) moisture by weight.
Material quality assurance shall be in accordance with pertinent provisions
of ACI 506.2, except as modified herein. Product handling shall conform to ACI
506.2, and these provisions. The mix design shall conform to ACI 318 and shall
obtain a twenty-eight (28) day compressive strength of 3,000 psi.
33-3 PROPORTIONS
The proportion of cement to sand shall be based on dry and loose volume
and shall not be less than one part Portland Cement to four and one-half parts
sand. The water content shall be maintained at a practical minimum and not in
excess of three (3) gallons per sack of cement as placed. Admixtures shall
conform to ASTM C 494, Type A. Calcium chloride or admixtures containing any
amount of calcium chloride shall not be used.
33-4 MIXING
Before being charged into the machine the cement and sand shall be
thoroughly mixed dry in an approved power batch mixer equipped with a device
for accurately measuring the quantity of sand and timing the mixing operation.
The mixture shall be mixed for at least one and one half (1½) minutes during
33-2
which time the mixer shall rotate at a peripheral speed of two hundred feet
(200’) per minute. The dry mixed materials shall be used promptly after their
preparation and any material which has been mixed for more than forty-five (45)
minutes shall be wasted. Rebound shall not be used on any portion of the work.
33-5 PREPARATION OF SURFACE
When gunite is to be placed on an earth slope for embankment protection,
the earth surface shall be cleaned of grass, roots, and other deleterious matter.
The surface shall be evenly graded to the lines, grade, and sections as indicated
on the drawings. The surfaces shall be moistened thoroughly to prevent moisture
from being drawn from the freshly placed lining. All surfaces on which lining is
to be placed shall be free from water, mud, and debris, and shall be firm enough
to prevent contamination of the fresh lining by earth or other foreign material.
When gunite is applied to steel or concrete structures the surface must be
cleaned of all loose material and be damp, as above specified at the time of
application of the material. Header board shall be placed as indicated on the
Plans.
33-6 PLACING
The velocity of the material as it leaves the nozzle shall be such that
minimum rebound occurs. Velocities of the material must be kept constant. The
nozzle shall be held in such position and at such distance that the stream of
flowing material will impinge at approximately right angles to the surface being
covered and so that excessive impact will be avoided.
Pneumatic pressure at the machine shall not be less than thirty pounds
per square inch (30 psi) when the length of hose does not exceed one hundred
feet (100’). Pressure shall be increased five pounds per square inch (5 psi) for
each additional fifty feet (50’) of hose or fraction thereof. Water used for
hydration at the nozzle shall be supplied at pressure of not less than fifteen
pounds per square inch (15 psi) greater than the air pressure. The mortar must
have uniform consistency at all times.
The mortar lining shall be applied to the surface at the thickness and to
the limits indicated on the drawings. Wires shall be placed at a maximum of 10
foot intervals, both horizontal and vertical, to control finish grade and thickness.
The appearance shall be neat and uniform. At regular intervals, the fresh surface
shall be checked with a minimum ten (10) foot length straight-edge, and all low
spots or depressions shall be filled to finish grade. Finished lining surfaces shall
be plus-or-minus ½ inch from the specified grade. Lining thickness tolerances
shall be plus-or-minus ½ inch. The finished surface shall be smooth and uniformly
constructed with a stiff broomed finish.
33-3
33-7 CURING AND PROTECTION
Curing shall be accomplished as set forth in Section 19-8 or Section 20-13
of these Specifications. Contractor’s attention is directed to Section 7-8,
“Protection of Work, Persons, and Property Against Damage”, of these
Specifications.
The lining shall be protected after placement in accordance with the
requirements of Section 20-13.
33-8 REINFORCEMENT
Steel reinforcement shall conform to Section 10 and shall be of the type
shown on the Plans or called for by the Special Provisions. Reinforcement shall
be embedded in the mortar so that it will be a minimum of one inch clear from
either face of the mortar unless otherwise noted.
33-9 JOINTS
Joints in Pneumatically Applied Mortar shall be neat and square, shall be
constructed where shown on the plans and in accordance with the Special
Provisions and the following:
1. Construction Joints
Construction joints shall be square, and shall be edged with a 1/4-inch
radius edging tool. The edge shall be thoroughly wetted before the next section
of lining is place. Construction joints shall be constructed whenever the
operation is halted for a period exceeding thirty (30) minutes. Welded wire fabric
reinforcing shall extend through the construction joint.
2. Expansion Joints
Transverse expansion joints shall be constructed at intervals of twenty
(20) feet and as located on the drawings. Expansion joints shall be filled with
premolded expansion joint filler material. The material shall have a minimum
thickness of 3/8 inch and shall conform to ASTM D 1751. Expansion joints shall
be edged with a 1/4-inch radius edging tool.
3. Contraction Joints
Transverse contraction joints shall be constructed at intervals of ten (10)
feet and shall be scored by troweling a groove 5/8 inch in depth and 1/4 inch in
width. All joints shall be true to a uniform line and neat in appearance.
33-4
33-10 PAYMENT
Payment for Pneumatically Applied Mortar shall be at the price bid per
square yard and shall be considered full compensation for doing all work and for
furnishing all labor, material, and equipment necessary to complete this item in
place. No additional compensation will be allowed for rebound.
34-1
Section 34
ELECTRICAL
34-1 GENERAL
The electrical work to be done consists of furnishing all labor, materials,
transportation, tools, equipment and appurtenances required for the complete
installation and testing of all electrical systems shown on the Plans, and as
specified in these Standard Specifications and Special Provisions.
All equipment, materials and supplies shall be new and currently
manufactured unless otherwise specified. All equipment shall be complete and
in operation to the satisfaction of the Engineer at the time of acceptance of the
work.
All incidental parts which are not shown on the Plans or specified herein
and which are necessary to complete the traffic signal and street lighting systems
shall be furnished and installed as though such parts were shown on the Plans or
specified herein.
For specifications not covered by these Standard Specifications, the latest
State of California Transportation Plans and Specifications shall apply.
34-2 RULES AND REGULATIONS
Electrical equipment furnished shall conform to the standards of the
National Electrical Manufacturers Association, the Underwriters’ Laboratories,
Inc., or the Electronic Industries Association, wherever applicable. All material
and work shall conform, where applicable, to the requirements of the National
Electrical Code; Title 8, California Administrative Code, Electrical Safety Orders;
Rules for Over Head Electrical Line Construction, General Order No. 95 of the
Public Utilities Commission; Standards of the American Society for Testing and
Materials (ASTM); American National Standards Institute (ANSI); and City of
Sacramento ordinances governing such types of construction.
34-3 EQUIPMENT LIST AND DRAWINGS
Unless otherwise permitted in writing by the Engineer, Contractor shall,
within twenty (20) days following notification of award of the Contract, submit
to the Engineer for approval a listing of equipment and material which he
proposes to furnish and install. The list shall be complete as to name of
manufacturer, size and catalog number of units, and shall be supplemented by
34-2
other data, including detailed scale drawings and wiring diagrams. All data shall
be submitted to the Engineer for review and approval.
Contractor shall submit to the Engineer a statement from each vendor
supplying electrical equipment, including but not limited to, traffic signal
controllers and cabinets, signal and pedestrian displays, pedestrian pushbuttons,
traffic signal standards, streetlight standards, luminaires, service pedestals,
conduits, conductors, pull boxes and all other electrical equipment indicating
that the orders for the materials required for this contract have been received
and accepted by said vendor. The confirmed date of delivery to Contractor shall
be indicated on the statement.
Prior to acceptance of the work, Contractor shall submit to the Engineer
a “Record Drawing” showing in detail all construction changes, especially
location and depth of conduit and completed schematic circuit diagram. All
construction changes, if any, shall be entered onto the Record Drawing by
Contractor at the end of each work day and the plan shall be available for
inspection by the Engineer at any time.
34-4 SCHEDULING OF WORK
Contractor shall submit a schedule of work to the Engineer or Inspector at
the pre-construction meeting and within 5 days of the Engineer’s written request
at any other time. The schedule shall show the order of work in which the
Contractor proposes to carry out the work, and the schedule shall show the
proposed dates of work.
Contractor shall not perform electrical work above ground at any location
until all electrical materials have been received by Contractor. Contractor may
place electrical service pedestals and underground infrastructure such as
conduit, pull boxes and foundations prior to receiving all electrical materials,
upon approval of the Engineer.
34-5 MAINTENANCE OF TRAFFIC AND PUBLIC SAFETY
Contractor shall have an approved traffic control plan showing proposed
traffic control measures and detours for vehicles and pedestrians prior to starting
any construction work. Contractor shall submit a proposed plan for review,
comments, and approval approximately ten (10) working days prior to the start
of any work.
Contractor shall furnish all labor, materials, tools, equipment, and
incidentals required for the maintenance of traffic and public safety to
adequately safeguard the general public and the work in accordance with the
requirements of Traffic Control Requirements of these Specifications.
34-3
34-6 EQUIPMENT TO BE SUPPLIED
All equipment, material and supplies called for in the Special Provisions
shall be new, free of defects, and currently manufactured items, unless
otherwise specified. All equipment shall be complete and in operation to the
satisfaction of the Engineer at the time of acceptance of the work.
All incidental parts which are not shown on the Plans or specified herein
and which are necessary to complete the project shall be furnished and installed
as though such parts were shown on the Plans or specified herein.
For Capital Improvement Projects, all equipment, materials, or supplies
to be considered as an approved equal must be submitted to the City for approval
no less than ten (10) calendar days prior to the bid opening date. If the City
finds said equipment, materials, or supplies to be acceptable, an addendum will
be issued notifying all bidders by the close of business on Friday before the bid
opening date. If there is no addendum accepting an approved equal, bidders
shall submit bids based on the original specified equipment, materials, or
supplies.
34-7 PROTECTION OF EXISTING IMPROVEMENTS
Existing improvements, utility and adjacent property shall be protected
from damage resulting from Contractor’s operations. All trees, shrubbery,
fences, walls, and other improvements including existing pavements, sidewalks,
street improvements and underground utilities and other improvements not to
be removed under this contract shall be protected from damage by Contractor
throughout the construction period.
Contractor shall notify the Traffic Signal Maintenance Section of the
Department of Transportation two (2) days prior to key cutting or planing within
three hundred feet (300’) of any signalized intersection to enable location of
buried detector or signal interconnect wiring to be identified.
All painted or other disfiguring markings on the pavement, sidewalk or
gutters shall be removed by Contractor before acceptance of the work.
Contractor shall be liable for costs or repairing damage to existing
improvements.
The contractor will ensure that utility services to customers in the project
area are maintained.
The Contractor is responsible for the protection of and for damage to
34-4
existing overhead and underground utility lines and services encountered
during the course of construction. The Contractor shall notify the respective
utility owner prior to any interruption of service.
The Contractor is expected to "pothole" existing underground utilities a
minimum of ten (10) working days in advance at any location where an existing
utility may be in conflict with the proposed work.
The cost of relocating existing overhead or underground utilities not
specified on Plans to be relocated, but which the Contractor elects to relocate
or cut and reconnect for his/her own convenience, shall be borne by the
Contractor.
34-8 MAINTAINING EXISTING ELECTRICAL FACILITIES
All existing streetlights and traffic signals shall be maintained in operation
until replacement standards are energized, as directed by the Engineer or
Inspector.
All new traffic signal heads and pedestrian signal heads installed but not
operational shall be entirely covered with burlap and securely tied to prevent
exposure of signal head face to vehicular or pedestrian traffic.
The modification of existing traffic signal intersections may require the
temporary shutdown of the traffic signals. Contractor shall take all steps
necessary to keep traffic signal intersection downtime to a minimum. The work
shall be scheduled so that the downtime of each intersection shall be four (4)
hours maximum and shall occur during the hours of 9 A.M. and 3 P.M. or as
directed by the Engineer. Contractor shall notify the Engineer five (5) working
days prior to a traffic signal intersection shutdown.
34-9 FOUNDATIONS
Concrete Foundations for ornamental streetlights shall conform to the
latest Caltrans Standard Specifications, Section 49 Cast-In-Place Concrete Piling,
unless otherwise specified.
Concrete Foundations for traffic signal standards shall conform to the
latest Caltrans Standard Specifications, Section 49 Cast-In-Place Concrete Piling
for Cast In Drilled Hole Concrete Piling, unless otherwise specified.
Concrete Foundations for service pedestal pads shall use the latest
Caltrans Standard Specifications, Section 87 for Concrete Pads, Foundations, and
Pedestals and Section 90 Minor Concrete, unless otherwise specified.
34-5
Foundations for traffic signal and streetlight standards shall be poured
monolithically. Grout shall be placed from the top of the foundation to the
bottom of the traffic signal standard. The exposed portion of the foundation
shall be formed to present a neat appearance. Tops of foundations for standards
shall be finished to curb or sidewalk grade as shown on the Plan or as directed
by the Engineer.
When a foundation is to be abandoned in place, the top of foundation,
anchor bolts and conduits shall be removed to a depth of two feet (2’) below the
surface of sidewalk or unimproved ground. The resulting hole shall be backfilled
with material equivalent to the surrounding material.
34-10 EXCAVATING AND BACKFILING
The excavations required for the installation of conduit, foundations and
other appurtenances shall be performed in such a manner as to cause the least
possible injury to the streets, sidewalks, and other improvements. All lawns or
improvements disturbed in excavating shall be replaced or reconstructed with
the same kind of material as found on the work or with materials of equal quality.
The trenches shall not be excavated wider than necessary for the proper
installation of the electrical appurtenances and foundations. Excavating shall
be performed immediately before installation of conduit.
The material from the excavation shall be placed in a position that will
not cause damage or obstruction to vehicular and pedestrian traffic nor interfere
with surface drainage.
Permission to cut or disturb the pavement in any street must be obtained
from the Engineer.
Whenever a part of a square or slab of existing concrete sidewalk or
driveway is broken or damaged or removed, the entire square or slab shall be
removed and replaced to the nearest score mark or joint.
For trenching in dirt, backfill material shall be placed in six inch (6”)
layers. Each layer of backfill shall be moistened as directed by the Engineer and
thoroughly tamped, rolled or otherwise compacted until the relative compaction
is not less than ninety-five percent (95%). Compacting of backfill material by
pounding or jetting will not be permitted.
The type of concrete used and its color shall match the adjacent concrete
construction. The cost of said concrete work will be at the expense of
Contractor. Concrete sidewalks shall have a minimum thickness of three and
34-6
one-half inches (3½”) and the minimum thickness of concrete driveways shall be
six inches (6”).
All surplus excavated material shall be removed and disposed of within
the same day of work. All sidewalks and gutters shall be washed down and swept
clean.
34-11 CONDUITS
Conduits to be installed shall be either rigid mild steel, hot dipped
galvanized conduits or Schedule 40 polyvinyl chloride conduit. The same type of
conduit shall be used for the entire system.
1. Requirement for Rigid Galvanized Steel Conduit
The rigid steel conduit and fittings shall be hot-dipped galvanized inside
and outside for corrosion resistance and shall be non-combustible and
specifically designed for underground, exposed outside use.
The rigid galvanized steel and fittings shall be thoroughly cleaned and all
burrs removed. The use of thin-wall conduit is specifically prohibited for
underground installation.
Exterior and interior surfaces of all conduit and fittings shall be uniformly
and adequately zinc coated by the hot-dipped galvanizing process.
The interior of the conduit shall have a continuous coating of lacquer or
enamel. Each length shall bear the label of Underwriters’ Laboratories, Inc. and
manufactured in accordance with ANSI. Installation shall conform to appropriate
articles of the Code.
Rigid steel conduits shall be a minimum of one and one-half inches (1½”)
in diameter. It will be the privilege of Contractor, at his own expense, to use
larger size conduit if desired. Where larger size conduit is used, it shall be for
the entire length of the run from pull box to pull box. No reducing couplings will
be permitted in any run. All conduit bends, except factory bends, shall have a
radius of not less than six (6) times the inside diameter of the conduit.
Where factory bends are not used, conduit shall be bent, with approved
hydraulic bender, without crimping or flattening, using the longest radius
practicable. All conduit ends shall be threaded and capped until wiring is
started. When caps are removed, conduit ends shall be provided with approved
grounding conduit bushings.
34-7
Conduit stubs, caps, exposed threads, and all standard screw joints shall
be painted with zinc rich paint or an equal rust preventive paint.
2. Requirements for Schedule 40 Polyvinyl Chloride Conduit
Polyvinyl chloride conduit (PVC) shall be ninety degrees (90°) C rated and
listed by the Underwriters Laboratories. Conduit shall be fabricated from
polyvinyl chloride and shall conform to NEMA Standards. It shall be in
conformance with Article 347 of the National Electrical Code. Conduit, fittings,
and cement shall be produced by the same manufacturer. Conduit shall meet
the crush rating listed in UL651 Standards. Schedule 40 conduit shall be rated
for use with 90 degree conductors.
All PVC conduits shall be a minimum of one and one-half inches (1½”) in
diameter. Where larger size conduit is used, it shall be for the entire length of
the run from pull box to pull box. No reducing couplings will be permitted in
any run. All conduit ends shall have the appropriate conduit bushing and shall
be sealed in an approved manner until wiring is started. Unless otherwise
specified, all PVC conduits shall contain a minimum of one No. 10 green ground
conductor.
Duct seal shall be installed on all conduits. All new conduits starting and
terminating in pull boxes shall have end bells.
High Density Polyethlene (HDPE) Conduit shall be manufactured to UL
651A specifications, compliant with NEC Article 353, and be of Schedule 40.
HDPE shall have high tensile strength to weight ratio, crush resistance, low
coefficient of friction for directional drilling.
3. Requirements for Conduit Installation
The installation of conduit in paved streets shall be accomplished by
directional drilling method or by trenching.
In sidewalk areas, conduit shall be laid to a depth of not less than eighteen
inches (18”) below the sidewalk grade. In all other areas, conduit shall be laid
to a depth of not less than thirty inches (30”) below the finished grade.
Conduit runs shown on the Plans to be located in the street, under street
pavement, shall be installed in the street within a minimum of twelve inches
(12”).
When a conduit is shown on the Plans as lying in a straight line parallel to
the curb line, sidewalk, or pavement edge, it shall not deviate more than six
inches (6”) to either side of the designated straight parallel line.
34-8
In order to determine that conduit is laid to the correct depth and in as
straight a line as possible, Contractor shall cause test or pilot holes to be dug at
a spacing of not over seventy-five feet (75’) and no such hole shall be backfilled
until approved by the Engineer or his representative.
The bending of PVC conduit shall be by a hot box bender, and in lieu of
jacking or boring, PVC conduit shall be installed by the drill rod method in which
a drill rod is first installed and the PVC is pulled into the cavity made by the
drilling rod as the rod is removed. At locations where conduit is not installed by
the said trenching method, the conduit shall be installed by the drill rod method.
Before any wire is pulled in the conduit system, all conduit shall be free
of any foreign material that is in the conduit. The removal of foreign material
from the conduit with compressed air is approved.
Conduit entering controller cabinet or service cabinet shall be sealed by
the use of a sealing compound approved by the Engineer.
Conduits terminating in pull boxes, standards, pedestals, and cabinets
shall rise vertically and shall not slope in any direction. Conduits terminating in
standards, pedestals, and cabinets shall terminate one and one-half inches (1½")
above finished grade. Conduits shown on the Plans to be adjacent and parallel
to each other shall be installed in the same trench or drill hole unless otherwise
specified or directed by the Engineer.
Contractor shall replace roadway striping and markings with same
material if damaged by directional drilling, bore pits, potholes, or trenching.
Replacement striping and markings shall be thermoplastic or paint, per the City
of Sacramento Standards.
The installation of conduit in lawn areas shall be done by approved boring
method or by trenching. If trenching is used, Contractor shall first remove the
sod before trenching. All sod removed shall be replaced within forty-eight (48)
hours.
4. Trenching Installation of Conduit in Paved Streets
For trenching in roadway, the Contractor shall use the City of Sacramento
“T”-trench method.
Trenches shall be backfilled or covered at the end of each work day. All
conduit installed by trenching shall be anchored every 10 feet to the bottom of
the trench, with an approved method, to prevent the conduit from floating when
the concrete is backfilled into the trench.
34-9
Trenches in reconstructed roadways shall be backfilled with Slurry Cement
Backfill as defined in Section 10 of these Standard Specifications. A red oxide in
the amount of 5 lbs. per cubic yard shall be mixed uniformly throughout the
slurry cement.
Trenches in existing roadways shall use the “T-Trench” method. The
portion over the trench shall be paved with City Standard asphalt concrete, per
Section 22 of the City Standard Specifications. Trenches shall be backfilled
with Slurry Cement Backfill as defined in Section 10 of these Standard
Specifications. A red oxide in the amount of 5 lbs. per cubic yard shall be
mixed uniformly throughout the slurry cement.
Trench shall not exceed six inches (6”) in width. The top of the installed
conduit shall be a minimum of twenty-four inches (24”) below finish grade.
The outline of all areas of pavement to be removed shall be cut to a
minimum depth of four inches (4”) with an abrasive type saw or with a rock
cutting excavator specifically designed for this purpose. The outline area shall
extend 6” beyond both sides of the conduit trench (6” in maximum).
Cuts shall be neat and true with no shatter outside the removal area.
Contractor shall not cut with saw or rock cutting excavators within 24 inches of
either side of located or marked buried electrical conduit. At these locations
Contractor shall daylight or pothole to continuing a saw cut.
The trenching machine shall be shielded to prevent loose material from
being thrown away from the machine. Loose material deposited on the
pavement behind the cutting machine shall be removed from the pavement
immediately and the pavement cleared to allow the passage of traffic. Only
those traffic lanes occupied by the cutting machine and the cleanup operation
shall be closed and they shall be opened as soon as the work has moved
sufficiently to clear them.
Spreading and compacting of asphalt concrete shall be performed by any
method which will produce an asphalt concrete surfacing of uniform smoothness,
texture, and density.
Excavation, installation of conduit and concrete backfill shall be
completed within the same working day. Asphalt concrete backfill shall be
completed within twenty-four (24) hours after excavation of trench.
Upon completion of all contract work, the trenches cut through existing
pavement will be inspected and, if found necessary by the Engineer, they will be
brought to grade with an appropriate asphaltic concrete mix. In addition to
34-10
bringing the trenches to grade, the Engineer may require a twelve inch (12”)
wide fog seal centered over the trench pavement or between the trench
pavement and the existing street pavement.
5. Directional Drilling Method of Conduit in Paved Streets
Conduits shall be installed such that the top of the conduit(s) are not
less than eighteen inches (18”) below the finished grade in sidewalk areas and
not less than thirty inches (30”) in all other areas except as otherwise specified
or directed by the Engineer.
Prior to the start of directional drilling, the Contractor shall submit a
plan which identifies location and size of proposed drill holes, describes
process for identifying/locating existing utility services and other underground
utilities or obstructions, identifies a proposed “drilling corridor” to avoid
conflicts with existing utilities, services and other facilities. This plan shall be
submitted to the Engineer a minimum of ten (10) working days prior to the
start of work. The Contractor will not be allowed to directional drill until an
approved plan is on file with the Engineer
Directional drilling shall be performed by the technique of creating and
directing a bore hole along a predetermined path to a specified targeted
location where indicated on the plans to install conduits. The technique shall
involve the use of mechanical and hydraulic equipment to change the boring
course and shall use instrumentation to monitor the location and orientation of
the boring head assembly along the predetermined course. Drilling shall be
accomplished with fluid-assisted mechanical cutting. Unless otherwise
approved, boring fluids shall be a mixture of bentonite and water or polymers
and additives. Bentonite sealants and water will be used to lubricate the
drilling head. It is mandatory that minimum pressures and flow rates be used
during drilling operations so as not to fracture the subgrade material around
and/or above the bore. Uncontrolled jetting (where the primary purpose is to
use fluid force to erode soil for creation of the final bore hold diameter) is
prohibited. The drilling system shall utilize small-diameter fluid jets to
fracture, and mechanical cutters to cut and excavate the soil as the head
advances forward.
All drilling shall be located a minimum of three feet (3’) from the center
of all existing maintenance holes. Drilling that run parallel to any sanitary
sewer or storm drainage lines shall maintain a minimum clearance of three feet
(3’) measured from the centerline of the sewer or drainage line to the adjacent
side of the drill hole. Drilling that crosses any sewer or drainage line shall cross
at 90 degrees to the line or at a minimum of 45 degrees if a 90 degree crossing
is not possible.
34-11
Each bore pit shall be restored to original roadway conditions.
34-12 PULL BOXES
Pull boxes shall be installed in the sidewalk at the locations shown on
the Plans or at locations designated by the Engineer at site of work. When pull
boxes are shown on the plans or designated by the Engineer to be in the
sidewalk the entire square or slab shall be replaced as specified in section 34-9
of these specifications. Contractor shall cut, remove, and replace the concrete
to the nearest joint when installing new pull boxes. For pull boxes to be
removed, holes or depressions resulting from the removed pull box shall be
filled, compacted, brought to grade, and filled to match surrounding materials.
Pull boxes shall be precast reinforced concrete boxes, unless otherwise
noted. Each box shall be set in concrete with a minimum of six inches (6”) of
concrete on all four sides. The six inch (6”) thick sides shall be a minimum of
twelve inches (12”) deep. The pull box shall rest on crushed rock foundation.
The crushed rock foundation shall have a minimum of 12” of depth and extend a
minimum of 6” beyond the outside edge of the pull box. Compact crushed rock
while maintaining integrity of conduit. Conduit and pull box shall not be
damaged nor cracked.
All new pull boxes shall be set in place prior to pouring any new
sidewalk.
Concrete pull box covers shall be protected during construction.
Damaged covers must be replaced with new covers by the Contractor.
Existing pull boxes damaged by the installation of new conduits shall be
removed and replaced at the Contractor's expense as directed by the Engineer
For traffic signal systems, pull boxes shall have reinforced concrete covers
and shall be inscribed “Traffic Signals”. Locking pull box lids are not permitted
to be used for traffic signal systems, unless otherwise specified by the Engineer
or shown in the Plans.
For street lighting systems, pull boxes shall have galvanized steel locking
security lids, unless otherwise specified by the Engineer or shown in the Plans.
Pull boxes shall not be set in driveways, vehicular traveled lanes or in any
part of a new sidewalk curb ramp area including the sidewalk ramp area of ADA
compliant driveways.
Where SMUD service points are designated on the plans, pull boxes for
SMUD service conductors shall meet SMUD specifications.
34-12
Unless otherwise specified, all pull boxes for street lighting systems shall
be CALTRANS Standard No. 5 size, and all pull boxes for traffic signal systems
shall be CALTRANS Standard No. 6, unless otherwise specified in the Plans. Pull
box extension shall be furnished and installed where called for on the Plan.
Where a pull box extension is to be installed over the ends of existing conduits,
the conduit ends shall be raised or lowered so they will be a minimum of five
inches (5”) and a maximum of seven inches (7”) below the underside of the pull
box cover. No more than two (2) extensions may be used.
34-13 CONDUCTORS
Unless otherwise specified, conductors shall be single conductor, solid or
stranded copper of the gauge shown on the Plans. Wire sizes shall be based on
American Wire Gauge (AWG). Copper wire shall conform to the applicable
portions of ASTMs B3 and B8. Contractor shall use color coded wires, using a
different color for each circuit with continuous color maintained throughout each
circuit. Color coding shall be as required by the Engineer or as detailed on the
Plans or Special Provisions. Where permitted by the Engineer, conductor of the
same color may be used on different circuits. These conductors shall be
identified with approved metal tags.
Traffic signal and multiple circuit lighting conductors shall be rated for
600 volt operation. The insulation for the conductors shall be Type THW.
Insulation types THHN and THWN are not approved for installation.
All conductors of AWG #10 or larger (such as #1, #6, #8, #10) shall be
identified by printed and embossed labels, unless otherwise specified in the
Plans or by the Engineer. Both printed and embossed labels shall clearly
identify the UL listing, insulation type, voltage rating, AWG number, and the
City of Sacramento. The printed label and the embossed label shall be placed
at approximately 90 degrees separation around the center of the conductors.
Labels shall appear every one foot interval. Embossed labels shall be between
0.002” to 0.003” in depth and shall not damage the conductors. Label heights
shall be no less than 3/32” for AWG #8 or larger, and shall be no less than
2/32” for AWG #10.
Three feet of slack conductors shall be provided in pull box.
34-14 DETECTOR LOOP AND HANDHOLE
Detector loop installation includes installing conductors, sealant, conduit,
detector handholes, and pull boxes.
34-13
1. Detector Loop Conductors
Each loop conductor shall be continuous, un-spliced, RHW-USE neoprene
jacketed or Type USE cross-linked polyethylene insulated No. 12 stranded copper
wire. Conductor insulation thickness shall be 40 mils minimum.
2. Detector Loop Conductor installation
Loop Conductor installation shall conform to the Caltrans Standard Plans.
Detector loops shall be installed in the center of traffic lanes. Splices are not
permitted in the detector loop.
Each loop shall have three (3) turns of conductors for each detector loop.
Unless otherwise shown or noted on the Plans, each new detector loop shall be
centered in the travel lane.
Slots cut in the pavement shall be blown out with compressed air and
dried and inspected for any sharp objects or corners which shall be removed prior
to installation of loop conductors.
Test each loop for continuity, circuit resistance, and insulation resistance
before filling the slots with sealant.
Remove excess sealant from the adjacent road surface before it sets. Do
not use solvents to remove the excess.
Loop conductors shall be installed without splices and shall terminate in
the nearest pull box. The detector loops shall be joined in the nearest pull
box. Final splices between loops and lead-in cable shall not be made until the
operation of the loops under actual traffic conditions is approved by the
Engineer. Each detector loop shall be identified and tagged by loop number,
start (S), and finish (F). For example: Phase 4D1-1S & Phase 4D1-1F; Phase
4D1-2S & Phase 4D1-2F.
All loop conductors for each direction of travel for the same phase of a
traffic signal system in the same pull box, shall be spliced to a cable which
shall be run from the pull box adjacent to the loop detector to the input panel
mounted in the controller cabinet. Splices between loop conductors and lead-
in cable shall be made in pull boxes only. All splices to the lead in cable and
between loops and the lead in cable shall be soldered.
Each detector loop circuit shall be tested for continuity, circuit
resistance, and insulation resistance at the controller location. The loop
circuit resistance shall not exceed 0.50 ohms plus 0.35 ohms per 100 feet of
lead-in cable. The insulation resistance shall be performed between each
34-14
circuit conductor and ground. The megger resistance shall not be less than 200
megohms. The Contractor shall replace any detector loop that fails this
requirement at the Contractor's expense.
All conductors and conductor loops installed in the traveled way shall be
installed so that the top of the conductor is a minimum of one-inch (1") below
the surface grade of the street.
Asphaltic Emulsion Sealant shall be used immediately after the loop
wires have been installed that conforms to Caltrans Standard Specifications.
Dry 20 mesh sandblasting sand shall then be poured in and around the slot. A
suitable and approved tool shall then be used to work the asphaltic emulsion up
through the dry sand. The slot will then be inspected for any dry spots in the
sand fill. Any dry sand spots will then be wetted with more asphaltic emulsion.
More dry sandblasting sand shall then be added to the slot and the asphalt
emulsion will again be worked up through the sand until a uniform mix of
asphaltic emulsion and sand with no voids completely fills the slot to the level
of the surrounding road surface. A final thin layer of sand will then be added
to surrounding surface to absorb the excess asphaltic emulsion. The traveled
way may be opened to vehicular traffic immediately after installation of the
asphaltic emulsion and sand loop sealant.
Hot Melt Rubberized Asphalt Sealant shall conform to and installed in
accordance with Caltrans Standard Specifications.
3. Detector Lead-In Cable
Detector lead-in cable shall consist of four (4) No. 18 A.W.G. stranded
copper conductors insulated with nine (9) mils minimum of polypropylene,
color coded, parallel laid, twisted together with four to six turns per foot. An
amorphous interior moisture penetration barrier shall be provided to prevent
hosing, siphoning, or capillary absorption of water along cable interstices. The
outer jacket shall be thirty (30) mils minimum in thickness, high density
polyethylene conforming to ASTM Designation: D-1248, 65T for Dielectric
Material, Type I, Class C, Grade 5, J3. The diameter of the cable shall be
approximately .25 inch. Aluminum-polyester shielding shall be applied around
the conductors. The detector lead-in cable shall be continuous from the pull
box adjacent to the conductor loops to the controller unless otherwise shown
on the Plans.
Splices between lead-in cable and loop cable shall be made in pull boxes
only. All splices to the lead in cable shall be soldered. The ends of the splice
shall then be inserted into an approved insulated spring type connector of the
correct size. When detector cables and detector loops are initially installed,
precautions shall be taken to ensure the cables and loops remain water tight
34-15
prior to splicing. If splicing is not to be done immediately after installation,
the ends of the conductors and cables shall be dipped in electrical insulating
liquid which shall render them water tight. The insulating liquid shall be fast
drying, resistant to oils, acids, alkalies and corrosive atmospheric conditions
and shall be compatible with the insulations used in the conductors and cables.
All conductors and cables shall be installed and splices shall be made in a dry
environment.
4. Detector Handholes
Detector loops shall be sawcut into detector handholes. Detector
handholes shall be Caltrans Type B. No splicing will be allowed in the detector
handholes. For detector handholes to be removed, holes or depressions
resulting from the removed handhole shall be filled, compacted, brought to
grade, and filled to match surrounding materials.
5. Abandonment of Loop Conductors.
Each detector loop shall be saw-cut in a minimum of two places.
34-15 WIRING
Pulling wires shall be accomplished with special care to avoid damage to
the insulation. Hand power only shall be employed in pulling wire. Only
lubricant shall be used. Loops or bends in wires in the base of standards and pull
boxes shall have a minimum radius of five (5) times its diameter, to ensure the
safety of the insulation.
A minimum of thirty-six inches (36”) of slack in each wire shall be left in
each standard base and pull box.
Conductor splices in the pull box shall be joined by a pigtail splice using a
wire nut. All splices shall be taped in a manner approved by the Engineer. After
the splice is taped, it shall be dipped in a moisture and corrosion resistant outer
seal. All splices shall be left with ends pointed up to allow water to run off of
splice.
Soldering of pressure connectors may be omitted provided the connectors
are applied with a ratchet type crimping tool which will not release the
connector until the crimping operation is completed. The sleeve shall be
compressed on each end.
34-16
34-16 BONDING AND GROUNDING
All metal conduit systems, standards, pedestals, ballast and transformer
cases, service equipment, anchor bolts, etc., shall be made mechanically and
electrically secure to form a continuous system and shall be effectively
grounded. Grounding shall be in accordance with all applicable codes and
regulations. Bonding and grounding jumpers shall be copper wire or copper strap
with a minimum cross sectional area equivalent to a No. 8 AWG.
Bonding wire or strap shall be secured to the lower section of metal
standard by brass or bronze bolts three-sixteenths inch (3/16”) or larger.
In conduit systems where rigid steel conduit and PVC conduits are mixed,
the following requirements apply:
1. The rigid steel conduit shall have an approved grounding bushing installed
at the conduit end(s).
2. The green No. 10 grounding conductors in the PVC conduit shall be
attached to a grounding bushing which shall be attached to the rigid steel
conduit.
34-17 ELECTRIC SERVICE
The locations of service points shown on the Plans are approximate only.
Contractor shall determine the exact locations from the Sacramento Municipal
Utility District (SMUD). Service conduits, service conductors, service grounds,
metering and transformer pads where required shall be installed in accordance
with the SMUD requirements. Service equipment and enclosure shall be
furnished and installed as detailed on the Plans and/or specified in the Special
Provisions.
34-18 SERVICE PEDESTALS
Service Pedestals shall be of the type called for on the Plans. Pedestal
shall be fabricated from 14 gauge stainless steel and 14 gauge cold rolled steel
electrically welded and reinforced. Construction will be Type 3R, raintight. All
nuts, bolts, and screws shall be stainless steel. Enclosure will be factory wired
and conform to NEMA and UL Standards. Each circuit breaker shall be
permanently marked with its trip rating. Multipole breakers shall be of the
common trip with single handle. Unless otherwise specified, each circuit breaker
shall be equipped with a device for padlocking the breaker in the “on” or “off”
position.
34-17
Unless otherwise specified, enclosures of service pedestals shall be
fabricated from code gauge stainless steel or powder coated steel. Enclosures
shall be stainless steel.
34-19 STANDARDS
All traffic signal standards and pedestrian push button assembly posts shall
be manufactured to the latest Caltrans Specifications, unless otherwise specified
in the Plans.
The locations of standards for traffic signals and street lights shown on
the Plan are approximate only. The exact location of each standard will be
determined by the Engineer prior to installation. Each standard shall be anchored
to the concrete foundation by galvanized steel anchor bolts, nuts, leveling nuts
and washers in accordance with the Plans and the standards shall be installed in
a true vertical position.
34-20 FIELD TEST OF STREETLIGHTS
Prior to acceptance of the work, Contractor shall perform the following
tests to be made:
1. For continuity of each circuit.
2. For grounds in each circuit.
3. A megger test on each circuit.
4. A functional test in which it is demonstrated that each and every part of
the system functions as specified or intended herein.
5. Contractor shall supply the temporary power source necessary to facilitate
the functional test as specified above.
34-21 INTERCONNECT
Traffic signal interconnect cable shall be fiber optic cable. The size,
type, and termination type of fiber optic cable shall be per Plan, comply with
the latest City of Sacramento Standards, department policies and City of
Sacramento Standard drawings.
All fiber optic splices shall be in splice boxes, maintenance holes or signal
cabinets. Fiber optic splices in #5 or smaller pull boxes will not be allowed. All
fiber optic cable shall be terminated in a signal cabinet, communication hub or
splice case or as noted on plans
When a contractor damages the existing traffic signal interconnect cable,
the interconnect shall be replaced with fiber optic cable to latest City of
Sacramento Standards, department policies and City of Sacramento Standard
34-18
drawings. In-kind replacement of legacy (copper) traffic signal interconnect
systems will not be allowed. Contractor is responsible to provide necessary
materials to terminate the replaced cable to a panel in the signal cabinet,
commination hub or in a splice case to existing cable.
When a contractor damages existing copper interconnect in a corridor
where a parallel fiber optic path exists, contractor shall abandon existing copper
interconnect cable and establish communication on the existing fiber optic cable
at all locations affected by the damaged copper interconnect. Work included in
establishing fiber optic communication may include, but not limited to, splicing
a 12 strand fiber optic drop into existing fiber optic cable, providing fiber patch
panel equipment in existing cabinet or terminating additional fiber optic strands
on existing fiber optic patch panel.
34-22 TRAFFIC SIGNAL HARDWARE
All vehicle signal displays, pedestrian displays, backplates, and framework
shall be powder coated black. All vehicle signal displays shall be aluminum and
12” diameter sections. Signal visors shall be aluminum and tunnel. All
backplates shall be aluminum and louvered. Pedestrian displays shall be
aluminum and 16” housing. The modules of the signal and pedestrian display
shall conform to the latest City of Sacramento Standards and Special Provisions.
34-23 VEHICLE AND BICYCLE DETECTION
Vehicle and bicycle detection is required at all intersections per the
latest edition of the California Manual on Uniform Traffic Control Devices or as
directed by the City Traffic Engineer and shall comply with the latest City of
Sacramento Standards, department Policies and City of Sacramento Standard
drawings. Presence detection shall be non-intrusive unless approved be the City
traffic engineer. For approaches with speeds of 30 mph or higher, advance
detection systems shall be provided per the latest City of Sacramento Standards.
When construction activities disturb or damages existing in-pavement
vehicle and bicycle detection systems, the detection shall be replaced and
installed per current Sacramento Standards, department Policies and City of
Sacramento Standard drawings. New or temporary detection shall be in-place
and functional prior to construction activities that will damage existing detection
systems. In-kind replacement of legacy vehicle and bicycle detection systems
will not be allowed.
34-24 TRAFFIC SIGNAL CONTROLLER ASSEMBLY TESTING AND INSPECTION
Traffic signal controller assembly is defined as a fully wired traffic signal
cabinet with traffic signal controller and conflict monitor installed and
34-19
programmed. All equipment as shown on the Plans or called for under the special
provision and these specifications shall be installed and operable, including, but
not limited to, Emergency Vehicle Preemption, fiber optic, network switch, and
CCTV equipment. All cabinet wiring and input/outputs shall be clearly and neatly
labeled.
All new traffic signal controller assemblies must be on the City of
Sacramento approved product list. For products not on the approved product
list, it must be submitted to the City of Sacramento for testing and approval prior
to be added to the approved products list. Test cabinets must be delivered to
City of Sacramento Corporate Center South 5730 24
th
Street Sacramento, CA.
95822 approximately 6 months prior to installation in the field.
For all new traffic signal controller assemblies installed on new
foundations, the contractor shall install a fully tested controller assembly. The
controller assembly shall be tested for full operation (full I/O) and running
approved signal timing. The controller assembly shall be configured per the
intersection plans or as directed by City Traffic Engineer. Once installed the
assembly shall be energized and input wiring terminated and labeled. The Traffic
Controller shall have the latest firmware installed and registered to City of
Sacramento. City will perform a functional test on the controller assembly per
the intersection plan. Contractor shall schedule the test upon the approval of
the Engineer. Included as a part of the functional test is the continuous
operation of the controller assembly for a minimum of five (5) working days. Any
part of the controller assembly that does not operate properly shall be repaired
and retested by the contractor. Contractor shall schedule a retest upon the
approval of the Engineer.
For all traffic signal controller assemblies installed on existing
foundations, the traffic signal controller assemblies shall be tested by the City
prior to installation in the field. Traffic signal controller assembly shall be
delivered to City of Sacramento Corporate Center South 5730 24
th
Street
Sacramento, CA. 95822 approximately 30 days prior to installation in the field.
Contractor shall request controller timing 10 days prior to controller assembly
being delivered to City of Sacramento Corporate Center. Controller shall have
the latest firmware installed and registered to City of Sacramento. City will
perform a functional test on the cabinet assembly per the intersection plan.
Contractor shall schedule the test upon the approval of the Engineer. Included
as a part of the functional test is the continuous satisfactory operation of the
controller assembly for a minimum of five (5) working days. Any part of the
controller assembly that does not operate properly shall be repaired and re-
tested by the contractor. Contractor is responsible for retrieving the traffic
34-20
signal controller assembly, repairing and delivering the repaired assembly to City
of Sacramento Corporate Center. Contractor shall schedule a retest upon the
approval of the Engineer.
34-25 TRAFFIC SIGNAL PRE-TURN ON
A Minimum Five (5) working days prior to the final traffic signal
intersection turn on, Contractor shall complete the City’s Traffic Signal turn-on
checklist. The Contractor shall be prepared to complete turn-on checklist in the
presence of City Engineer or Inspector. After Completion of checklist the
contractor shall schedule the traffic signal pre-turn on meeting to ensure project
readiness. During the traffic signal pre-turn on meeting the contractor shall
perform functional test of all applicable items on the checklist, including but not
limited to:
1. All vehicular and pedestrian displays shall be flashed out (individually turned
on momentarily) and proper operation and phasing shall be checked. All
vehicular and pedestrian signal heads shall be properly adjusted and covered.
2. The controller shall be turned on with the vehicle and pedestrian indications
turned off, all pedestrian pushbuttons, vehicle and bicycle detector inputs
shall be checked for proper operation and per phasing shown on the plans.
3. Controller shall have latest software version, registered to City of
Sacramento, installed and operating per City Standards and the Engineer.
4. Conflict monitor is operational and programmed correctly per the
intersection plan.
5. All termination, communication, preemption and CCTV equipment has been
provided per special provisions and plans and is installed and is powered on.
6. Verify all input/output are fully functional, labeled and complete.
If any system component, circuit or communication device does not
operate properly, it shall be repaired and retested prior to final traffic signal
intersection turn on. After the successful completion of all pre-turn on tests,
34-21
Contractor shall request through the City Traffic Engineer, a time and date for
final turn on.
34-26 TRAFFIC SIGNAL FINAL TURN ON
The traffic signal final turn on can only occur between the hours of 9 A.M.
and 3 P.M. on Tuesday, Wednesday or Thursday and during a week without
holidays. Contractor shall give the Engineer at least five (5) working day notice
prior to the traffic signal final turn on. Final traffic signal turn on shall not be
scheduled until the City Traffic Engineer has accepted the pre-turn on checklist.
The final traffic signal turn on date shall be subject to the approval of the
City Traffic Engineer. Contractor shall make arrangements to have a City signal
technician and a technician from the controller manufacturer, or his
representative, qualified to work on the controller, present at the time of traffic
signal intersection turn on.
Final signing, striping and stop bar shall be installed no earlier than one
business day prior to turn-on date. All traffic signal and pedestrian displays
shall remain bagged until day of final turn on.
Contractor shall provide sufficient personnel and equipment for the timely
completion of the traffic signal intersection turn on. If the Contractor does not
provided sufficient personnel and equipment, the Engineer may postpone the
traffic signal turn on until sufficient personnel and equipment are provided by
the Contractor.
If any system component, circuit or communication device is determined
to be non-compliant, it shall be resolved by the contractor to meet City of
Sacramento Standards. All non-compliance items must be resolved within 5
working days.
34-27 SALVAGE
The Contractor shall schedule the delivery of salvaged equipment with the
City Inspector. Equipment drop-off shall be done in the presence of the City
Inspector or designated representative.
All salvageable material and equipment removed from present installation
which is not to be re-installed shall be delivered in good condition to the City
Corporation Yard at 5730 24
th
Street, Sacramento, California or the City
Corporate Center North 918 Del Paso Road, Sacramento, California as directed
by the Engineer. Contractor is responsible to provide machinery and manpower
34-22
to unload and load all salvaged equipment and materials. Loading, unloading,
pick-up and delivery of these items shall be included in the price bid for various
items and no additional compensation will be allowed therefore.
Contractor shall remove all signal heads, mounting brackets, luminaires,
mast arms and appurtenances from all salvaged traffic signal and street lighting
standards prior to delivery to the City Corporation Yard.
Contractor shall provide for the safe transfer with no damage to the
salvaged equipment. Any equipment broken or lost by the Contractor shall be
replaced with equipment of equal quality at the expense of the Contractor.
35-1
Section 35
LANDSCAPE PLANTING
35-1 GENERAL
Landscape planting shall consist of preparing and planting the areas
shown on the Plans or specified in this Section and the Special Provisions.
Unless otherwise provided, walls, curbs, planter boxes, walks, irrigation
systems and similar improvements required by the Plans and Specification shall
be constructed per the grading, layout, and irrigation plans and before
landscaping.
All work on the irrigation system, including hydrostatic and coverage
tests, preliminary operational tests of automatic control system, and the back
fill of trenches, and other excavations shall be performed before planting.
35-2 CERTIFICATE OF COMPLETION
A Certificate of Completion must be furnished to the Engineer at the end
of project per the City of Sacramento Water Conservation Ordinance 15.92.130.
This document is required for all new construction project with an
aggregate landscape area equal to or greater than 500 square feet of irrigated
landscape area. For rehabilitation project this document is required for irrigation
landscape areas equal to or greater than 2,500 square feet.
35-3 MEASUREMENT OF QUANTITIES
Measurement of Quantities shall be determined by the Engineer based on
delivery tags presented at time of delivery unless otherwise indicated in the
Contract Documents. Contractor shall give four-eight (48) hour notice of all
delivery dates and times. Materials delivered at such times that the Engineer is
not present will not be counted, unless the contractor is able to provide the City
with tags for all materials delivered to the site.
35-4 MATERIALS
Materials shall conform to the provisions of Section 10 of these
Specifications.
35-5 PREPARING PLANTING AREAS
The work involved in preparing planting areas shall be so conducted that
35-2
existing flow lines will be maintained. Material displaced by Contractor’s
operations which interferes with drainage shall be removed and disposed of as
directed by the Engineer.
Contractor shall perform a laboratory soil analysis to determine what
amendments and method of application are required to support trees, shrubs
and groundcovers, seeds and sod identified on the landscaping plan. Contractor
shall submit this soil fertility analysis upon completion of rough grading for
approval. For native soil, samples of area to be landscaped shall be taken at the
locations shown on the plans, directed by the Engineer or specified in the Special
Provisions. For imported soil, one sample for every 100 cubic yards shall be
taken. A laboratory soil analysis is not required for non-irrigated native grass
areas.
The samples shall be place in a sturdy container, properly identified,
labeled, numbered and dated and delivered to a soils laboratory. Results of the
analysis shall be provided to the Engineer and Contractor. The recommended soil
amendments and methods of application shall be approved by the Engineer prior
to adding them in the soil. All cost to perform the analysis and prepare the report
will be paid by Contractor.
Soil shall be cultivated until the condition of the soil is loose and fine-
textured to a depth of six inches (6”). The top two inches (2”) shall be cleared
of all stones larger than one inch (1”) in diameter and debris. Soil amendment
shall be applied as shown on the plans or identified in the Special Provisions.
The contractor shall provide proof of soil amendment application to the Engineer
or Project Inspector. This text shall be completed at the contractor’s expense.
The contractor shall not drive heavy equipment over the areas where the soil has
been cultivated with the amendments. If heavy equipment is parked or driven
over the soil amended area then the contractor will be required to re-cultivate
the top six inches (6”) of soil prior to planting. Contractor shall provide proof of
soil conditioner application to the Engineer or Project Construction Inspector.
Weeds shall be sprayed with an approved chemical, which controls both
broadleaf plants and grasses, but which will not contaminate the soil.
The use of rubber-tired equipment will be permitted for cultivating
operations, provided that any compaction caused by the equipment used is
completely eradicated, to the satisfaction of the Engineer or Landscape
Architect.
35-6 WEED AND PEST CONTROL
Prior to planting all weeds including bermuda grass in the areas to be
planted with trees, shrubbery and groundcover, seeds and sod shall be
35-3
completely killed with a post emergent systemic herbicide and removed. After
planting, all areas, except seed and turf areas, shall be treated with a pre-
emergent as approved by Engineer or Landscape Architect. Application of all
herbicides shall be in accordance with the manufacture’s recommendations or
per a pest control advisor (PCA) recommendations.
Before applying any pesticides, Contractor shall provide the Engineer or
Landscape Architect written recommendations from a licensed pest control
advisor and the Engineer or Landscape Architect shall provide Contractor written
approval for the materials to be used, the rate of application, method of
application, name of applicator and area to which material is to be applied. If
special permits are required for the materials to be used, they shall be obtained
from the Department of Pesticide Regulations submitted with the request for the
use of the materials.
35-7 PLANTING TREES
Plantings shall consist of furnishing, preparing, and planting trees in
accordance with these provisions, Section 10, and the Contract documents and
as directed by the Engineer or Landscape Architect.
1. Preparing of Planting Areas shall conform to Section 35-5.
Soil in lawn areas adjacent to paved areas shall be graded so that after
settlement, the soil will be one half inch (½") below the top of the paving.
Weed Control shall conform to Section 35-6
2. Trees and Planting Materials
a. Trees shall be located as shown on the plans. Proposed tree
locations shall be field staked by Contractor prior to planting,
subject to the approval of the Engineer.
No tree planting will be allowed until all soil amendment delivery
tags are received and quantities used are approved by the Engineer.
Planting trees will not be allowed in any area which in the opinion
of the Engineer or Landscape Architect is unsuitable for planting.
a. Finish grade of all planting areas shall be reviewed and approved
by the Engineer or Landscape Architect before proceeding with
planting.
b. Trees shall have a planting pit twice the diameter of the root ball.
Root defects such as circling or girdling roots shall be corrected at
35-4
the time of planting by cutting or scoring the root ball. Trees that
are severely root bound to the point where cutting or scoring the
root ball would not be effective shall be rejected and replaced with
healthy specimens, at the discretion of the engineer.
c. Plant Schedules shown on the plans are for Contractor’s
convenience only. Contractor shall confirm all quantities and shall
plant as required by the Planting Plan when discrepancies exist.
d. Trees shall be of the variety and size as shown on the plans and
shall conform to Sections 10-43 and 35-7.
e. Tree support staking shall be installed at the time the trees are
planted. Stakes shall be placed and the trees shall be tied
thereto. The size and number of stakes and ties to be installed
shall be as shown on the tree planting detail. Stakes shall be
placed against but not through the root ball. All tree nursery
stakes shall be removed at the time the trees are planted and
prior to the project acceptance.
f. Trees shall be secured to their supporting stakes with tree ties
made of waterproof vinyl-impregnated nylon material that is
approximately one inch (1”) wide and has a tensile strength of
approximately 300 lbs. Substitutions must be approved by the
Engineer.
35-8 PLANTING SHRUB AND GROUNDCOVER AREAS
Plantings shall consist of furnishing, preparing, and planting shrubs and
groundcover in accordance with the following provisions, Section 10, and as
directed by the Engineer or Landscape Architect.
Where shrubs are shown on the Plans to be planted in groups, the outer
rows shall be parallel to the nearest pavement or fence. Adjustment in the
number or alignment of plants shall be made between the outer rows. Outer row
plantings shall be adjusted so at plant maturity they will not encroach onto
curbs, sidewalks or fences.
No more plants shall be placed at planting locations on any day than can
be planted and watered on that day.
Containers shall be cut and plants shall be removed from the containers
in such a manner that the ball of earth surrounding the roots remains intact, and
they shall be planted and watered as hereinafter specified immediately after
removal from the containers. Containers shall not be cut prior to delivery of the
35-5
plants to the planting area. Plants that are root bound shall have the root ball
scored to prevent continued restriction of the root growth.
Roots of plants not in containers shall be kept moist and covered at all
times, and shall not be exposed to the air except while actually being placed in
the ground.
Plants shall be set in the backfill material in flat bottomed holes to such
depth that after the soil has settled the top of the plant ball will be one inch
(1”) above the bottom of the basin or even with the surrounding soil where there
is no basin. Plants shall be planted in such a manner that the roots will not be
restricted or distorted. Soil shall not be compacted around the roots or ball of
the plant during or after planting operations.
Any plants which have settled deeper or stand higher than specified in the
above paragraph shall be adjusted to the required level or replaced at the option
of Contractor.
Groundcover plants in areas equipped with an irrigation system shall be
planted in blocks which conform to the design of the irrigation system. The area
covered by one unit of the irrigation system shall be as completely planted as
possible, and then watered. Not more than one (1) hour shall elapse from the
time any groundcover is planted until it has been watered, unless otherwise
specified in the Special Provisions or authorized by the Engineer or Landscape
Architect.
Groundcover plants shall be planted in moist soil and in neat, straight rows
parallel to the nearest pavement or fence.
Plants shall be spaced as indicated on the Plans or in the Special
Provisions. Plants in adjacent rows shall be staggered. Groundcover plants shall
not be planted closer than five feet (5’) to trees or shrubs nor closer than twenty-
four inches (24”) to curbs, paved areas, and fences, unless otherwise shown on
the Plans.
Planting areas that in the opinion of the Engineer or Landscape Architect
have been compacted for any reason, either before or after planting, shall be
re-cultivated by Contractor, at his expense.
Trees, shrubs, and vines in groundcover areas shall be planted before
groundcover plants or cuttings are planted.
At the time the plants are planted, stakes shall be placed at certain plants
and the plants shall be tied thereto. The plants to be staked and the size of
stake and number of ties to be installed shall be as shown on the Plans or
35-6
specified in the Special Provisions. Stakes shall be placed against, but not
through, the plant ball and shall be placed on the side toward the prevailing
wind, unless otherwise directed by the Engineer or Landscape Architect.
Planting area slopes shall not exceed 4:1 ratio for shrubs unless otherwise
specified in the Special Provisions.
From the time any plants are planted and through the maintenance
period, plants shall be watered, trash and debris shall be removed, weeds shall
be controlled and replacements shall be made.
1. Preparing of Planting Areas shall conform to Section 35-5.
Soil in Shrub and Groundcover areas adjacent to paved areas shall be
graded so that after settlement, the soil will be two inches (2") below the top of
the adjacent paving or curb.
2. Weed Control shall conform to Section 35-6.
a. Granular Pre-emergent Herbicide shall be a broad spectrum, per-
emergent herbicide approved by the Engineer shall be applied at a
rate consistent with the manufacture’s recommendation in all
shrub and groundcover planter areas after completion of planting
and before installation of wood mulch. Contractor shall provide
proof of application of pre-emergent herbicide to the Engineer.
Contractor shall provide proof of application of pre-emergent
herbicide to the Engineer or Landscape Architect.
3. Soil Preparation Materials
Fertilizer shall be 6-20-20 applied at 12 lbs. per 1000 square feet and soil
sulfur applied at 1lb. per 1000 square feet, or approved equal. Soil conditioner
shall be a 90% bark based product, fir, and 0-1/4" in size, treated with nitrogen
having a 2-0-0 NPK ratio applied at a rate of 3 yards per 1000 square feet. The
above rate is for bid purposes only, the contractor shall have soil test performed
per Section 35-5.
4. Planting Materials
a. Schedules shown on the plans are for the Contractor’s convenience
only. Contractor shall confirm all quantities and shall plant as
required by the Planting Plan when discrepancies exist.
35-7
b. Plants shall be of the variety and size as shown on the plans and
shall conform to Sections 35-7, 35-8 and 10-43 of the Standard
Specifications.
c. Backfill Mix shall consist of three parts native soil to one part soil
amendment. Soil Amendment for planting pits shall be a 90% bark
based product, fir, and 0-1/4" in size, treated with nitrogen having
a 2-0-0 NPK ratio.
d. Mulch shall be evenly spread in all shrub and groundcover areas to
a three-inch (3") finished depth at the time of final acceptance by
the City. Mulch shall be large walk-on cedar bark, fibrous in nature,
one-inch (1") minimum to four-inch (4") maximum in length or
Douglas Fir Walk on Bark. Fibrous and or gorilla hair bark mulch is
not acceptable. Contractor shall submit a mulch sample to the
Engineer or Landscape Architect for approval at least forty-eight
(48) hours prior to installation.
35-9 PLANTING SEED
Grass seed shall be sowed at the rate specified in the Special Provisions
sowing one-half (½) of the amount in each direction.
Planting area slopes shall not exceed 5:1 ratio for grass unless otherwise
specified in the special provisions.
An even finish grade shall be maintained during seeding operations to
ensure proper surface drainage with ridges and depressions removed.
No seeding will be allowed between October 15 and March 15 and between
July 15 through the end of August, without approval of the Engineer or Landscape
Architect.
Soil shall be watered so that the soil is moist, not soggy, or dried out.
From the time grass has been sowed until the beginning of the
establishment period, grass shall be watered, trash and debris shall be removed,
weeds shall be controlled and replacements shall be made.
Full compensation for such work will be considered as included in the
contract unit prices paid for landscape planting.
At the time of sowing grass commercial fertilizer approved by Engineer or
Landscape Architect shall be applied to all lawn areas as specified in the Special
Provisions.
35-8
35-10 HYDRO-SEED PLACEMENT
Work will consist of all labor, materials, transportation, and
appurtenances required to turf hydroseed the areas shown on the Plans in
accordance with the following provisions and as directed by the Engineer or
Landscape Architect.
Contractor shall submit data including irrigation schedule, type and
analysis of fertilizer, application frequency, recommended coverage of fertilizer
and cutting and trimming schedule.
Contractor shall provide seed mixture in container showing percentage of
seed mix, year of production, net weight, date of packaging, and location of
packaging. USDA seed shall have a rating of 5.9 or higher.
Contractor shall have a minimum of 5 years documented experience and
shall comply with the County Agricultural Commission’s recommendations for
pesticide application. Contractor shall provide certificate of compliance from
authority having jurisdiction indicating approval of plants, fertilizer and
herbicide mixture and be licensed by regulatory agency to perform work.
Contractor shall deliver, store, protect and handle all products. Fertilizer
shall be delivered in waterproof bags showing weight, chemical analysis, and
name of manufacturer. Grass seed mixture shall be delivered in sealed
containers and damaged packaging will not be accepted.
Contractor shall not install hydro-seed when the ambient temperature is
below 45 degrees F (12 degrees C) or above 95 degrees F (39 degrees C).
Contractor shall not install hydro-seed when the wind velocity exceeds 30 mph.
Contractor shall coordinate the hydro-seed application with the
installation of irrigation piping, watering heads and electrical conduit and shall
comply with the plans and Special Provisions.
1. Preparing of Planting Areas, Section 35-5 shall be amended as follows: Soil
shall be cultivated until the condition of the soil is loose and fine-textured
to a depth of four inches (4"). Prior to hydro-seeding Contractor shall
prepare the soil base to receive hydro-seed. This shall include, but not
necessarily be limited to,
a. repairing the surface eliminating uneven areas and low spots
b. maintaining lines, levels, and contours and making changes in grade
gradual
35-9
c. blending slopes into level areas
d. cultivating areas where equipment has compacted sub-soil
Finish grade of all hydro-seed areas shall be reviewed and
approved by the Engineer or Landscaped Architect before proceeding with
planting. Four (4) to seven (7) days prior to hydro-seeding, Contractor
shall irrigate area to be planted to obtain twelve (12) inches of
penetration.
Soil in lawn areas adjacent to curbs or paved areas shall be graded
so that after settlement, the soil will be one-half inch (1/2") below the
top of curb or paving.
2. Weed Control shall conform to Section 35-6.
3. Soil Preparation Materials
a. Contractor shall place topsoil as indicated on the plans, rake until
smooth and remove vegetation and non-organic material from
topsoil while spreading. After smooth raking of topsoil and prior to
roller compaction, Contractor shall apply fertilizer in accordance
with manufacturer's instructions and mix it thoroughly into upper 4
inches to topsoil. Contractor shall lightly water fertilized area to
aid in the dissipation of the fertilizer. Contractor shall not mix the
fertilizer with the hydroseed.
b. Soil Conditioner/Fertilizer shall be 6-20-20 applies at 12 lbs. per
1000 square feet and soil sulfur applied at 1lb. per 1000 square
feet, or approved equal. Soil conditioner shall be a 90% bark based
product, fir, and 0-1/4" in size, treated with nitrogen having a 2-0-0
NPK ratio applied at a rate of 4 yards per 1000 square feet. The
above rate is for bid purposes only.
4. Turf Hydroseeding shall conform to Section 10-42, 35-7 and the following
provisions.
a. Seed Mix shall consist of 90% Dwarf fescue, 10% Dwarf Kentucky
Blue Grass applied at the rate of not less than twelve (12) lbs. of
viable seed per 1,000 square feet. Seed mix shall be submitted to
the Engineer or Landscape Architect for approval. All seed shall be
labeled in accordance with the California Food and Agricultural
Code and shall be delivered to the site in original, unopened
containers and shall bear a dated guaranteed analysis.
35-10
b. Wood Fiber Mulch shall be applied at the rate of 60 lbs. per 1,000
square feet. Wood Mulch shall be fibrous cellulose mulch
containing no growth or germination inhibiting substances, and
shall be manufactured in such a manner that when thoroughly
mixed with seed, fertilizer, and water, in the proportions specified,
it will form homogenous slurry, which is capable of being sprayed
to form a porous mat. The fibrous mulch in its air-dry state shall
contain not more than 10 percent by weight of water.
c. Fungicide shall be applied in accordance with the rate and method
of application recommended by the manufacturer and/or a Pest
Control Advisor.
d. Binder shall be Am-Tac tackifier or approved equal applied at the
rate as recommended by the manufacturer. Binder shall bind the
fiber mulch to prevent erosion.
5. Turf Starter Fertilizer shall be applied at the rate of ten (10) lbs. per 1,000
square. Starter fertilizer shall conform to the requirements of the
California Food and Agricultural Code A.
For non irrigated areas Contractor shall apply hydro-seed mixture with a
hydraulic seeder having a minimum capacity of 1,500 gallons with agitator
in tank, minimum pressure of 100 psi, and a distribution rate of 12,000
square feet within a fifteen (15) minute period. Contractor shall apply
hydro-seed mixture evenly in two intersecting directions. Spraying shall
be done in a sweeping motion allowing the slurry to fall evenly and
eventually building consistent matting. All hydro-seed mixture, which has
not been applied within four hours after mixing, will be rejected, removed
and disposed, as directed by the Engineer or Landscape Architect.
Contractor shall prevent hydro-seed from being sprayed in irrigation
drainage appurtenances.
35-11 HYDRO-SEED PLACEMENT (Non-irrigated Native Grass/Wildflower)
NOTE:
Please note that the following items are project specific and are used
as an example only. They must be modified to reflect the requirements for
the particular project.
Work will consist of all labor, materials, transportation, and
appurtenances required to turf hydroseeded the areas shown on the Plans in
35-11
accordance with the following provisions, Section 10-42, and as directed by the
Engineer or Landscape Architect.
1. Preparation of Planting Areas as shown on the plans, including mowing,
raking, and removing existing vegetation.
2. Native grass/wildflower hydroseeding shall conform to Section 10-42 and
the following provisions.
a. Wildflower Seed Mix shall be pre-mixed and packaged by a
commercial seed supplier, labeled in accordance with California
Agricultural Code, shall be delivered to the site in original,
unopened containers, and shall bear a dated guaranteed analysis.
The seed mix shall include the following seed proportions:
Species PLS lbs/acre
Hordeum brachyanthorum (Meadow Barley) 7
Bromus carinatus (California Brome) 7
Lolium multiflorum (Italian Ryegrass) 6
Eschscholzia californica (California Poppy) 1
Lupinus species (Lupine) 2
Trifolium hirtum (Rose Clover) 1
Layia platyglossai (Tidy Tips) 1
Nemophila menziesii (Baby Blue Eyes) 1
Castilleja exserta (Purple Owl’s Clover) 1
Seed shall be submitted to the Landscape Architect for approval.
Native Grass Mix shall be as specified on the plans.
b. Fertilizer shall conform to the applicable state fertilizer laws. It
shall be uniform in composition, dry and free flowing and shall be
delivered to the site in original, unopened containers, each bearing
the manufacturer's guaranteed analysis. Any fertilizer that
becomes caked or otherwise damaged, making it unsuitable for use,
will not be accepted.
35-12
c. Cellulose Fiber shall be colored with a non-toxic, water-soluble
green dye to provide a visual gauge for metering of material over
ground surfaces.
Fiber shall be produced from natural or recycled (pulp) fiber, such
as wood chips or similar wood materials or from newsprint,
chipboard, corrugated cardboard, or a combination of these
processed materials, and shall be free of synthetic or plastic
materials. Fiber shall not contain more than 7 percent ash as
determined by the Technical Association of the Pulp and Paper
Industry (TAPPI) Standard T-413, shall contain less than 250 parts
per million boron, and shall be otherwise nontoxic to plant or
animal life.
Fiber shall have a water holding capacity by weight of not less than
1,200 percent as determined by the procedure used in the
Department's Final Report, CA-DOT-TL-2176-1-76-36, "Water-
holding Capacity for Hydromulch", available at the Transportation
Translab, 5900 Folsom Boulevard, Sacramento, CA 95819.
Fiber shall be of such character that the fiber will disperse into
uniform slurry when mixed with water. Water content of the fiber
before mixing into slurry shall not exceed 15 percent of the dry
weight of the fiber. The percentage of water in the fiber shall be
determined by California Test 226. Commercially packaged fiber
shall have the moisture content of the fiber marked on the
package. Fiber shall be colored to contrast with the area on which
the fiber is to be applied and shall not stain concrete or painted
surfaces.
A Certificate of Compliance for fiber shall be furnished to the
Engineer or Landscape Architect.
d. Organic Stabilizer shall contain a Bonded Fiber Matrix and
Stabilized Fiber Matrix and shall be a biodegradable tackifier,
non-toxic to plant or animal life, such as Sentinel or M-Binder.
e. Water shall be provided by Contractor.
3. Hydroseeding installation shall be performed during a windless period
using approved equipment and materials. Contractor shall verify that
hydroseed areas are adequately graded for seed application and free of
deleterious material and weeds at the time of planting.
35-13
a. Hydraulic equipment shall be reviewed by the Engineer or
Landscape Architect prior to starting work.
i. Equipment shall have a built-in agitation system and
operating capacity sufficient to agitate, suspend and
homogeneously mix a slurry of water, fertilizer, fiber, seed,
and other additives.
ii. Slurry Distribution Lines shall be large enough to prevent
clogging and shall be equipped with a set of hydraulic spray
nozzles which provide a continuous nonfluctuating discharge
and uniform delivery of slurry in prescribed quantities
without misses, waste, or erosion.
iii. Slurry Tank shall have a minimum capacity of 1000 gallons
and shall be mounted on a traveling unit which may be
drawn by a separate or self propelled unit in order to
properly place the slurry tank and spray nozzle for uniform
distribution.
b. Slurry Preparation shall occur on site and materials shall be added
in such a manner that they are uniformly blended into the mixture.
Slurry shall be completely homogenous before application.
i. With Agitation System operating at half speed, water shall
be added to the tank, and good circulation established. The
seed shall be added first, then fiber. The mixture shall be
agitated at full speed when the tank is half full.
ii. Fiber shall not be added until the tank is at least one-third
filled with water. Fertilizer and seed mix shall be added at
the last practical moment. Total time from the addition of
seed to seed discharge shall be less than one hour; if more
than one hour, the remainder of the load shall be recharged
with seed.
c. The operator shall spray the areas with a uniform, visible coat using
the green color of the wood pulp as a guide. The slurry shall be
applied in a sweeping motion, so as to allow the fibers to build on
each other until a good coat is achieved and the material is spread
at the required rate per acre.
d. The materials shall be mixed and applied in the approximate
proportions:
35-14
Materials Per Acre
Fiber 1800 lbs.
Seed Mix See 2.1 MATERIALS
16-20-20 (N-P-K) 350 lbs.
Organic Stabilizer 80 lbs.
Water As needed for application
e. The limits indicated on the drawings reflect the only part of the
area required to be hydroseeded. This area, plus all other areas
graded and disturbed by Contractor shall be hydroseeded. Any
compacted or otherwise unsuitably prepared areas within these
descriptions shall be scarified and rototilled to prepare the areas
for seeding.
f. Prior to completion of all operations, Contractor shall remove,
wash clean, or otherwise correct any unsightly overspray, trash,
excess soil, other debris, or damage. All walks and pavement shall
be swept and washed clean, and clean-up operations performed in
the general work area as needed to leave the entire area in neat,
orderly condition. Paving and other areas washed clean shall retain
the runoff onsite and shall not let the runoff enter into the storm
drain.
35-12 SOD PLACEMENT
Contractor shall place and establish sod in all areas as delineated on the
Plans. Work will consist of labor, materials, transportation, and all
appurtenances required to install the sod.
Contractor shall submit data including irrigation schedule, type and
analysis of fertilizer, application frequency, recommended coverage of
fertilizer, and cutting and trimming schedule. Contractor shall provide growers
certificate, percentage of seed mix, and year of production.
Contractor shall have a minimum of 5 years documented experience and
shall comply with the County Agricultural Commission’s recommendations for
pesticide application. Contractor shall provide certificate of compliance from
authority having jurisdiction indicating approval of plants, fertilizer and
herbicide mixture and be licensed by regulatory agency to perform work.
Contractor shall deliver, store, protect and handle all products. Fertilizer
shall be delivered in waterproof bags showing weight, chemical analysis, and
name of manufacturer.
Contractor shall not install Sod when the ambient temperature may drop
35-15
below 45 degrees F (12 degrees C) or rise above 95 degrees F (39 degrees C).
Contractor shall not install Sod when the wind velocity exceeds 30 mph.
Contractor shall coordinate the installation of irrigation piping, watering
heads and electrical conduit with sod application.
Sod support materials shall be as specified in the following table.
Fertilizer 16-8-8 Commercial "Gro-power” or
approved equal fertilizer
Herbicide:
Glyphosate or approved equal
Topsoil: Class ‘A-
fertile, agricultural soil,
typical for locality, capable of
sustaining vigorous plant growth,
taken from drained site; free of
subsoil, clay or
impurities, plants,
weeds and roots; minimum Ph value
of 5.4 and maximum of 7.0.
Prior to placing sod, Contractor shall prepare the soil base to receive
hydro-seed as per Section 35-5. This shall include, but not necessarily be limited
to,
1. preparing the surface eliminating uneven areas and low spots,
2. maintaining lines, levels, and contours and making changes in grade
gradual,
3. blending slopes into level areas,
4. cultivating areas where equipment has compacted sub-soil.
Four (4) to seven (7) days prior to planting, Contractor shall irrigate area
where Sod is to be placed to obtain twelve (12) inches of penetration.
Contractor shall place topsoil as indicated on the plans, rake until smooth
and remove vegetation and non-organic material from topsoil while spreading.
After smooth raking of topsoil and prior to roller compaction, Contractor shall
apply fertilizer in accordance with manufacturer's instructions and mix it
thoroughly into upper 4 inches of topsoil. Contractor shall lightly water fertilized
35-16
area to aid in the dissipation of the fertilizer.
Contractor shall install trees and liner stock plant material before lawn
areas are sodded and shall place Sod only when weather and soil conditions are
suitable according to locally accepted practices. Any Sod that does not take hold
and dies after fourteen (14) days from its installation shall be replaced by
Contractor. This replaced Sod will also have to be replaced if it dies after
fourteen (14) days.
Placing Sod shall include, but not necessarily be limited to:
1. laying sod as shown on the plans,
2. applying slow release 13-8-4 or approved equal commercial fertilizer prior
to placing sod,
3. laying all sod on the same day delivered,
4. laying strips of sod straight and tight, stagger joints,
5. rolling sod with suitable weighted roller, and
6. watering with a fine spray to keep surface moist until roots take hold.
Engineer may require Sod to be replaced take and analyze samples of
materials for conformity to specifications at any time. Contractor shall furnish
samples upon Owner’s request. Rejected materials shall be immediately
removed from the site at Contractor’s expense. Costs of testing materials not
meeting specifications shall be paid by Contractor.
All material shall be of standard, approved, and first-rate quality and shall
be in prime condition when installed and accepted. Any commercially processed
or packaged material shall be delivered to the site in the original unopened
container bearing the manufacturer’s guaranteed analysis.
35-13 WATERING
All plants shall be watered immediately after planting. Water shall be
applied in a moderate stream until the backfill soil around and below the roots
or ball of earth around the roots of each plant is thoroughly saturated.
Precautions shall be taken to prevent water from wetting vehicles,
pedestrians, and pavement. Any erosion or slippage of the soil caused by
watering shall be repaired by Contractor, at their expense.
35-17
Compliance with the provisions in this section shall not relieve Contractor
of his responsibility for the replacement of plants. Any additional watering
measure required to maintain the plants in a growing condition shall be furnished
by Contractor, at his expense.
Contractor is responsible for all water and all utility bills until the City
accepts the project at the end of any required landscape maintenance period.
35-14 REPLACEMENT
All trees, plants, shrubs, seeds and grass areas that show signs of failure
to grow at any time or which are injured or damaged as to render them
unsuitable for the purpose intended as determined by the Engineer or Landscape
Architect shall be removed and replaced. The Engineer or Landscape Architect
will inspect the work once each week or at longer intervals at his discretion and
will mark or otherwise indicate all plants or lawn areas to be replaced.
Contractor shall replace unsuitable plants or lawn areas within one (1) week of
such inspection.
Replacements shall be furnished and planted by Contractor, at his
expense. Contractor and Engineer or Landscape Architect may agree to the
substitute alternative species of plants to be used as replacements.
Any damage to the finish grading caused by re-planting operations and/or
vandalism shall be repaired and re-planted by Contractor, at his expense.
Damage caused by premature or heavy use of facilities before final acceptance
will be determined by the Engineer or Landscape Architect.
Lawn damage caused by vandalism or premature use shall be repaired and
reseeded before final inspection but will not cause extension of the maintenance
period.
Lawn failure caused by improper / lack of maintenance practices and/or
weather shall be re-planted, and the maintenance period shall be extended to
thirty (30) days after the re-planting, or as required by the Engineer or Landscape
Architect.
35-15 START OF MAINTENANCE PERIOD
After all planting and related work within the planting area is completed,
Contractor shall request an inspection by the Engineer, the Landscape Architect,
or a representative of the City’s Streetscape Office. The request shall be given
48-hours in advance of the inspection and Contractor must attend the inspection.
The Engineer or Landscape Architect shall test the irrigation system for
35-18
coverage and review the plant materials for proper installation. The written
approval of the completed work by the Engineer or Landscape Architect shall
establish the beginning of the maintenance period. The Engineer or Landscape
Architect will confirm start date, in writing. No partial approvals will be given.
35-16 LANDSCAPE MAINTENANCE
Landscape maintenance work shall consist of caring for the landscape
planting portion of the project and satisfying the City’s Landscape Maintenance
Specification and Provisions (LS18) or most current version of Landscape
Specifications.
Landscape maintenance period shall be as specified in the Special
Provisions and or a specified on the plans. Plant establishment shall continue
until final acceptance of the work.
The time required for plant establishment work shall be considered as
included in the total time limit specified for the Contract.
Contractor will be required to fill trench settlement, adjust sprinkler
heads, water plants, replace unsuitable plants and lawn areas, do weed, rodent
and other pest control work as determined necessary by the Engineer or
Landscape Architect.
Contractor shall provide and ensure that an experienced foreman is
present during maintenance operations. All sprinkler materials used either shall
conform to Section 36 of the Standard Specifications, or otherwise be acceptable
to the Engineer or Landscape Architect.
Contractor shall perform the following:
1. Check the irrigation system weekly for proper operation. Lateral lines
shall be flushed out after removing the last sprinkler head or two heads
at each end of the lateral. All sprinkler heads are to be adjusted as
necessary for unimpeded coverage and to protect structures.
2. Contractor shall set and program automatic controllers for seasonal water
requirements. Contractor shall give Engineer or Landscape Architect a
spare key to controllers, instruction on their operation, and a 24-hour
phone number in case of emergency.
3. Repair all damages to sprinkler irrigation system at Contractor’s expense.
Repairs shall be made within one watering period or one week, whichever
is the shortest time.
35-19
4. Weeding and/or cultivation weekly of all planted and seed areas to
maintain the project in a neat and uniform condition at all times, as
determined by the Engineer or Landscape Architect.
5. Sidewalks, gutters, and the area within the limit of work shall be cleaned
weekly. Failure to comply will result in an extension of the landscape
maintenance period, as determined by the Engineer or Landscape
Architect.
6. All planting and seeding shall be kept in a healthy growing condition by
watering, weeding, cultivation, pruning, mowing, edging, spraying,
fertilizing, and by performing any other necessary operation of
maintenance.
7. Lawn mowing of turf will commence when the grass has reached a height
of three (3) inches.
a. The height of cut will be as recommended for the type of turf
specified. Lawn growing around trees, light poles, fences, and
other obstacles shall be maintained at a height equal to that of the
adjacent lawn areas, or may be chemically controlled with the
approval of the Engineer or Landscape Architect.
b. Mowing will be at least weekly after the first cut. Following a
minimum of three (3) mowings Contractor shall be required to treat
the lawn with a selective broadleaf and grass weed herbicide that
will not harm the lawn. Contractor shall conform to Section 35-6
of the Standard Specifications for application of herbicides.
c. Turf must be well established and free of bare spots and weeds to
the satisfaction of the Engineer or Landscape Architect prior to
final acceptance.
d. Edges shall be trimmed at least twice monthly or as needed for
neat appearance.
e. Unless otherwise required in the Special Provisions, clipping shall
be removed at the time of mowing.
f. Lawns shall be watered at such frequency, as weather conditions
require replenishing soil moisture below root zone; normally, a
total of 1½ inches of water is needed weekly in hot weather.
g. Fertilize the turf areas at the start of the landscape maintenance
period and every 30 days thereafter with a ,complete fertilizer with
35-20
a two-to-one nitrogen to potassium ratio at a rate of six (6) pounds
of nitrogen per thousand (1,000) square feet of application area,
unless otherwise directed.
h. Re-sod lawn areas weekly as needed or directed by Engineer or
Landscape Architect.
8. Application of pesticide spray by a licensed Pest Control Applicator shall
be used, if needed, to control:
a. crabgrass
b. broad leaf weeds
c. nut sedge
d. insects pests
During the course of the maintenance period, all planted areas shall
be in a weed free and/or neatly mowed condition and shall receive a
second application of fertilizer as may be specified in the Special
Provisions.
Contractor shall provide the Engineer or Landscape Architect a
monthly report of all herbicides, insecticides, and disease control
chemicals used, as well as dates and rates of application applied.
9. All work shall be executed in an orderly and careful manner to protect
new concrete walks, work of other trades, and other improvements.
10. Cleanliness on paved areas and other public areas used by equipment shall
be maintained.
a. Contractor shall be responsible for immediate removal of all
spillage on all paved areas.
b. Contractor shall remove from project site all rubbish and debris
found thereon and all material and debris resulting from work,
leaving site in a safe and clean condition.
11. Improper maintenance or poor condition of any planting at the
termination of scheduled maintenance period may cause postponement of
completion date; maintenance shall be continued until all work is
accepted.
35-21
12. Regular on-site meetings shall be held by Contractor and Engineer or
Landscape Architect; dates and location to be jointly agreed upon.
Meeting notes shall be prepared.
13. Contractor shall guarantee all new plant materials for duration of
landscape maintenance period.
a. Plants not alive and in satisfactory growing condition, as
determined by Engineer or Landscape Architect, shall be replaced
within one week of notification, at no cost to the City.
b. Replace guarantee shall include all plants damaged or destroyed by
any action, including but not limited to, vandalism, theft, neglect,
or pests.
c. Plants shall be replaced of same kind and size as specified,
furnished, and installed as herein specified.
14. Trees and Shrubs shall be pruned and shaped as directed by the Landscape
Architect. Trees shall be restaked as necessary. Maintain watering basins
and shrub and groundcover areas free of weeds.
15. Surplus earth, Papers, trash, and debris, which accumulate in the planted
areas shall be removed and disposed of and the planted areas shall be so
cared for as to present a neat and clean condition at all times.
35-17 PRE-FINAL INSPECTION
One month prior to the end of the maintenance period or as modified in
the special provisions, the Engineer or Landscape Architect will conduct a pre-
final inspection. At this time Contractor will acquaint the Engineer or Landscape
Architect with the operational requirements of the project. At this time, all
systems will be tested, and a punch list will be prepared and presented to
Contractor by the Engineer or Landscape Architect.
35-18 FINAL INSPECTION
At the end of the maintenance period and when all the punch list items
from the pre-final have been completed Contractor shall schedule the final
inspection with the Engineer or Landscape Architect, giving them two (2) working
days notice. If no other punch list items are identified, the project will be
accepted and Contractor will be relieved of responsibility for the work, except
for warranties or guarantees.
At the time of acceptance of the project, all lawn areas shall be in a neatly
35-22
mowed condition. All planting areas shall be fertilized as specified in the Special
Provisions.
35-19 RECORD DRAWINGS AND CONTROLLER CHARTS
Prior to the final inspection, Contractor shall submit to the City, for
review and comment by the Engineer or Landscape Architect, two (2) sets of
Record Drawings. The work will not be formally accepted until the Record
Drawings are accepted by the Engineer or Landscape Architect. Upon approval
by the Engineer or Landscape Architect, these records shall be delivered to the
City, in reproducible form, and in good and acceptable condition prior to final
acceptance of the work.
Contractor shall also provide two (2) reduced (original 11”X 17”) charts
for each controller. Once copy shall be placed on the inside of the controller
enclosure door. The second copy shall be provided to the Engineer or Landscape
Architect. Record Drawings shall be approved by the Engineer or Landscape
Architect prior to preparing the charts.
Each controller chart shall show the as-built condition of the area
controlled by the automatic controller. All symbols shall be readable at the final
reduced size. The controller chart shall include:
1. Connection to existing water lines.
2. Routing of pressure lines.
3. Routing of control valves.
4. Locations of remote control valves, gate valves, quick coupling valves,
and electrical power source.
5. Other items as directed by the City. (Controller keys, remotes, etc.)
The chart shall be colored or otherwise coded to indicate the area of
coverage for each station.
When completed and approved, the chart shall be hermetically sealed
between two (2) pieced of 10 mil plastic, minimum.
Each chart shall be completed and approved prior to final inspection of
the irrigation system.
35-23
35-20 PAYMENT
Unless otherwise specified in the Special Provisions payment for:
1. Maintenance work shall be at the contract lump sum bid price which
payment shall include full compensation for all labor, tools, equipment,
materials and incidentals necessary to complete the items.
2. Trees shall be made at the unit price bid per each, and shall include full
compensation for furnishing all labor, materials, tools, equipment and
incidentals and for doing all work involved in completing the Trees as
shown on the plans, as specified in these Special Provisions and as directed
by the Engineer.
3. Shrub and groundcover areas shall be made at the lump sum price bid and
shall include full compensation for furnishing all labor, materials, tools,
equipment and incidentals and for doing all work involved in completing
the Shrub and Groundcover Areas as shown on the plans, as specified in
these Special Provisions and as directed by the Engineer.
4. Hydro-seed (non-irrigated), seed and sod, shall be at the lump sum price
bid and shall include full compensation for all submittals, labor, materials,
tools, equipment, and incidentals, and for doing all work involved with
placing and establishing hydro-seed and sod as shown on the Plans, as
specified in the Special Provisions and as directed by the Engineer.
5. Hydro-seed turf areas shall be made at the lump sum price bid and shall
include full compensation for furnishing all labor, materials, tools,
equipment and incidentals and for doing all work involved in completing
the Turf Hydro seeding as shown on the plans, as specified in these Special
Provisions and as directed by the Engineer.
36-1
Section 36
IRRIGATION SYSTEM
36-1 GENERAL
Irrigation system shall include all appurtenances, incidentals and
accessories required for proper installation and operation of the system.
36-2 MANUFACTURER’S WARRANTIES
Manufacturer’s warranties, guarantees, instruction sheets and parts lists
which are furnished with certain articles or materials incorporated in the work,
shall be delivered to the Engineer before acceptance of the Contract.
36-3 GUARANTEE
The entire sprinkler system shall be guaranteed for a period of one (1)
year from date of completion. Should any trouble develop within the time
specified above due to faulty workmanship or materials, the trouble shall be
corrected by the contractor, without expense to the City. The contractor shall
make the repairs within two day to the satisfaction of the City.
Any settling of backfilled trenches which may occur during the one (1)
year period after completion shall be repaired by, without expense to the City,
including the complete restoration of all damaged property.
36-4 RECORD DRAWINGS
Contractor shall furnish the Engineer 2 sets of “as built” drawings hard
copy and PDF document showing any changes in plans, location of pipe, wire
splices and valves, depth, electric power source for controllers, etc. The
irrigation system will not be accepted until “as-builts” are furnished and
accepted.
36-5 WATER TAPS ON CITY MAINS
Unless otherwise set forth in the Special Provisions, all taps on existing
City mains will be made by the City at Contractor’s expense.
When taps are made in any location other than street sections, all
excavations and backfill necessary for the connection shall be done by
Contractor. Contractor shall make the necessary arrangements with the Water
Division of the City to have City crews available to make the connection. No taps
will be made until tap fees have been paid to the Water Division.
36-2
Street medians shall have independent water taps for each section of
median and shall not be connected to the side of the roadways. In addition each
park site shall have a two taps for each park site, one irrigation and one domestic
water tap.
36-6 CONNECTIONS TO EXISTING WATER MAINS
Unless otherwise set forth in the Special Provisions, all connections to
existing park and or other City irrigation water mains including labor, excavation,
cutting and furnishing necessary materials to do the work shall be done by
Contractor. Connections must be approved by appropriate party responsible for
final maintenance.
Contractor will notify the Engineer twenty-four (24) hours prior to
proposed connections.
City forces will make necessary shut-downs of existing facilities for
Contractor.
36-7 SALVAGE
Unless otherwise specified, all salvageable material and equipment
removed from present installations which are not to be reinstalled shall be
delivered in good condition to the Streetscape Division at the City Corporation
Yard.
36-8 CONDUITS
Conduit shall conform to Section 34-10 of these Specifications, except
that conduit for 24 volt irrigation control wire installed under pedestrian walks
and paved areas within landscape project limits shall be PVC Schedule 40 solvent
weld pipe conforming to Section 10-45 of these Specifications.
36-9 BACKFLOW PREVENTION ASSEMBLIES
Backflow prevention assemblies shall conform to Section 10 of these
Specifications.
Installation shall be in the location indicated on the Plans and shall
conform to the drawings shown in Section 38 of these Specifications, unless
otherwise indicated in the Contract Documents.
36-3
36-10 IRRIGATION PIPE AND FITTINGS
Pipe and fittings used in irrigation systems shall be in accordance with
Section 10 of these Specifications or as specified on the plans.
The Special Provisions may designate that a particular type of pipe shall
be used in which case the use of an alternate type of pipe shall not apply.
36-11 ELECTRIC AUTOMATIC CONTROLLERS
Electric automatic controllers shall be of the type shown on the Plans or
specified in the Special Provisions and shall conform to Section 10 of these
Specifications.
Installation shall be in the location indicated on the Plans or in the Special
Provisions and shall conform to the drawings in Section 38 of these
Specifications, unless otherwise indicated on the Plans.
Electrical service of electric automatic controllers shall conform to
Section 34 of these Specifications.
For medians 18 Station maximum. Controllers shall be sole sourced and
not shared by medians and side roads. Controllers shall be a State of California
EPA Water Wise Approved controller.
36-12 ELECTRIC CONTROL CONDUCTORS
Irrigation control conductors shall conform to Section 10 of these
Specifications and shall be installed in conformance with Section 34 of these
Specifications and as amended in this section.
Conductors shall be buried directly in the ground a minimum of eighteen
inches (18”) below the surface and shall follow irrigation supply lines whenever
possible, except that where conductors pass under paved areas, conductors shall
be installed in conduit conforming to the provisions in Section 36-8 of these
Specifications.
Conductors shall be run continuous without splices from controller
enclosure to the valve boxes. Splices shall be clamped and sealed with
waterproof connectors.
At least one foot (1’) of slack shall be left in each conductor at each splice.
Conductors from controllers to valves shall be wrapped together with
electrical tape at ten-foot (10’) intervals.
36-4
36-13 IRRIGATION CONTROL VALVES AND VALVE BOXES
Irrigation control valves and valve boxes shall be of the type shown on the
Plans or specified in the Special Provisions and shall conform to Section 10 of
these Specifications. Irrigation control valves and valve boxes shall not be placed
within concrete or paving. They shall be placed in planter, turf, or native planted
areas. Also control valves and boxes shall be a minimum of eight feet (8’) away
from the tree trunk.
Installation shall be in the location indicated on the Plans and shall
conform to the drawings shown on Detail L-20 of these Specifications, unless
otherwise shown on the Plans or called for in the Special Provisions.
Valves boxes indicated to be installed at grade shall include valve box
extensions as required.
36-14 VALVE MANIFOLDS
Valve manifolds shall be constructed of PVC Schedule 80 fittings.
36-15 TYPE B SPRINKLER RISER ASSEMBLIES
Type B Sprinkler Riser Assemblies shall be constructed as indicated on the
drawings. Risers and cells shall be galvanized steel. Adapters shall be Class 1 or
2, PVC Schedule 80. The horizontal nipple shall be Flexible PVC complying with
ASTM D 2287 and D2466. This unit shall be equal to Excalibur Flexible PVC Nipple.
36-16 SWING JOINT ASSEMBLIES
Swing joint assemblies shall be constructed of galvanized steel pipe and
Marlex fittings conforming to Section 10 of these Specifications. All joints of
swing joint assemblies shall be tightened one (1) turn beyond hand tight.
Installation shall conform to the drawings shown in Section 38 of these
Specifications.
36-17 SPRINKLERS
Sprinklers and bubbler heads shall be of the type shown on the Plans or
specified in the Special Provisions. All sprinklers and bubblers shall have a
manufactured installed check valve.
Sprinklers shall be made theft resistant by applying “Loctite Retaining
Compound No. 3, Catalog No. 35-31” on all pipe threads down to the first elbow
underground. Mating threaded surfaces shall first be primed with “LOCQUIC
36-5
Primer T”. This compound shall only be applied on male threads to prevent
excess compound from entering the working mechanism of the sprinklers.
Sprinklers “Type C and D” including risers and stakes shall be painted gray.
Installation shall conform to the drawings shown in Section 38 of these
Specifications.
36-18 QUICK COUPLING VALVES
Quick coupling valves shall conform to Section 10 of these Specifications.
Installation shall conform to the drawings shown in Section 38 of these
Specifications.
36-19 TRENCHING FOR IRRIGATION PIPE
Trenches shall be dug to an even laying grade and to a depth sufficient to
provide twenty-four inches (24”) of cover over all pipe on the supply side of the
irrigation valve and eighteen inches (18”) of cover over all pipe on the discharge
side of the irrigation valve. Trenches shall be excavated only as far in advance
of pipe laying as is permitted by the Engineer. Excavated material shall be piled
in a manner that will not endanger the work and will avoid obstructing sidewalks
and driveways. Open trenches and piles of dirt will be so marked and lighted as
to provide safety to all pedestrians and to vehicular traffic.
Trenches shall be of sufficient width to permit snaking of all plastic pipe
not connected by rubber ring-tite fittings. Pipe connected with ring-tite fittings
need not be snaked.
Trenches for plastic pipe shall be smooth and free of jagged rubble or
sharp objects which will cause abrupt bending stress and uneven weight
distribution during backfilling operation.
Rock, pavement, and other debris encountered during trenching operation
shall be removed and disposed of outside of the project limits at Contractor’s
expense. The size and quantity of material to be disposed of will be determined
by the Engineer.
36-20 INSTALLATION OF IRRIGATION AND POTABLE PIPE
Installation of irrigation and potable pipe shall be as shown on the Plans
and in accordance with these Specifications and the Special Provisions.
Plastic pipe, including fittings, shall be installed according to the
36-6
Manufacturer’s directions and as directed by the Engineer.
Portland Cement concrete thrust blocking conforming to Standard
Drawing W-103 shall be provided at each change in alignment and at the ends of
plastic pipe (ring-tite) supply lines. Concrete for thrust blocking shall be
Portland Cement concrete Class “C” and shall conform to Section 10-5 of these
Specifications.
The quantity of concrete used shall be as required to provide contact with
undisturbed soil.
Plastic irrigation pipe shall be placed in trenches on level, undisturbed or
well compacted earth and shall be snaked from side to side in the trench at
intervals of approximately fifty feet (50’). Pipe shall be held down between
joints with small mounds of earth to prevent movement.
Foreign material shall be prevented from entering the irrigation system
during installation. Immediately prior to assembling all pipes, valves and fittings,
all valves shall be plugged or capped pending the attachment of additional pipe
or fittings. All lines shall be thoroughly flushed out prior to attachment of
terminal fittings.
Pipe shall be cut with a fine tooth hacksaw and any burrs shall be
removed. The outside surface of the pipe and the inside surface of the fittings
shall be wiped with a clean cloth to remove all dirt and moisture before the
cement solution is applied. The cement solution shall be applied to the pipe and
fitting socket with a brush having a width approximately three-quarters (¾) of
the depth of the socket. The cement solution shall be applied freely with a light
wiping action to spread the cement uniformly over the surface. The pipe
surfaces or fitting socket shall not be rubbed with the brush any more than is
necessary to spread the cement. If the cement thickens, it shall be discarded.
Solvent weld connections on the supply side of valves shall first be cleaned with
Weld-on Solvent No. 660, or equal. Cement solution shall be Weld-on Solvent No.
715, or approved equal.
Pipe cleaner and cement shall be same brand to assure compatibility.
Immediately after the cement has been applied to the surface to be
joined, the pipe shall be inserted into the fitting with a twisting motion to the
full depth of the fitting socket. Immediately after joining is completed, any
excess cement shall be thoroughly wiped from the pipe and fitting. The jointed
members shall be allowed to cure for at least five (5) minutes before they are
handled. An additional fitting or pipe section may be added to the completed
joint within three (3) minutes if care is exercised in handling so that strain is not
placed on the previous joint.
36-7
The male pipe threads of all threaded connections on PVC plastic pipe
shall be coated with a joint compound suitable for use with plastic pipe.
36-21 TESTING OF IRRIGATION SYSTEM
After laying and before backfilling and compacting of irrigation main and
laterals, they shall be tested in presence of Engineer for leakage and for sprinkler
coverage.
1. Leakage Test for Irrigation Main
The section of main to be tested shall be flushed to remove all air from
the line, capped and tested under full static pressure for a minimum of four (4)
hours. Any leaks which develop in the portion of the system being inspected
shall be repaired and all defective material shall be replaced.
At Contractor’s option a one (1) hour pressure test of one hundred pounds
per square inch (100 psi) may be substituted for the above test. Contractor shall
provide the necessary pump and equipment required for this test.
2. Leakage Test for Irrigation Laterals
Laterals shall not be tested.
3. Sprinkler Coverage Test
The risers for sprinklers on slopes shall be set approximately
perpendicular to the slope. Each series of sprinklers shall be installed and test
operated. Nozzles of all sprinklers and bubblers shall be adjusted for proper rate
of flow and coverage. Sprinklers or bubblers shall be relocated as required to
produce uniform coverage.
Extra sprinklers or bubblers required to produce uniform coverage as
determined by the Engineer shall be paid for as extra work.
36-22 STERILIZING PLASTIC POTABLE PIPE
Sterilization of plastic potable pipe shall conform to Disinfection of Water
Mains, Section 27-12 of these Specifications.
36-23 BACKFILL OF IRRIGATION PIPELINES
Backfill in street sections shall be as specified in Section 27-8 of these
36-8
Specifications. Sand backfill is not required in planting areas.
Special backfill requirements may be set forth in the Special Provisions.
36-24 REPAVING
Repaving over trenches shall be as specified in Section 26-9 of these
Specifications, unless otherwise set forth on the Plans or in the Special
Provisions.
36-25 WATER CONSERVATION SECTION
Irrigation installed shall be installed per the City’s Water Efficient Landscape
Requirements, Ordinance 15.92.
Prior to the final acceptance the contractor shall supply the City with a
Certificate of Completion which includes but not limited to:
Part 1. Project Information Sheet
Park 2. Certification of installation according to the Landscape
Documentation Package.
Part 3. Irrigation Scheduling
Part 4. Schedule of Landscape and Irrigation Maintenance
Part 5. Landscape Irrigation Audit Report
Part 6. Soil Management Report
36-26 PAYMENT
Unless unit prices are required by the Special Provisions, payment for the
Irrigation System shall be at the lump sum price bid. Such payment shall be full
compensation for furnishing all labor, materials, tools and equipment and doing
all work involved in installing and testing of the Irrigation System as required
herein, in the Special Provisions, on the Plans or by the Standard Drawings.
37-1
Section 37
BORING AND JACKING
37-1 GENERAL
This section covers tunneling and/or boring and jacking of casing pipe and
furnishing and placing water pipe, sewer or drain pipe (conveyance pipe) within
the casing pipe (two-pass system) or direct jacking of conveyance pipe (single-
pass system) at the location(s) indicated on the Plans, to the lines, grades, and
details given. Installation of casing pipe shall meet the applicable requirements
of the Construction Safety Orders of the State of California Department of
Industrial Relations and Division of Occupational Safety and Health.
Casing pipe shall be installed either by tunneling or by dry boring and
jacking, as dictated by existing soil conditions and/or the size of the casing pipe.
Only workers experienced in tunneling or boring and jacking operations shall be
used in performing the work.
Prior to proceeding with the work, Contractor shall submit to the Engineer
for review and approval, a written description of the materials, equipment,
method, and sequence of operations proposed to be used to furnish and install
the casing pipe or the direct jack pipe, including the conveyance pipe grades.
Contractor shall also provide detail drawings and structural calculations
to the Engineer indicating the materials and methods to be used to shore the
excavated jacking and receiving pits signed by a civil or structural engineer
licensed by the State of California. Approval of the proposed method by the
Engineer shall not relieve Contractor of the full responsibility of making a
satisfactory installation meeting the criteria set forth herein and on the plans.
Excavation for the boring operation shall be the minimum necessary to
satisfactorily complete the work. Contractor shall use extreme care in shoring
the jacking and receiving pits so as to ensure the stability of adjacent
improvements and structures and to protect workmen. Special backfill
requirements may be specified in the Special Provisions for pipe installed in the
area excavated for the boring operations.
37-2 SINGLE-PASS SYSTEM
Unless specified otherwise, Contractor may elect to jack the conveyance
pipe directly in a single pass in conformance with these Specifications.
RCP Class V flush bell pipe with double-rubber gasket joints, or with
fiberglass reinforced epoxy collar, or approved equal type joints may be jacked
37-2
directly for installation of drainage or sewer facilities. The pipe must be designed
to safely bear all loads imposed by jacking in addition to the design D-loads. A
cushion material of plywood or hardwood spacers shall be placed in the joints
between adjacent pipe sections being jacked in order to distribute the jacking
load uniformly throughout the entire pipe length and avoid radial gasket pressures
which may over stress the pipe sockets or grooves.
Guide rails shall be accurately set to line and grade to ensure installation
within tolerances allowed. Maximum length of direct jacking shall be one
hundred feet (100’). The diameter of the hole shall not be more than 0.1 foot
greater than the outside diameter of the reinforced concrete pipe.
37-3 TWO-PASS SYSTEM
The two-pass system utilizes a conveyance pipe within a casing pipe.
1. Casing Pipe Material
Material for casing pipe shall be either welded steel pipe or reinforced
concrete pipe. Joints for the casing pipe shall provide for a rigid and watertight
installation. Contractor shall be fully responsible for any or all damage arising
from subsidence or any other disturbance due to any boring and jacking
operation.
a. Welded Steel Pipe
Contractor is fully responsible for design and selection of steel
casing pipe consistent with the requirements herein. Unless otherwise
approved, steel casing pipe shall be welded steel with a wall thickness of
three-quarter inch (¾”) conforming to AWWA C 200 or API 5L pressure
pipe X-42 minimum as appropriate for the project and site subsurface
conditions. Factory hydrostatic testing not required unless otherwise
specified. Field joints shall be either full circumference welded butt joints
or integral machined press-fit connections such as Permalok or approved
equal. It shall be Contractor’s responsibility to provide stress transfer
across the joints which is capable of resisting the jacking forces involved.
b. Reinforced Concrete Pipe
Reinforced concrete casing pipe shall conform to ASTM C 76. The
design of reinforced concrete pipe shall be based upon dead and live loads
and jacking forces. RCP casing pipe shall have double-rubber gasket
joints. A cushion material of plywood or hardwood spacers shall be placed
in the joints between adjacent pipe sections being jacked in order to
distribute the jacking load uniformly throughout the entire pipe length
37-3
and avoid radial gasket pressures which may over stress the pipe sockets
or grooves.
c. Casing Pipe Spacers
Insulating spacers shall be installed at the intervals recommended
by the manufacturer. Insulating spacers shall be Pipeline Seal and
Insulator (PSI) Model A12, Calpico Model M-12 or approved equal.
d. Casing Pipe End Seals
Casing Pipe End Seals shall be PSI Model C, Calpico Model C, or
approved equal.
2. Installation of Casing Pipe
The jacking pit shall be of sufficient size for the following: provide ample
working space for soil removal and room for the jacking head, if used; jacks;
jacking frame; reaction blocks; and one or two sections of pipe. Guide rails shall
be accurately set and anchored in the bottom of the pit so that the casing pipe,
while being jacked, will be guided along the prescribed line and grade within the
tolerances allowed.
Excavation or tunneling for the subsequent accommodation of the casing
pipe shall have a diameter of not more than 0.1 foot greater than the outside
diameter of the respective casing pipe and shall be performed by dry bore
methods. All excavated material shall be removed from the casing pipe as
excavation progresses, and no accumulation of such material within the casing
pipe will be permitted.
The leading section of casing pipe shall be equipped with a jacking head
securely anchored thereto and extending at least eighteen inches (18”) from the
leading edge of the pipe to protect the end of the pipe, to maintain equal
pressure around the circumference of the pipe and to prevent any wobble or
variation in alignment during the jacking operation. The jacking head shall cover
the upper two-thirds (2/3) of the casing pipe and project not more than one-half
inch (½”) beyond the outer surface. Excavation shall not be made in advance of
this jacking head.
The driving ends of the casing pipe shall be properly protected against
spalling and other damage, and intermediate joints shall be similarly protected
by the installation of sufficient gearing shims to properly distribute the jacking
stresses. Any section of conduit showing signs of failure shall be removed and
replaced with a new section of casing pipe which is adequate to carry the loads
imposed upon it.
37-4
3. Installation of Conveyance Pipe
Guide rails shall be accurately set to line and grade to insure installation
of the conveyance pipe within allowable limits. Casing pipe diameter shall be
sufficient to allow adjustment of line and grade of the conveyance pipe to meet
allowable tolerance. Minimum casing pipe diameter shall be six inches (6”)
larger than the outside diameter of the conveyance pipe joints.
Conveyance Pipe sections shall be joined outside the casing pipe and then
slid into place. Necessary adjustments in grade shall be made by adjusting the
height of the skids.
All pressure pipe installed within the casing pipe shall be restrained. The
annular space between the conveyance pipe and the casing pipe shall not be
backfilled.
37-4 GROUTING OF VOIDS
Upon completion of the jacking operation, Contractor shall pressure grout
all voids around the outside of the casing pipe. Grouting equipment and material
shall be on the work site before jacking operations and drilling of grout holes are
completed in order that grouting around the jacked casing pipe may be started
immediately after the jacking operations have finished. The spacing of grout
holes shall be eight (8) foot staggered and located 22-1/2 degrees from the
vertical axis of the casing pipe. Pressure shall not exceed five (5) PSI for a
duration sufficient to fill all voids to refusal, following which Contractor shall
repair the drilled holes.
37-5 TOLERANCES
Extreme care shall be exercised by Contractor to maintain line and grade
during jacking operations. Maximum deviation from design line and grade of
casing pipe shall be such that line and grade of the conveyance pipe can be
adjusted a sufficient amount within the casing pipe to achieve the tolerances for
line and grade indicated below. This adjustment shall be made to all pipe
deviating from line and grade and not merely to the sections of pipe nearest the
ends of the casing pipe. Deviation from design line and grade shall not exceed
0.2 foot for line and 0.20 foot for grade per 100 feet of pipe length.
Directly jacked reinforced concrete pipe will be allowed a maximum
deviation of 0.25 foot per one hundred feet (100’) from intended line and grade
unless more stringent tolerances are shown on the Plans or directed by the
Engineer.
37-5
37-6 BORING UNDER CURB, GUTTER AND SIDEWALK
Portions of sanitary sewers, house connections, drainage lines, and water
mains which pass beneath curbs and gutters, sidewalks, and other obstructions
may be placed by boring. If under the curb, gutter and sidewalk, the bore shall
begin at the lip of the gutter and continue to a point from twelve inches (12”)
to eighteen inches (18”) beyond the property line The terminus of all house
connections which are bored shall be exposed in order to determine final line
and grade and to place the locating stake.
If the connection is vitrified clay pipe it shall be plain end pipe connected
with compression type couplings. The bore shall be just large enough to pass the
couplings and need not be backfilled. The maximum length of bore shall be
fifteen feet (15’), unless otherwise specified.
Boring shall not be used on sewer house connections when the required
slope is such that probable deviation of the bore from the intended line would
result in a final slope of less than one-quarter inch (¼”) per foot.
37-7 DRILLING WITH BENTONITE
When required by the Special Provisions or permitted by the Engineer,
casing or conductor pipe may be placed by drilling with bentonite. Equipment,
methods, sequence of operations, and proportions of bentonite, water, and soil
shall be approved by the Engineer prior to drilling. The maximum drilled hole
diameter shall be fourteen inches (14”); the minimum diameter shall be two
inches (2”). The minimum thickness of the bentonite slurry around the pipe wall
shall be one inch (1”). Undermining of pavement or softening of the subgrade
shall not be permitted. Voids shall be filled by injecting bentonite slurry into
the cavity. In soils where the clay content is high, other chemicals may be
substituted for water in a quantity that will establish a workable mixture.
37-8 REPAVING IN EXCAVATED AREAS
Asphalt pavement removed in association with boring and jacking shall be
restored. Pavement restoration shall conform to the provisions of Sections 10,
22, 26-11, and 38 (DWG No. T-8). All exposed edges and aggregate base against
which asphaltic concrete is to be placed shall be tacked with emulsion prior to
paving.
Contractor shall restore the surface to the thickness of the pavement
removed; but in no case shall be less than four (4) inches of asphaltic concrete
and twelve (12) inches aggregate base. Where expansive or other low R value
subgrade material exists as determined by the Engineer, the City will provide an
engineered design of the structural section based on the Caltrans “Flexible
37-6
Pavement Structural Section design Guide for California Cities and Counties” or
other acceptable method and Contractor shall construct the section accordingly.
The new asphaltic concrete pavement shall be type A Max-Medium with a
three-quarter inch (3/4”) maximum aggregate in accordance with Sections 10
and 22. Aggregate base material shall be Class 2 and conform to Sections 10 and
17.
37-9 PAYMENT
Payment for Boring and Jacking shall be at the price bid per lineal foot
for furnishing and placing by boring and jacking the respective sizes and types of
pipe as indicated on the Plans and in the Proposal. The unit price shall include
the casing pipe, if specified or permitted, the conveyance pipe all excavation,
backfill, and all other tools, material, labor, and equipment necessary to
complete the installation.
NUMBER DRAWING TITLE
38-1
Section 38
STANDARD DRAWINGS
38-1 STANDARD DRAWINGS
A. The standard drawings listed follow the Index.
NUMBER DRAWING TITLE
(TRANSPORTATION)
T-11 STANDARD CURB AND GUTTER DETAILS
T-12 BUS STOP REINFORCED CURB & GUTTER DETAIL
T-13 CURB & GUTTER NEAR TREE DETAILS
T-21 SIDEWALK DRIVEWAY DETAIL
T-22 PLANTER STRIP DRIVEWAY DETAIL
T-23 DRIVEWAY DETAIL UNIMPROVED STREET
T-24 STANDARD ALLEY ENTRANCE DETAIL
T-25 HISTORIC SIDEWALK SCORING PATTERN
T-31 THROUGH SDWK DRAIN DETAIL (C&G TYPE 1)
T-32 THROUGH SDWK DRAIN DETAIL (C&G TYPE 2)
T-40 SUBDRAIN TRENCH, DETAIL
T-50 CURB RAMP ELEMENTS DEFINITIONS AND STANDARDS
T-60 CURB RAMP GENERAL DETAILS
T-71 SINGLE PAN CURB RAMPS
T-72 DUAL PAN CURB RAMPS
T-73 SINGLE FLARE CURB RAMPS
T-74 DUAL FLARE CURB RAMPS
T-75 SINGLE COMBINATION CURB RAMP
NUMBER DRAWING TITLE
38-2
T-76 DUAL COMBINATION CURB RAMPS
T-76A STANDARD CURB AND CURB RAMPS
T-77 PLANTER STRIP CURB RAMPS
T-78 TRUNCATED DOME STANDARD LAYOUT
T-79 TRUNCATED DOME DETAIL
T-80 BACKFILL AND RESURFACING IN PAVED AREAS
T-90 CHAIN LINK FENCE AND GATE
T-101 STREET BARRICADE
T-102 CURB, GUTTER AND SIDEWALK BARRICADE
T-103 SIDEWALK BARRICADE
T-110 SIGNS AND BARRICADES AT ENDS OF PAVEMENT WIDENING
T-120 50'-0" CONFORM DETAIL
T-130 18'-0" CONFORM DETAIL
T-140 18'-0" CONFORM DETAIL (WITHOUT KEY CUT)
T-150 SIDE STREET CONFORM DETAIL
T-160 CURB PAINTING
T-180 CROSSWALK, CENTERLINE AND STOP LEGEND
T-185 TRIPLE FOUR CROSSWALK
T-210 OBJECT MARKER DETAIL
T-221 SPEED HUMP DETAIL
T-222 SPEED LUMP DETAIL (A) (w) < 24’
T-223 SPEED LUMP DETAIL (B) (w) ≥ 24’ & < 34’
T-224 SPEED LUMP DETAIL (C) (w) ≥ 34’ & < 40’
T-226 SPEED TABLE DETAIL
NUMBER DRAWING TITLE
38-3
T-227 SPEED LUMP DETAIL (D) (w) ≥ 40’
T-230 FIXED BOLLARD
T-231 REMOVABLE BOLLARD
T-250 NARROW MEDIAN ISLAND WITH REFLECTORS
T-260 MEDIAN ISLAND NOSE DETAIL
T-270 STANDARD 2” PIPE SIGN MOUNTING
T-280 STANDARD ELECTROLIER SIGN MOUNTING
T-290 STANDARD STREET NAME SIGN
T-301 STANDARD OVERHEAD STREET NAME SIGN
T-302 STANDARD OVERHEAD STREET NAME (SMALL SIGNS)
T-303 OVERHEAD STREET NAME SIGN SWING ARM BRACKET
T-304 OVERHEAD STREET NAME SIGN SPECIFICATIONS
T-310 METER PIPES DETAIL
T-350 CONCRETE SURVEY MONUMENT
T-360 TEMPORARY STREET SIGN
(ELECTRICAL)
E-10 METERED SERVICE PEDESTAL
E-20 METERED TRAFFIC SIGNAL SERVICE PEDESTAL
E-30 METERED STREETLIGHT SERVICE PEDESTAL
E-40 ORNAMENTAL STREETLIGHT STYLE 1
E-50 ORNAMENTAL STREET LIGHT 2
E-60 ORNAMENTAL STREETLIGHT FOUNDATION DETAIL
E-70 POST TOP LUMINAIRES AND DETAILS
E-80 ORNAMENTAL STREETLIGHT LOCATIONS
NUMBER DRAWING TITLE
38-4
E-90 ”T” TRENCH DETAIL AND DIRECTIONAL DRILL
E-100 TRENCH DETAIL AND DIRECTIONAL DRILL
E-110 TRAFFIC SIGNAL STANDARD SYMBOLS
E-120 TYPICAL FIXED-TIMED SIGNAL PHASING
E-130 TYPICAL 6 AND 8 SIGNAL PHASING
E-140 CONDUIT LAYOUT GUIDE FOR TRAFFIC SIGNALS
E-150 TRAFFIC SIGNAL PULL BOX
E-160 VIDEO DETECTION AND LOOP LAYOUTS
E-170 LOOP SAW CUTTING
E-180 LOOP SAW CUTTING
E-190 LOOP WINDING PATTERNS
E-200 VIDEO DETECTION DETAILS
E-210 VIDEO DETECTION GENERAL NOTES
E-220 VIDEO DETECTION CAMERA MOUNTING DETAILS
E-230 CCTV INSTALLATIONS DETAILS (1)
E-240 EMERGENCY VEHICLE PREEMTION MOUNTING
E-250 FIBER OPTIC CONDUIT LAYOUT
E-260 FIBER OPTIC CABLE INSTALLATION DETAILS (N48 VAULT)
E-270 FIBER OPTIC CABLE INSTALLATION DETAILS (#6E PULL BOX)
E-280 N48 SPLICE VAULT DETAILS
E-290 N48 SPLICE VAULT GENERAL NOTES
(WATER)
W-102 TRACER/LOCATOR WIRE FOR ALL WATER MAINS
W-103 CHANGES IN MAIN ELEVATION & THRUST BLOCKING FOR WATER MAINS
NUMBER DRAWING TITLE
38-5
W-104 BACKFILL & REPAIR AT SEWER & DRAIN UTILITY CROSSING
W-105 WATER MAIN “CUT-IN” INSTALLATIONS
W-106 RAISING AND LOWERING WATER MAINS
W-107 TYP. CONNECTIONS FOR INTIAL FILLING OF NEW WATER MAIN
W-201 FIRE HYDRANT INSTALLATIONS
W-202 FIRE HYDRANT PROTECTION
W-203 REQUIREMENTS FOR FIRE HYDRANT USE PERMITS WATER TRUCKS
W-204 PORTABLE WATER TRUCK FILL STATIONS
W-205 VERTICAL SHOE FIRE HYDRANT
W-301 STANDARD 2-INCH AND 4-INCH BLOW-OFF
W-302 TEMPORARY 2-INCH SAMPLING DEVICE
W-303 STANDARD VALVE BOX INSTALLATION FOR CITY STREETS, ALLEY EASEMENTS
W-304 STANDARD VALVE BOX AND DROP CAP
W-306 RAISING VALVE BOXES AND DROP CAPS
W-307 WATER SERVICE BOX AND COVERS
W-308 VALVE OPERATING NUT EXTENSION
W-400 METER BOX AND LIDS
W-401 LOCATION OF RESIDENTIAL WATER METERS-NEW CONSTRUCTION
W-402 INSTALLATION OF RESIDENTIAL WATER METER SETTER & BOX
W-403 STD WATER SERVICE TAPS 1-INCH THRU 2-INCH
W-404 TAP EXCAVATION REQUIREMENTS ON EXISTING MAINS THRU 12” TAPS
W-405 1” RES. WATER SERVICES
W-406 INSTALLATION OF 1 INCH RP ASSEMBLY WITH WATER METER
W-501 APPROVED INSTALLATION FOR AIR GAP SEPARATION
NUMBER DRAWING TITLE
38-6
W-504 INSTALLATION OF METERED TEMP. WTR SVC W/BACKFLOW PREVENTERS
W-505 INSTALLTION OF 1 ½ TO 2-INCH RP ASSEMBLY WITH WATER METER
W-507 1 ½” & 2” METERED WATER SERVICE WITH NO RP DEVICE
W-510 4-INCH & LARGER FIRE SERVICE WITH DOUBLE CHECK VALVE ASSEMBLY
W-515 3”-8” WATER SERVICE BELOW GROUND WITH BYPASS (COMPOUND METERS)
W-604 2-INCH & SMALLER BACKFLOW ASSEMBLY IN LANDSCAPED SETBACK OWNED
BY CITY
W-606 2-INCH & SMALLER RP ASSEMBLY W/METER ON ALL CITY IRRIGATION SYSTEMS
W-607 3-INCH & LARGER RP DEVICE W/METER ON ALL CITY IRRIGATION SYSTEMS
W-608 INSTALLATION OF 3” & LARGER METERED WTR SERV w/ BF ASSEMBLY
W-609 3-INCH & LARGER RP DEVICE W/METER ON NON CITY IRRIGATION & LOOPED
DOMESTIC SYSTEM
W-702 ACCESS MANHOLE DETAILS
W-801 BUTTERFLY VALVE STANDARD BURIED INSTALLATION DETAIL
W-802 1 AND 2 INCH AIR VACUUM AND AIR RELEASE VALVE ABOVE GROUND
INSTALLATIONS
W-803 3 INCH & LARGER AIR VACUUM AND AIR RELEASE VALVE ABOVE GROUND
INSTALLATIONS
W-803A 3 INCH & LARGER AIR VACCUM AND AIR RELEASE VALVE ABOVE GROUND
INSTALLATIONS WITHOUT FLOODSAFE
W-804 6 INCH BLOW OFF FOR DUCTILE IRON PIPE
W-805 6-INCH BLOW OFF FOR WELDED STEEL AND CONCRETE CYLINDER PIPE
W-901 CASING INSULATOR SPACING ASSEMBLY
W-902 FLANGE INSULATOR FOR T-MAIN SIDE OUTLET THRU 12-INCH PIPE
W-903 CCP AND WSP JOINT DETAILS
W-904 DETAIL OF FIELD WELDED BUTT-STRAP JOINT
W-905 DIELECTRIC INSULATING FLANGE DETAIL
NUMBER DRAWING TITLE
38-7
W-1001 INSULATING JOINT TEST STATION
W-1002 TEST STATION INSTALLATION DETAIL
W-1004 TEST STATION HOUSING DETAIL IN TRAFFIC/NON-TRAFFICE AREAS
W-1005 INSULATING JOINT TEST BOARD DETAIL
W-1006 TEST BOARD DETAIL
W-1008 CCP AND WS PIPE JOINT BOND CABLE DETAIL
W-1009 CCP AND WS PIPE JOINT BOND CLIP DETAIL
W-1011 EXOTHERMIC WELD
W-1012 JOINT BOND CABLE DETAIL DUCTILE-WS-CCP
W-1013 GALVANIC ANODE INSTALLATION DETAIL
W-1014 ANODE TEST BOARD DETAIL
W-1015 ANODE CABLE IDENTIFICATION DETAIL
(SEWER AND DRAINAGE)
S-9 INLET GRATE WITH CHAIN & LABEL
S-10 TYPE “B” DPOP INLET
S-20 MODIFIED TYPE “B” D.I. (WITH TRAP AND SUMP)
S-30 DITCH BOX
S-40 TYPE “B” FRAME AND GRATE
S-42 GUTTER DRAIN NO. 20
S-45 GUTTER DRAIN NO. 21
S-50 GUTTER DRAIN NO. 22
S-55 GUTTER DRAIN NO. 24
S-60 OPTIONAL GUTTER DITCH INSTALLATION
S-65 ROLLED CURB DROP BOX INLETS
NUMBER DRAWING TITLE
38-8
S-66 ROLLED CURB TRANSITION TYPE “B” DROP INLETS
S-67 CURB TYPE 2 TRANSITION FOR TYPE “B” DROP INLETS
S-70 STANDARD MANHOLE No. 3
S-80 STANDARD MANHOLE No. 3A
S-90 MANHOLE # 3 (WITH TRAP AND SUMP)
S-110 STANDARD MANHOLE No. 4
S-120 SADDLE TYPE MANHOLE
S-130 INSIDE/OUTSIDE DROP CONNECTION FOR MAIN LINES 6
S-135 INSIDE DROP CONNECTION FOR MAIN LINES & SERVICES ≤ 6”
S-140 STANDARD MANHOLE HEAD 1, COVER A
S-150 STANDARD MANHOLE HEADS 3 & 4, COVER B
S-160 STANDARD MANHOLE HEAD AND COVER 1-C
S-230 UTILITY CROSSING
S-250 CONCRETE PROTECTIVE COVERING
S-260 A.B.S SEWER SERVICE
S-261 CAST IRON CLEANOUT HEAD & COVER
S-265 TYPICAL SEWER SERVICE CLEANOUT LOCATIONS
S-270 PIPE INLET/OUTLET STRUCTURE 22" PIPE & SMALLER
S-280 PIPE INLET/OUTLET STRUCTURE 24" TO 60" PIPES
S-290 TRASH RACK 24" TO 60" PIPES
S-300 PIPE OUTLET ACCESS CONTROL RACK
S-310 TYPICAL JUNCTION BOX PIPE CONNECTION DETAIL
S-320 CONCRETE CLOSURE COLLAR
S-400 POST & CABLE FENCE DETAIL
NUMBER DRAWING TITLE
38-9
(WATER QUALITY)
Q-10 STABILIZED CONSTRUCTION ENTRANCE
Q-30 STORM DRAIN INLET FILTER BAG
Q-40 FIBER ROLLS
Q-50 SILT FENCE - 36”
Q-60 SILT FENCE 18”
Q-70 STORM DRAIN MESSAGE LAYOUT
Q-80 CONCRETE WASHOUT
Q-90 EROSION CONTROL BLANKETS/MATS SLOPE INSTALLATION
(LANDSCAPING)
L-100 SINGLE FLOW SENSOR
L-101 SINGLE MASTER VALVE
L-102 IRRIGATION GATE VALVE 3 INCHES & SMALLER
L-103 IRRIGATION GATE VALVE 4 INCHES AND LARGER
L-104 QUICK COUPLER
L-105 REMOTE CONTROL VALVE
L-106 TRENCH
L-107 VALVE BOX
L-108 WIRE CONNECTION
L-109 ROTOR
L-110 SPRAY HEAD
L-111 TREE BUBBLER
L-112 TREE SPRAY HEAD LAYOUT
L-200 GROUNDCOVER PLANTING
NUMBER DRAWING TITLE
38-10
L-201 TREE PLANTING
L-202 VINE PLANTING
L-203 SHRUB PLANTING
L-300 PLAY AREA CATCH BASIN
L-301 PLAY AREA CURB
L-302 12 INCH PLAY AREA CURB
L-400 9 INCH MOW CURB
L-401 INFIELD FINES
L402 DECOMPOSED GRANITE TRAIL
L500 DRINKING FOUNTAIN
L-501 SURFACE AND INGROUND MOUNT
38-11
38-2 REQUESTS FOR CLARIFICATION
A. Contractor requests for clarification of the plans and/or specifications shall be
directed to the ENGINEER in writing. Such requests shall not be received directly from
a Subcontractor or Supplier.
B. Normally, a separate form shall be used for each specific item for which a clarification
is required. Requests for clarification for more than one item using a single transmittal
form will be permitted only when the items are so functionally related that
expediency indicates review of the group of items as a whole.
C. The ENGINEER will reply to Contractor’s request for clarification within fifteen (15)
working days following receipt by the ENGINEER.
38-3 DEVIATION REQUESTS
A. Contractor requests for deviation from the plans and/or specifications shall be
directed to the ENGINEER in writing. Such requests shall not be received directly from
a subcontractor or Supplier.
B. The ENGINEER will reply to Contractor’s request for deviation from the plans within
fifteen (15) working days following receipt by the ENGINEER.
i - 1
INDEX
Subject Page
A
Addendum ................................................................................................. 1-1
Adequate Resources, Work Schedule and ............................................................. 7-1
Adhesive Capsules for Dowel Anchorage ........................................................... 10-55
Aggregate
Bases .................................................................................................. 10-6
Concrete .............................................................................................. 10-1
Aggregate Subbase (Graded) ........................................................................... 10-7
Agreement ................................................................................................. 1-1
Agreement to Assign ..................................................................................... 2-6
American Association of State Highway and Transportation Officials ............................ 1-1
American Society for Testing Materials ............................................................... 1-1
American Water Works Association .................................................................... 1-1
Approval of Contractor’s Plans No Release from Liability ......................................... 6-12
Approval of Sources of Supply of Materials .......................................................... 5-11
Appurtenances (Water Transmission)
Air Release Valves ................................................................................ 10-35
Air Vacuum Valves ................................................................................ 10-35
Blind Flanges ....................................................................................... 10-36
Dished Heads ...................................................................................... 10-36
Asphalts, Liquid Asphalts and Asphaltic Emulsions ............................................... 10-13
Asphaltic Concrete
Density Testing, Pavement ........................................................................ 22-8
Keycutting, Conforms, and Planing ............................................................... 22-3
Materials ............................................................................................. 22-1
Mixing Equipment ................................................................................... 22-2
Pavement Reinforcing Fabric ...................................................................... 22-9
Pay Factors ........................................................................................... 22-8
Payment ............................................................................................ 22-11
Placing ................................................................................................ 22-5
Placing, General Requirements ................................................................... 22-2
Tack Coat ............................................................................................ 22-6
Type and Mix Design ................................................................................ 22-1
Spreading and Compacting ........................................................................ 22-6
Assignment of Claims .................................................................................... 8-4
Award and Execution of Contract ...................................................................... 3-1
B
Backfill
Roadway .............................................................................................. 14-1
Slurry Cement ..................................................................................... 10-11
Structure ............................................................................................. 14-1
i - 2
Trench ................................................................................................ 14-2
Backflow Prevention Assembly ...................................................................... 10-47
Bases
Aggregate ............................................................................................ 10-6
Cement Treated ..................................................................................... 10-8
Laying ................................................................................................. 17-1
Treated Permeable ................................................................................. 10-8
Bedding Sand ........................................................................................... 10-10
Bid .......................................................................................................... 1-1
Bidder ...................................................................................................... 1-1
Bituminous Seals
Cape ............................................................................................. 23-2, 10
Chip ............................................................................................... 23-1, 7
General Requirements............................................................................ 23-10
Measurement & Payment ........................................................................ 23-13
Placing .............................................................................................. 23-12
Sand ................................................................................................... 23-2
Slurry ................................................................................................. 23-2
Types and Mix Design ............................................................................... 23-1
Boring and Jacking
Boring Under Curb, Gutter and Sidewalk ........................................................ 37-5
Drilling with Bentonite ............................................................................. 37-5
General ............................................................................................... 37-1
Grouting of Voids .................................................................................... 37-4
Payment .............................................................................................. 37-6
Repaving in Excavated Areas ...................................................................... 37-5
Single-Pass System .................................................................................. 37-1
Tolerances ........................................................................................... 37-4
Two-Pass System .................................................................................... 37-2
Butterfly Valves & Flexible Couplings (Transmission) ............................................ 10-32
Butterfly Valves (Transmission)
Coating, (Interior, Exterior) ............................................................ 10-34
General .................................................................................... 10-32
Manual Valve Actuator .................................................................. 10-34
Materials and Construction ............................................................. 10-33
C
Castings for Manholes, Covers, Etc. ................................................................ 10-18
Certain Laws Affecting the Work ....................................................................... 6-1
Changes in the Work
.............................................................................................. 4-2
Change Order .................................................................................... 1-1
City................................................................................................ 1-1
City Council ...................................................................................... 1-1
City Manager ..................................................................................... 1-2
Claims
Assignment of ............................................................................... 8-4
Disputed ...................................................................................... 4-5
i - 3
Notice of Claims for Additional Compensation or Damages .......................... 4-5
Review by Claim Review Committee and Issuance of Decision by Department Director
................................................................................................ 4-6
Cleaning Up ...................................................................................... 4-1
Clearing and Grubbing, Tree Removal
Disposal ..................................................................................... 12-2
Existing Facilities .......................................................................... 12-1
General ...................................................................................... 12-1
Payment ..................................................................................... 12-2
Trees ......................................................................................... 12-1
Vegetation and Debris..................................................................... 12-1
Commercial Fertilizer ....................................................................... 10-44
Comparison of Bids ............................................................................. 3-1
Completion Date ................................................................................ 1-2
Completion of Work and Final Payment ..................................................... 8-2
Compliance with OSHA ......................................................................... 6-7
Conformity with Plans and Allowable Deviations .......................................... 5-1
Concrete
Aggregates .................................................................................. 10-1
Curing Compounds for ..................................................................... 10-6
Water for .................................................................................... 10-1
Concrete Structures
Concrete Placed Under Water ......................................................... 20-14
Construction Joints ...................................................................... 20-10
Curing ..................................................................................... 20-11
Design of Mixes ............................................................................. 20-8
Drain Inlets ................................................................................. 20-4
Expansion Joints and Rubber Waterstops ............................................ 20-10
Flatness Tolerance for Floor Slab ....................................................... 20-8
Flatwork ................................................................................... 20-11
Finishing Formed Surfaces .............................................................. 20-11
Footings ..................................................................................... 20-4
Formwork ................................................................................... 20-4
General ...................................................................................... 20-1
Grouting and Drypacking ............................................................... 20-13
Measurement of Quantities ............................................................. 20-15
Payment ................................................................................... 20-15
Placing Concrete ........................................................................... 20-9
Preparing to Place Concrete ............................................................. 20-8
Quality Control ........................................................................... 20-14
Reinforcement ............................................................................. 20-7
Removal of Forms .......................................................................... 20-6
Surface Finishes .......................................................................... 20-11
Weep Holes in Walls ..................................................................... 20-13
Construction Materials ........................................................................ 10-1
Contract
Assignment ................................................................................... 7-1
i - 4
Definition of ................................................................................. 1-2
Contract Documents ............................................................................ 1-2
Contract Price ................................................................................... 1-2
Contractor
Cooperation of .............................................................................. 5-3
Definition of ................................................................................. 1-2
Legal Address ............................................................................... 6-13
Not an Agent of City ....................................................................... 6-12
Payments by ................................................................................. 8-5
Shall Not Mortgage Equipment ........................................................... 6-13
Control of Work and Materials ................................................................ 5-1
Control Density Fill (CDF) ................................................................... 10-11
Controlling Operation .......................................................................... 1-2
Coordination of Contract Documents ........................................................ 5-2
Critical Path Method (CPM) Schedule ........................................................ 1-2
Crushed Rock ................................................................................. 10-10
Crushed Rock, Clean ........................................................................ 10-12
Culvert, Driveway .............................................................................. 28-1
Curbs, Gutters, and Sidewalks
Concrete .................................................................................... 24-1
Concrete Cutting ........................................................................... 24-1
Curb Dowel and Tie Bars ................................................................ 10-18
Curbs & Gutter Reconstruction to Accommodate Driveways ........................ 24-4
Curb Ramps and Driveways ............................................................... 24-4
Curing ....................................................................................... 24-3
Damage and Repairs ....................................................................... 24-4
Dowel Reinforcement ..................................................................... 24-4
Expansion Joints and Score Lines ........................................................ 24-2
Extruded (Slip-Form) ...................................................................... 24-2
Finishing ..................................................................................... 24-3
Formwork Nonextruded ................................................................. 24-1
Payment ..................................................................................... 24-5
Slope and Width of Sidewalks ............................................................ 24-4
Subgrade and Aggregate Base ............................................................ 24-1
D
Day, Definition of ............................................................................... 1-2
Date of Signing Contract ....................................................................... 1-2
Definitions and terms .................................................................................... 1-1
Payment Bond ........................................................................................ 1-4
Performance Bond ................................................................................... 1-4
Project Estimate ..................................................................................... 1-4
Proposal Form ........................................................................................ 1-4
Proposal Guarantee .................................................................................. 1-4
Subcontractor ........................................................................................ 1-5
i - 5
Determination of Amount Bid Mathematical Error ....................................... 2-3
Detours ........................................................................................... 7-7
Director .................................................................................................... 1-2
Disputed Claims ........................................................................................... 4-5
Disqualification of Bidders .............................................................................. 2-5
Division Manager .......................................................................................... 1-2
Dowel Anchorage, Adhesive Capsules .............................................................. 10-55
Drain Inlets, Gutter Drains and Ditch Boxes ......................................................... 30-1
Driveway Culvert and Sidewalk French Drains ...................................................... 28-1
Duties and Powers of Inspectors ...................................................................... 5-10
E
Earthwork, Excavation, Embankment and Subgrade ............................................... 14-1
Electric Automatic Controller ....................................................................... 10-46
Electric Remote Control Valves Sizes ¾” to 2” ................................................. 10-48
Electrical
Bonding and Grouning ............................................................................ 34-16
Conductors ......................................................................................... 34-13
Conduits ............................................................................................ 34-11
Detector Loop and Handhole .................................................................... 34-12
Electric Service .................................................................................... 34-16
Equipment and Drawings ........................................................................... 34-1
Equipment to be Supplied ......................................................................... 34-3
Excavating and Backfill ............................................................................ 34-5
Field Test .......................................................................................... 34-17
Foundations .......................................................................................... 34-4
General ............................................................................................... 34-1
Inspection .......................................................................................... 34-18
Interconnect ....................................................................................... 34-17
Maintaining Existing Electrical Facilities ........................................................ 34-4
Maintenance of Traffic and Public Safety ....................................................... 34-2
Painting ............................................................................................. 34-11
Panelboards ........................................................................................ 34-11
Protection of Existing Improvements............................................................. 34-2
Pull Boxes .......................................................................................... 34-12
Rules and Regulations .............................................................................. 34-1
Salvage ............................................................................................. 34-21
Scheduling of Work ................................................................................. 34-2
Service Pedestals.................................................................................. 34-16
Standards ........................................................................................... 34-17
Traffic Signal Controller and Intersection Turn On .......................................... 34-20
Traffic Signal Controller Functional Test ...................................................... 34-13
Traffic Signal Hardware .......................................................................... 34-18
Vehicle and Bicycle Detection .................................................................. 34-18
Wiring ............................................................................................... 34-15
Electronic Marker System (EMS) ..................................................................... 10-49
Eliminated Items ......................................................................................... 4-4
Embankment and Fill ...................................................................................
14-4
i - 6
Engineer
Authority of ........................................................................................... 5-1
Definition of .......................................................................................... 1-2
Examination of Contract Documents and Site of Work .............................................. 2-1
Excavation
Roadway .............................................................................................. 14-1
Structure ............................................................................................. 14-1
Trench ................................................................................................ 14-2
Execution of Contract ................................................................................... 3-2
Existing Facilities
Maintaining Water, Sewer, and Drainage Flows ................................................ 13-1
Pavement for Trench Surface Restoration ...................................................... 13-4
Payment .............................................................................................. 13-5
Protection ............................................................................................ 13-1
Removing/Relocating ............................................................................... 13-3
Extra Work ................................................................................................. 4-4
Extra Work a Part of the Contract ..................................................................... 8-6
Expansion Joint Filler, Premoulded ................................................................... 10-1
Explosives
Use of ................................................................................................. 6-13
F
Failure to Execute Contract ............................................................................ 3-2
Federal Specifications ................................................................................... 1-3
Fencing Chain Link
Constructing ......................................................................................... 31-1
Materials .................................................................................... 10-42, 31-1
Payment .............................................................................................. 31-2
Vinyl Slats ............................................................................................ 31-2
Field Order ................................................................................................ 1-3
Final Acceptance of the Work .......................................................................... 8-3
Final Payment ............................................................................................. 8-3
Finance Director .......................................................................................... 1-3
Fire Hydrants ........................................................................................... 10-36
Fixed Cost ................................................................................................. 1-3
Flexible Couplings (Transmission) ................................................................... 10-35
Float Period ............................................................................................... 1-3
Form of Agreement and Surety Bonds ................................................................. 3-3
French Drains, Sidewalk ................................................................................ 28-1
G
Geogrid ................................................................................................... 10-8
Grout
Cement ............................................................................................. 10-52
i - 7
Drypack ............................................................................................. 10-51
Epoxy ............................................................................................... 10-53
Nonshrink ........................................................................................... 10-52
Grouting, Pressure .................................................................................... 10-55
Gunite (See Pneumatically Applied Mortar) ......................................................... 33-1
H
Headers ................................................................................................... 18-1
Holiday Season Construction Moratorium ............................................................ 6-10
Housekeeping Practices ................................................................................. 6-6
I
Inspection ................................................................................................ 5-10
Inspection and Payments No Waiver of Contract Provisions ....................................... 8-6
Inspector
Definition of .......................................................................................... 1-3
Duties and Powers of ............................................................................... 5-10
Intent of Plans and Specifications ..................................................................... 4-1
Iron Sulfate ............................................................................................. 10-44
Irrigation System
Backfill of Irrigation Pipelines ..................................................................... 36-7
Backflow Prevention Assemblies .................................................................. 36-2
Conduit ............................................................................................... 36-2
Connections to existing Streetscape ............................................................. 36-2
Control Conductors ........................................................................ 10-47, 36-3
Control Valves ....................................................................................... 36-3
Electrical Automatic Controllers .................................................................. 36-3
General ............................................................................................... 36-1
Guarantee ............................................................................................ 36-1
Installation of Irrigation and Potable Pipe ...................................................... 36-5
Manufacturer’s Warranties ........................................................................ 36-1
Payment .............................................................................................. 36-8
Pipe and Fittings .................................................................................... 36-2
Quick Coupling Valves .............................................................................. 36-5
Record Drawings .................................................................................... 36-1
Repaving .............................................................................................. 36-8
Salvage ............................................................................................... 36-2
Sprinklers ............................................................................................. 36-4
Sterilizing Plastic Potable Pipe ................................................................... 36-7
Swing Joint Assemblies ............................................................................. 36-4
Testing ................................................................................................ 36-6
Trenching ............................................................................................ 36-5
Type B Sprinkler Riser Assemblies ................................................................ 36-4
Valve Boxes ................................................................................. 10-48, 36-3
Valve Manifolds ...................................................................................... 36-4
Water Taps on City Mains .......................................................................... 36-1
Issuance of Punchlist ..................................................................................... 8-2
i - 8
Items Containing Trade Secrets or Proprietary Rights Prohibited ................................ 6-16
J
Joint Materials
Clay Pipe ........................................................................................... 10-41
Concrete Pipe ..................................................................................... 10-41
Manholes ........................................................................................... 10-41
Joint Venture Bids ........................................................................................ 2-6
L
Landscape Architect ..................................................................................... 1-4
Landscape Fill ............................................................................................ 14-5
Landscape Planting
Certificate of Compliance Materials ............................................................ 35-1
General ............................................................................................... 35-1
Hydro-Seed Placement ............................................................................. 35-8
Hydro-Seed Placement (Non-irrigated Native Grass/Wildflower) .......................... 35-11
Inspection, Final .................................................................................. 35-22
Inspection, Pre-Final ............................................................................. 35-22
Maintenance ....................................................................................... 35-19
Maintenance Period, Start of .................................................................... 35-18
Materials ............................................................................................. 35-1
Measurement of Quantities ........................................................................ 35-1
Payment ............................................................................................ 35-23
Planting Seed ........................................................................................ 35-8
Planting Trees ....................................................................................... 35-3
Preparing Planting Areas ........................................................................... 35-2
Record Drawings and Controller Charts ........................................................ 35-22
Replacement ....................................................................................... 35-18
Shrub and Groundcover Areas ..................................................................... 35-4
Sod Placement ..................................................................................... 35-15
Watering ............................................................................................ 35-17
Weed and Pest Control ............................................................................. 35-3
Laws or Regulations ...................................................................................... 1-3
Laws
Certain Laws Affecting the Work .................................................................. 6-1
Local Ordinances ..................................................................................... 6-2
State Laws ............................................................................................ 6-1
To be Observed ....................................................................................... 6-1
Laying Aggregate Bases ................................................................................. 17-1
Laying Road-Mixed and Plant-Mixed Cement Treated Bases ...................................... 17-2
LBE Participation ......................................................................................... 1-3
Legal Relations and Responsibilities to the Public ................................................... 6-1
Licensing of Bidders ...................................................................................... 2-5
Lime Stabilization ....................................................................................... 10-8
Lines and Grades ......................................................................................... 4-1
Liquidated Damages ...................................................................................... 1-3
i - 9
M
Main and Trunkline Utilities ........................................................................... 6-15
Manholes, Sanitary Sewer & Storm Drains
Adjusting Manhole Heads .......................................................................... 25-6
Castings ............................................................................................... 25-1
Construction of Manholes (New or Reconstructed) ............................................. 25-1
Flusher Branches .................................................................................... 25-7
Payment .............................................................................................. 25-7
Standard .............................................................................................. 25-1
Manual Control Valves ................................................................................ 10-48
Manufacturer’s Direction ................................................................................ 5-9
Materials
Property Rights in ................................................................................... 6-13
Storage of ............................................................................................. 5-8
Mathematical Error, Determination of Amount Bid ................................................. 2-3
Measurement of Quantities ............................................................................. 8-1
Methods of Sampling and testing ...................................................................... 5-12
Moving or Changing Utilities and Water Services ................................................... 29-1
N
Notice of Claims for Additional Compensation or Damages ........................................ 4-5
Notice to Contractors .................................................................................... 2-1
O
On Street Parking Removal ............................................................................. 6-14
P
Parking Removal, On Street ............................................................................ 6-14
Payment
By Contractor ......................................................................................... 8-5
By Cost and Percentage ............................................................................. 8-6
Final .................................................................................................... 8-3
On Engineer’s Certificate ........................................................................... 8-1
Scope of ............................................................................................... 8-1
Performance and Payment Bonds ...................................................................... 3-1
Permits, Licenses and Fees ............................................................................. 6-4
Pipe, Sewer and Drainage
Acrylonitrile-Butadiene-Styrene (ABS) ......................................................... 10-14
Glass-Fiber-Reinforced Thermosetting-Resin ................................................. 10-17
i - 10
Closed Profile Poly Vinyl Chloride (CPPVC).................................................... 10-14
Corrugated HDPE .................................................................................. 10-17
Corrugated Metal .................................................................................. 10-16
Deflection .......................................................................................... 10-13
High Density Polyethylene (HDPE) Solid Wall Fusion Jointed ............................... 10-14
Joints ............................................................................................... 10-13
Manhole Connections ............................................................................. 10-13
Polyvinyl Chloride (PVC) ......................................................................... 10-15
Reinforced Concrete (RCP) ...................................................................... 10-16
Sewer and Drainage ............................................................................... 10-13
Vitrified Clay Pipe (VCP) ......................................................................... 10-16
Pipe, Water Distribution (12inch diameter & smaller)
Ductile Iron ........................................................................................ 10-19
Fittings ............................................................................................. 10-20
Polyvinyl Chloride (PVC) ......................................................................... 10-19
Pipe, Water Transmission (greater than 12 inch diameter)
Concrete Cylinder (CCP) ......................................................................... 10-25
Ductile Iron (DIP) .................................................................................. 10-29
Welded Steel (WSP) ............................................................................... 10-22
Plans ........................................................................................................ 1-4
Project Plans.......................................................................................... 1-4
Standard Details ...................................................................................... 1-4
Plants.................................................................................................... 10-44
Plastic Irrigation Pipe ................................................................................. 10-45
Plastic Irrigation Pipe Fittings ....................................................................... 10-47
Plastic Potable Pipe ................................................................................... 10-46
Plate Culvert, Field Assembled ...................................................................... 10-17
Pneumatically Applied Mortar
Curing and Protecting .............................................................................. 33-3
General ............................................................................................... 33-1
Joints ................................................................................................. 33-3
Materials ............................................................................................. 33-1
Mixing ................................................................................................. 33-1
Payment .............................................................................................. 33-4
Placing ................................................................................................ 33-2
Preparation of Surface ............................................................................. 33-2
Proportions ........................................................................................... 33-1
Reinforcement ....................................................................................... 33-3
Polymer Concrete (For Resurfacing or Patching) ................................................. 10-54
Portland Cement ........................................................................................ 10-1
Portland Cement Concrete
Composition .......................................................................................... 10-2
Curing Compounds for Concrete .................................................................. 10-6
Grading and Composition Requirements ......................................................... 10-3
Mixing ................................................................................................. 10-4
Placing ................................................................................................ 10-5
Proportioning ........................................................................................ 10-2
Water Control ....................................................................................... 10-5
Portland Cement Concrete Pavement
Curing ................................................................................................. 19-3
Cutting ................................................................................................ 19-1
i - 11
Damage and Repair ................................................................................. 19-3
Expansion Joints in Alley Pavement .............................................................. 19-1
Finishing .............................................................................................. 19-2
General Description................................................................................. 19-1
Payment .............................................................................................. 19-3
Placing ................................................................................................ 19-2
Protection of ......................................................................................... 19-3
Sideforms ............................................................................................. 19-1
Subgrade ............................................................................................. 19-1
Preconstruction Photographs .......................................................................... 11-1
Preparation for Testing ................................................................................. 5-12
Preparation of Proposal ................................................................................. 2-2
Prequalification of Bidders .............................................................................. 2-6
Pressure Grouting ..................................................................................... 10-55
Project Estimate .......................................................................................... 2-1
Property Rights in Materials ........................................................................... 6-13
Proposal Form ............................................................................................. 2-1
Proposal Requirements and Conditions ............................................................... 2-1
Proposal Form ............................................................................................. 1-4
Proposal Guarantee ...................................................................................... 2-3
Proprietary Rights Prohibited, Items Containing Trade Secrets or ............................... 6-16
Protection of City Against Patent Claims ............................................................. 6-4
Protection of Work, Persons and Property Against Damage ........................................ 7-3
Provisions for Emergencies .............................................................................. 5-7
Public Convenience and Safety ......................................................................... 6-5
Public Opening of Proposal.............................................................................. 2-5
Q
Quality of Materials and Workmanship ................................................................ 5-9
Quick Coupling Valves ................................................................................ 10-49
R
Record Drawings .......................................................................................... 5-6
Regulations, Laws and ................................................................................... 1-3
Reinforcement
Bending ............................................................................................... 21-2
Cleaning .............................................................................................. 21-2
Materials ............................................................................................. 21-1
Payment .............................................................................................. 21-4
Placing ................................................................................................ 21-3
Preparation for Placing ............................................................................. 21-2
Submittals ............................................................................................ 21-1
Welds and Splicing .................................................................................. 21-3
Reinforcing Steel ...................................................................................... 10-17
Rejection of Proposals ................................................................................... 2-3
Release at Time of Final Payment ..................................................................... 8-5
Relief of Bidders .......................................................................................... 2-5
Removal of Rejected Materials and Structures ..................................................... 5-11
i - 12
Removal of Unsatisfactory Employees ................................................................. 7-3
Request for Modification of Work ...................................................................... 5-6
Return of Proposal Guarantees ......................................................................... 3-2
Right to Perform Extra Work ............................................................................ 5-7
Right to Retain Imperfect Work ........................................................................ 5-8
S
Sanitary Regulations ..................................................................................... 6-5
Sanitary Sewer and Storm Drain Manholes ........................................................... 25-1
Saturday, Sunday, Holiday, and Night Work .......................................................... 7-2
Scope of Work ............................................................................................. 4-1
Seed ..................................................................................................... 10-44
Separate Contracts ....................................................................................... 7-3
Sewer and Drainage Pipe ............................................................................. 10-13
Sewer and Drain Pipe, Laying
Dewatering ........................................................................................... 26-2
Drain and Ditch Box Leads ....................................................................... 26-12
Excavation ........................................................................................... 26-1
Health & Safety ..................................................................................... 26-3
Joints ............................................................................................... 26-13
Laying Pipe ........................................................................................... 26-4
Materials/Types ..................................................................................... 26-3
Payment ............................................................................................ 26-24
Protective Covering ............................................................................... 26-13
Repaving Trenches ................................................................................ 26-17
Services ............................................................................................. 26-12
Testing .............................................................................................. 26-13
TV Inspection ...................................................................................... 26-18
Shotcrete (See Pneumatically Applied Mortar) ...................................................... 33-1
Slurry Cement Backfill ................................................................................ 10-11
Soil Amendment ....................................................................................... 10-44
Special Provisions......................................................................................... 1-5
Specifications ............................................................................................. 1-5
State Specifications ...................................................................................... 1-5
Storage of Materials and Equipment ................................................................... 5-8
Subcontractors ............................................................................................ 2-4
Subgrade .................................................................................................. 14-5
Submission of Proposal .................................................................................. 2-5
Submittals ................................................................................................. 5-5
Substantially Complete .................................................................................. 1-5
Subsurface Drains...................................................................................... 10-17
Suggestions to Contractor Adopted at Contractor’s Own Risk ..................................... 5-6
Supplier .................................................................................................... 1-5
Survey
Construction Stakes .................................................................................. 5-4
Permanent Survey Monuments ..................................................................... 5-4
Suspension of Work to Protect Health, Safety or Welfare of Persons or Property .............. 5-7
i - 13
T
Terms and definitions .................................................................................... 1-1
Temporary Paving ....................................................................................... 14-3
Temporary Suspension of Work ......................................................................... 7-5
Time of Award ............................................................................................ 3-1
Time of Completion ...................................................................................... 7-4
Trade Names and Alternatives.......................................................................... 5-9
Trade Secrets or Proprietary Rights Prohibited, Items Containing ............................... 6-16
Traffic Control Requirements ........................................................................... 6-7
Traffic Signs, Markings, and Barricades
Painted Markings .................................................................................... 32-5
Raised Reflective Markers ......................................................................... 32-6
Signs .................................................................................................. 32-1
Street Barricades .................................................................................... 32-8
Temporary Markings ................................................................................ 32-6
Temporary Street Signs ............................................................................ 32-8
Thermoplastic Markings ............................................................................ 32-2
Trench Safety Plans ...................................................................................... 6-7
U
Unsuitable Material/Import .................................................................. 14-5
Utilities and Franchises ....................................................................... 29-1
Utilities and Water Services, Moving or Changing ......................................... 29-1
Utilities, Main and Trunkline ................................................................. 6-15
Utility Connection, Provision for ............................................................ 29-1
V
Valves ................................................................................................... 10-39
Valve Boxes and Covers, Drop Caps, and Service Valve Boxes .................................. 10-40
W
Water for Concrete...................................................................................... 10-1
Water Distribution Systems
Air Release Valves, Adjusting ................................................................... 27-27
Appurtenances ..................................................................................... 27-11
Bedding and Backfilling of Trenches ........................................................... 27-16
Corrosion Monitoring ............................................................................. 27-28
Cut-In Connection to Existing Water Mains .................................................... 27-26
Disinfection ........................................................................................ 27-20
General ............................................................................................... 27-1
Laying ................................................................................................. 27-5
Payment ............................................................................................ 27-36
i - 14
Pipe ................................................................................................... 27-1
Placing Locating Wire with Distribution Mains ................................................ 27-10
Pressure Testing ................................................................................... 27-25
Repaving of Trenches ............................................................................. 27-17
Services ............................................................................................. 27-19
Taps to New and Existing Mains ................................................................. 27-19
Thrust Blocking and Restrained Joints ......................................................... 27-10
Trenching ............................................................................................ 27-2
Valve Boxes, Setting, Adjusting and Locating................................................. 27-27
Water Pipe Distribution (12 inch diameter & smaller) ......................................... 10-18
Water Pipe Transmission (greater than 12 inch diameter) .................................... 10-21
Water Quality Control
Enforcement ......................................................................................... 16-6
Erosion, Sediment, and Pollution Control ....................................................... 16-3
Ground Water Discharges .......................................................................... 16-1
Water Quality Control ....................................................................... 16-1,16-2
Water Service Connection Materials ................................................................ 10-40
Water Transmission, Appurtenances ................................................................ 10-35
Water Used in Construction ............................................................................ 15-1
Work ........................................................................................................ 1-5
Working Day
Definition of .......................................................................................... 1-6
Saturday, Sunday, Holiday, and Night Work ..................................................... 7-2
Work Schedule and Adequate Resources .............................................................. 7-1
Work Under Unfavorable Weather and Other Adverse Conditions ................................ 7-2